Queensferry Crossing opens £245m below budget

Aaron Morby 7 years ago
Share

The £1.35bn Queensferry Crossing over the Forth has officially opened to traffic today.

2.7km bridge will be formally opened by the Queen on Monday, 53 years to the day after she opened its predecessor, the Forth road bridge. Pic courtesy of Ramboll
2.7km bridge will be formally opened by the Queen on Monday, 53 years to the day after she opened its predecessor, the Forth road bridge. Pic courtesy of Ramboll

Despite severe weather hampering the timetable for delivery, the project was hailed by the Scottish Government for coming in £245m under its spending budget.

Joint venture builder Dragados, Hochtief, American Bridge International and Galliford Try have had to battle against harsh weather condition seeing the completion date pushed back twice and the bridge opening eight months later than originally targeted six years ago.

At the time the consortium secured the design and build job with a £790m bid, significantly lower that the initial estimated cost of somewhere between £0.9bn and £1.2bn.

Because this bridge contract ran until June 2017, the project is technically just 10 weeks late.

The time overrun has had no impact on the overall budget as the joint venture contractors are responsible for all costs associated with the over-run.

The bridge has been a catalyst for employment and business opportunities since work began.

Over 15,000 people have been inducted to work on the construction site since 2011, clocking up over 18 million hours of work in the process.

World class & world record breaking

Queensferry Crossing

  • The structure spans 1.7 miles (2.7km) making it the longest three-tower, cable-stayed bridge in the world.
  • The biggest infrastructure project in Scotland for a generation.
  • New world record in 2013 when we achieved the largest continuous underwater concrete pour. The 24-hour non-stop operation successfully poured 16,869 cubic metres of concrete into the water-filled south tower caisson.
  • Prior to the completion of the final closure sections on the deck, the balanced cantilevers which extend 322m north and south from the central tower, i.e. 644m tip to tip, were recorded by Guinness as the longest ever.
  • Highest bridge towers in the UK. (210m)
  • Longest free-standing balanced cantilever in the world. (Centre Tower deck fan was 644m wide prior to being connected to rest of structure)

Project Director David Climie said: ” It’s been a real roller coaster of emotions but the over-riding emotion at the moment is one of pride.

“Until you’ve actually been out on the bridge during severe winds it’s hard to appreciate the task at hand of delivering such a complex project.

“Experts from across the globe have marvelled at this achievement and so it’s nice to think there will be some recognition at home for the workforce this week too.”

Economy Secretary Keith Brown, said:  “To think that the crossing has been completed six years from the date construction started and ten years since Parliament approved legislation is a remarkable achievement for a project of this scale and complexity.

“The challenges of this location have been well-documented and the real heroes are those who have braved the elements in sometimes horrendous conditions to finish the job.

“This project has released £245m of savings back into the Scottish Budget since construction began. Quite often we see and hear of projects running significantly over budget, so I believe we should be proud of this achievement and take confidence going forward.

“Of course these savings are in addition to those achieved during at contract procurement which reduced the forecast by £512m from the outset.”

The bridge features pioneering new windshielding, which should almost entirely eliminate the need for closures during the frequent periods of high winds in the Forth estuary.

Latest news

Carpenter killed by falling timber frame panels

Court fines specialist contractor £8,000 after site tragedy
2 days ago

Road sweeper specialist files administration notice

Go Plant lodges court notice
3 days ago

Anglian Homes rides in to finish crashed Everest contracts

Rival doubled glazed window specialist commits to complete orders
3 days ago

Final work starts to connect super sewer to London system

End in sight with 1.5m thick concrete wall to be demolished to link-up to Lee Tunnel sewer system
3 days ago

Legal challenge launched against £1.5bn A66 dualling

Balfour Beatty, Kier and Keltbray must now await outcome of court challenge
3 days ago

John F Hunt wins 24-storey Battersea tower

Specialist to carry-out demolition, enabling works and RC frame construction
3 days ago

William Hare wins steelwork on £500m Broadgate towers

Specialist to work on 2 Finsbury Avenue with McAlpine
3 days ago

McAlpine appoints MD to grow ventures business

Owain Thomas will build on private rental and healthcare development successes
3 days ago

BAM Co-op Live Arena opening delayed yet again

Another gig cancelled last night amid last minute safety concerns
4 days ago

National Grid unveils winners for £9bn network upgrade

New 'enterprise model' to deliver infrastructure schemes quicker and cheaper
4 days ago

Turkish insulation panel maker to build £45m UK factory

Assan Panel to open first UK plant at Freeport East
4 days ago

Expanding consultant Stantec swoops for Hydrock

Stantec UK business expands by a third as 950 staff join from Bristol-based engineer
4 days ago

Contractors wanted for £800m highways deal

Bids invited for Eastern Highways Alliance Framework 4
4 days ago

Galliford Try names group head of infrastructure

David Lowery promoted to Divisional Managing Director – Infrastructure.
4 days ago

Chigwell Group looks at stock market listing

Essex contractor registers as Public Limited Company
5 days ago

A57 Mottram Bypass clears final legal challenge

Balfour Beatty to get go-ahead to start shortly
5 days ago

100 jobs axed as Geoffrey Osborne confirms administration

Chairman Andrew Osborne calls it a 'sad day' as board loses fight for survival
5 days ago

Midgard set for Notting Hill office tower overhaul

Landmark project edges towards final approval after 10-year planning saga
5 days ago

Cumbrian civils firm clinches £40m Sellafield contract

Civils specialist Stobbarts will support McAlpine on groundworks and concrete
5 days ago

Designers named for London 2000-bed student rooms job

Bouygues will build £400m London School of Economics student scheme next to Tate Modern
5 days ago

£117m-turnover contractor files administration notice

ARJ Construction lodges court notice
6 days ago

£1bn London Blackfriars tower blocks approved

Trio of buildings rising to 45, 40 and 22 storeys approved by Southwark Council
6 days ago

Council decides to end Balfour deal after 13 years

Contractor has been maintaining roads across Herefordshire since 2013
6 days ago

Six civils clients to switch to low carbon concrete and steel

National Highways, Northumbrian Water and Sellafield sign fresh decarbonising pledge
6 days ago

Fortem extends homes repair deal across Birmingham

Willmott Dixon owned firm adds another two years to deal worth £170m
6 days ago

Kier wins £118m civil service Darlington hub

Work is expected to start towards the end of this year
6 days ago

Green light for 34-storey Digbeth apartments tower

480 flats will be delivered for Clarion housing association
6 days ago

LHC starts race for major retrofit and decarb framework

Hunt starts for firms to help with 6.1m social homes upgrade target
7 days ago

Windows giant Everest crashes into administration

Around 350 jobs at risk while hunt starts for a buyer to salvage business
7 days ago

Green light for £500m Newcastle health complex

Mixed use scheme will promote healthy living across all stages of life
7 days ago

Contractor services