Network Rail’s £35bn CP6 spending plan rubber stamped

Aaron Morby 7 years ago
Share

The Office of Rail and Road has approved Network Rail’s plan to spend £35bn making Britain’s railways more reliable and focused on passengers’ needs over the five years from April 2019.

Spending plan approved after regulator demanded more focus on track renewal
Spending plan approved after regulator demanded more focus on track renewal

The spending split will be £31bn for England and Wales and £4bn in Scotland.

The regulator has now approved £24.3bn to be spent in Great Britain on maintaining (£7.7bn) and renewing (£16.6bn) the existing railway, with renewal work seeing a 17% increase from the £14.2bn in CP5.

Renewal spend has been lifted after the ORR challenged Network Rail to make more progress towards long-term asset sustainability.

CP5/CP6 spending plans £m (17/18 prices)
England and Wales Scotland
CP5 CP6 CP5 CP6
Operations £2,607m £3,186m £235m £239m
Support £1,768m £2,314m £219m £295m
Maintenance £6,040m £6,977m £121m £715m
Renewals £12,535m £14,581m £1,683m £2,061m

For both passengers and freight operators, this will help cut delays caused by infrastructure failures, such as track defects.

The ORR has also confirmed Network Rail’s plans for a significant funding and resource boost for its timetabling and planning functions, with forecast spend almost doubling from around £145m in CP5 to over £270m in CP6.

This part of Network Rail can now employ around 100 new staff from the current total of around 700.

The five-year plans will see Network Rail become much more locally focused, with each of its eight geographic routes having its own budget, delivery plans and scorecards.

England & Wales geographic route spend, total CP6 (£m)
Region Operations & Maintenance Renewals Other Total
Anglia 1,185m 1,588m 1,054m 3,826m
LNEEM 2,624m 3,322m 1,985m 7,931m
LNW 3,411m 3,203m 2,109m 8,724m
Southeast 2,018m 2,346m 1,689m 6,052m
Wales 678m 957m 349m 1,984m
Wessex 1,030m 1,455m 964m 3,449m
Western 1,286m 1,627m 933m 3,846m

In addition, ORR has strengthened local routes’ ability to buy goods and services they need locally rather than centrally, where it offers better value for money.

This is part of a shift in approach to give more responsibility to Network Rail’s routes, which are best placed to deliver for local passengers and freight users.

 

Latest news

Six guilty of £2m bribery over Devon housing site deals

Corrupt building bosses and E.ON project chief and QS sentenced
3 days ago

1,650 former ISG staff launch legal claims

Redundancy Payment Service facing payout of more than £9m
3 days ago

Plans lodged for £1bn cancer research centre in Sutton

London Cancer Hub will deliver around 1m sq ft of lab and research space
2 days ago

London Met Uni seeks firm for £284m estate revamp

Contractor wanted to deliver capital works and FM
2 days ago

Delayed £2bn estate rebuild back on as Berkeley signs deal

Birmingham council development agreement paves way for 2028 Ladywood start
3 days ago

Tilbury Douglas boosts margin to 2.1% as profits double

Firm targets 3.5% margin by 2029 under new business plan
3 days ago

Subbies battle for fastest bricklayer title

Winchmore management team go back on the tools
3 days ago

Green light for revised McLaren Reading revamp

Mixed-use plans to transform Broad Street Mall site
2 days ago

Three arrested in Blu-3 and Mace bribery probe

Serious fraud office swoops over alleged £3m bribes to former Mace associates
4 days ago

Scotland’s most complex A9 dualling job heads to market

Market testing starts for £205m Pitlochry to Killiecrankie 6.4km upgrade
4 days ago

Unite signs £390m student beds JV with Manchester Met

Construction at Cambridge Halls site to start next year
3 days ago

Turkish contractor Limak to build new Luton Town stadium

Construction to start this summer on 25,000-seater venue
4 days ago

Kitchen fitter crushed to death by concrete blocks

House builder goes into liquidation before court case
3 days ago

Mears clinches £230m renewal for key Milton Keynes housing deal

Housing upkeep contractor achieves 100% renewal rate in bust rebid period
3 days ago

Murphy on board at new £32m rail station

Construction to start next year at Golborne station
4 days ago

HS2 engineers finish UK’s heaviest bridge slide early

A46 Kenilworth Bypass reopens 30 hours earlier than planned
4 days ago

Bowmer + Kirkland to build £190m Oxford science scheme

Work to start at end of next month on 180,000 sq ft Fabrica scheme
4 days ago

New BAM leisure centre pool springs a leak

Contractor investigating "technical issues" delaying new £36m green leisure centre
5 days ago

United Living lands £250m HyNet pipeline deal

Firm wins deal to design and build over 34km of pipework to collect CO2
4 days ago

Hydrogen diggers get green light to use roads

JCB hails historic decision for advance of hydrogen-fuelled plant on sites
4 days ago

Go-ahead for McAleer & Rushe Glasgow student job

£100m funding deal paves way for 591-bed student tower
4 days ago

Fly-tippers to get their vehicles crushed

Drones will be used to identify cowboy construction waste operators
4 days ago

Green light for £150m West End office revamp

Shaftesbury Avenue office retrofit retains 75% of original building
5 days ago

Morgan Sindall lands £30m Brunswick Wharf scheme in Bideford

North Devon waterside project will provide 100 flats
5 days ago

Former Keltbray managers jailed after corruption trial

Jail sentences following bribery probe on jobs including Battersea Power Station
6 days ago

Lidl pumps £500m into store and logistics expansion

Discounter plans 40 new stores this year as expansion ramps up
5 days ago

JJ Rhatigan UK profit jumps as turnover tops £150m

Irish contractor's expansion in England gathers pace
5 days ago

Driverless digger to be used on Taylor Woodrow site

Autonomous excavator to work at Manchester Airport after successful trial
5 days ago

MCS Build lands Basingstoke warehouse scheme

Construction starts this month after £26m funding deal
5 days ago

Leeds United unveil stadium revamp design

Club has still to set a timeframe for staged Elland Road upgrade
6 days ago

Contractor services