£1bn potentially wasted on M25 widening

Aaron Morby 14 years ago
Share

Spending watchdog MPs have slammed the Highways Agency for mishandling the massive M25 widening project.

Public accounts committee MPs believe poor cost estimates and serious delays to plans to widen two stretches of Britain’s busiest motorway may have potentially cost taxpayers an extra £1bn.

Errors in calculations on cost estimates ruled out hard shoulder running as an option at an early stage while financing costs soared by £600m during the nine years it took to sign a deal with contractors.

The agency said the project to widen 35km between junction 16 and junction 23 of the M25, in Buckinghamshire, Hertfordshire and Essex was progressing on time and under budget.

But the agency’s cost estimates for a 30-year, £3.4bn private finance contract for widening the M25 were “poor”, the committee said.

Committee chairman Margaret Hodge MP said: “The Highways Agency’s mishandling of the project to tackle congestion on the M25 could cost the taxpayer an extra £1bn.

“The agency should not have focused just on widening but also have given proper consideration to a much cheaper alternative, hard shoulder running.

“A private finance project intended to transfer risk to the private sector should not have restricted innovation by ruling out this alternative solution.

“The decision to stick with widening was also substantially influenced by a technical error in the agency’s cost estimates. Had the error not been made, HSR would have been shown to be the cheaper option.”

She added: “The costs of the widening project have also been driven up by the nine years it took to conduct the procurement process, from the first commissioning of consultants in 2000 to the signing of the private finance contract in May 2009.

“This delay exposed the project to the credit crisis, resulting in £660m of extra financing costs. And the advisers upon whom the agency spent an excessive £80 million would have benefited from the drawn-out procurement.”

Roads Minister Mike Penning said: “This Government is driven by the need to get value for money for taxpayers so I welcome this report. It is another example of Labour costing taxpayers dearly. I am determined to learn the lessons of the report and we will act on its recommendations.”

Highways Agency chief executive Graham Dalton said: “We note the conclusions reached by the Public Accounts Committee and will act on its recommendations.

“Meanwhile, widening of the M25 in Buckinghamshire, Hertfordshire and Essex is progressing to time and under budget and will be completed before the opening of the Olympic Games in summer 2012.”

Latest news

Thames Water seeks tunnelling contractors

Bidding launched for £242m Teddington drought resilience scheme
2 days ago

UK’s biggest data centre plan breaks cover in Lincolnshire

Plans submitted for £7.6bn AI hyperscale build near Scunthorpe
2 days ago

Government seizes control to fast-track £5bn reservoir plan

Ministers bypass local planners for Lincolnshire and Fens reservoir projects
2 days ago

London council unveils £150m housing estate revamp plan

Hackney gears up to deliver 341 infill homes at De Beauvoir estate
2 days ago

Worker injured during prep work at Persimmon site

Houlihan & Co worker airlifted to hospital
3 days ago

Morrisroe sales slide 15% but group edges back into profit

Turnover hit by safety regulator brake on new high rise resi projects
3 days ago

First platforms installed at HS2 Old Oak Common station

Balfour Beatty VINCI SYSTRA starts station fit-out work: Video
2 days ago

Murphy hikes profit 25% to £84m as orders smash £5.4bn

Order book jumps by nearly two-thirds as firm extends global reach
3 days ago

Cladding specialist EAG files administration notice

Sister firm of failed contractor Alucraft lodges court notice
3 days ago

John Lewis wins battle to build four resi towers above store

Ardmore in frame for landmark £240m Ealing towers plan above new Waitrose
3 days ago

Restructure pays-off for HG Construction

Turnover down but profit up as Building Safety Act delays schemes
3 days ago

Mace confirmed for £100m Natural History Museum job

Construction to start imminently at Thames Valley site
4 days ago

McAleer & Rushe starts £90m Birmingham student rooms job

Selly Oak project will transform derelict supermarket site
3 days ago

20 firms win £577m public estate maintenance framework

Procurement Assist signs off four-year framework for cyclical works
3 days ago

Cubby in talks over rescue restructure after civils job setback

Carlisle contractor hit by Carlisle Southern Link Road losses
4 days ago

Rayner rips up rules to get small builders building

Wildlife habitat rules and building safety levy dropped on sites up to 49 homes
4 days ago

Cladding costs recovery helps Willmott Dixon return to profit

Contractor claimed back £20m from third parties last year
4 days ago

£35m Hereford Western Bypass job to go to tender

Phase 1 tender set for September with design element included
4 days ago

GEG Capital swoops for high-voltage cable contractor APS

Inverness investor continues market expansion with deal for St Helens cable firm
4 days ago

Blackburn seeks bidders for £250m framework

Council starts tender process for major eight-year deal
4 days ago

House builders to face fines for dragging feet on site starts

New powers will let councils penalise slow developers and reclaim stalled plots
5 days ago

HS2 investigation into labour supply pay rates

Probe follows claims that self-employed workers were charged out at PAYE rates
5 days ago

Rydon narrows losses as £27m spent on fire safety repairs

Post-Grenfell work provisions increased to £19m
5 days ago

McLaren lands Boxing Academy school

Contractor starts work on East London site
5 days ago

Firms wanted for £1.5bn green housing retrofit deal

Procure Plus opens bidding for low-carbon housing upgrades framework
5 days ago

Waterloo Station revamp plan advances with new regeneration pact

15-year improvement scheme back on track with new partnership deal
5 days ago

Groundworks firm Corbyn goes under

£33m-turnover specialist now in hands of administrators
1 week ago

Home office says sorry to FP McCann after site raid

Precast concrete contractor wins damages over "entirely erroneous and unfounded allegation"
1 week ago

Race on for £60m London Gateway container yard job

Civils and M&E job up for grabs at Berth 5
1 week ago

How Construction Enquirer can boost your business

Promote your business to a vast industry audience
1 week ago

Contractor services