Power station tunnel collapse could cost £30m

Grant Prior 14 years ago
Share

Scottish and Southern Energy is considering a damages claim of up to £30m after a tunnel collapse forced the closure of the new hydroelectric plant at Glendoe.

Hochtief was main contractor on the £150m Glendoe power station at Loch Ness.

A tunnel collapse last August forced the site to close after only eight months in operation.

The cost of lost power production has been estimated by experts at around £15m while the repair bill has been estimated at more than £10m.

The plant is not expected to reopen until next summer. The repair job is being carried out by BAM Nuttall and involves the construction of two new tunnels to divert water around the blockage

A spokeswoman at SSE told the Sunday Herald that the two sides were in dispute on the terms of the contract, which stipulates that Hochtief would fix any faults arising in the first two years.

SSE decided not to appoint Hochtief for the repair work.

The spokeswoman said: “The closure was a huge disappointment for us but BAM Nuttall is going to get it sorted. We will sort out the contractual issues with Hochtief once it is up and running.”

A spokesman for Hochtief said: “In August 2009, eight months after operations started, unforeseeable rockfall occurred. Our client has started an investigation programme and is still examining the problem at the moment to find a suitable and sustainable solution.

“We have made suggestions for rehabilitation measures considering different scenarios. As long as investigations are in progress we unfortunately cannot talk about further details.”

SSE’s annual results document, published earlier this month, said: “In August 2009, SSE identified a blockage caused by a fall of rock near the top of the tunnel carrying water from the reservoir to the power station at the 100MW Glendoe hydro electric scheme, thus stopping operations at the station.

“The repair will require the construction of two new tunnels: one around 900 metres, to divert water around the blockage; and a second, shorter, access tunnel. The tunnelling work will be carried out using the drill and blast method. BAM Nuttall has been retained as the contractor for this work, which is under way.

“Nevertheless, the extent of the repair work is such that electricity generation is unlikely to resume before the summer of 2011.”

Latest news

Carpenter killed by falling timber frame panels

Court fines specialist contractor £8,000 after site tragedy
16 hours ago

Road sweeper specialist files administration notice

Go Plant lodges court notice
22 hours ago

Anglian Homes rides in to finish crashed Everest contracts

Rival doubled glazed window specialist commits to complete orders
21 hours ago

Final work starts to connect super sewer to London system

End in sight with 1.5m thick concrete wall to be demolished to link-up to Lee Tunnel sewer system
22 hours ago

Legal challenge launched against £1.5bn A66 dualling

Balfour Beatty, Kier and Keltbray must now await outcome of court challenge
22 hours ago

John F Hunt wins 24-storey Battersea tower

Specialist to carry-out demolition, enabling works and RC frame construction
2 days ago

William Hare wins steelwork on £500m Broadgate towers

Specialist to work on 2 Finsbury Avenue with McAlpine
2 days ago

McAlpine appoints MD to grow ventures business

Owain Thomas will build on private rental and healthcare development successes
2 days ago

BAM Co-op Live Arena opening delayed yet again

Another gig cancelled last night amid last minute safety concerns
2 days ago

National Grid unveils winners for £9bn network upgrade

New 'enterprise model' to deliver infrastructure schemes quicker and cheaper
3 days ago

Turkish insulation panel maker to build £45m UK factory

Assan Panel to open first UK plant at Freeport East
2 days ago

Expanding consultant Stantec swoops for Hydrock

Stantec UK business expands by a third as 950 staff join from Bristol-based engineer
3 days ago

Contractors wanted for £800m highways deal

Bids invited for Eastern Highways Alliance Framework 4
2 days ago

Galliford Try names group head of infrastructure

David Lowery promoted to Divisional Managing Director – Infrastructure.
2 days ago

Chigwell Group looks at stock market listing

Essex contractor registers as Public Limited Company
3 days ago

A57 Mottram Bypass clears final legal challenge

Balfour Beatty to get go-ahead to start shortly
3 days ago

100 jobs axed as Geoffrey Osborne confirms administration

Chairman Andrew Osborne calls it a 'sad day' as board loses fight for survival
4 days ago

Midgard set for Notting Hill office tower overhaul

Landmark project edges towards final approval after 10-year planning saga
3 days ago

Cumbrian civils firm clinches £40m Sellafield contract

Civils specialist Stobbarts will support McAlpine on groundworks and concrete
3 days ago

Designers named for London 2000-bed student rooms job

Bouygues will build £400m London School of Economics student scheme next to Tate Modern
3 days ago

£117m-turnover contractor files administration notice

ARJ Construction lodges court notice
4 days ago

£1bn London Blackfriars tower blocks approved

Trio of buildings rising to 45, 40 and 22 storeys approved by Southwark Council
4 days ago

Council decides to end Balfour deal after 13 years

Contractor has been maintaining roads across Herefordshire since 2013
4 days ago

Six civils clients to switch to low carbon concrete and steel

National Highways, Northumbrian Water and Sellafield sign fresh decarbonising pledge
5 days ago

Fortem extends homes repair deal across Birmingham

Willmott Dixon owned firm adds another two years to deal worth £170m
4 days ago

Kier wins £118m civil service Darlington hub

Work is expected to start towards the end of this year
5 days ago

Green light for 34-storey Digbeth apartments tower

480 flats will be delivered for Clarion housing association
4 days ago

LHC starts race for major retrofit and decarb framework

Hunt starts for firms to help with 6.1m social homes upgrade target
5 days ago

Windows giant Everest crashes into administration

Around 350 jobs at risk while hunt starts for a buyer to salvage business
5 days ago

Green light for £500m Newcastle health complex

Mixed use scheme will promote healthy living across all stages of life
5 days ago

Contractor services