Don bridge hitches delay Aberdeen bypass opening

Aaron Morby 6 years ago
Share

Scotland’s transport secretary has revealed that the opening of the Aberdeen Western Peripheral Route has been pushed back to at least December.

The already delayed scheme was expected to finally open this autumn but further problems with the River Don crossing involving concrete cladding panels have pushed it back.

The £745m road scheme has already been beset with  delays due to weather, technical problems and the collapse of contractor Carillion.

This saw the opening in the spring put back to autumn.

Transport secretary Michael Matheson told MSPs that engineers were now targeting a December opening, but that no firm date could be given.

He said that problems revealed in May at Balfour Beatty’s new Don crossing section of the scheme were more “extensive” than initially believed.

Matheson has now urged the AWPR contractor to ‘stop deliberating and start acting’ and requested an urgent meeting with the contractors’ board members to seek clarity on the timescales for opening the remaining sections of the AWPR.

He also revealed frustration that talks with Galliford Try to open the Craibstone to Stonehaven and Charleston section, which required a variation to the contract, have not progressed as hoped.

“Earlier this week, I spoke with Peter Truscott, chief executive of Galliford Try,  to receive an update on the progress they were making in discussing this variation with their lenders.

“Despite assurances that they were doing everything possible to open the road at the earliest opportunity, as well as a clear indication from Mr Truscott that they were making the necessary changes to the AWPR contract to open the 31.5km section, I was then disappointed to receive a letter from him which contradicted our discussion.

“It is this kind of inconsistency which is frustrating efforts to progress the opening of this new section. As recently as 12th September, Galliford Try issued a statement to markets to say the AWPR was on target to open in late Autumn 2018 and we had no reason to doubt that assessment.

“I have been urging the contractor to conclude its deliberations for some time. I repeated this to him on Monday and reiterated it again today in writing, It is now time for the contractor to stop deliberating and start acting. It now has to take the necessary steps to open the majority of this road and let the people of the North East enjoy the benefits they have been so patiently anticipating.

“I have therefore asked for unequivocal confirmation that the agreement is being progressed and when it will be concluded.”

 

Latest news

Three arrested in Blu-3 and Mace bribery probe

Serious fraud office swoops over alleged £3m bribes to former Mace associates
9 hours ago

Scotland’s most complex A9 dualling job heads to market

Market testing starts for £205m Pitlochry to Killiecrankie 6.4km upgrade
8 hours ago

Unite signs £390m student beds JV with Manchester Met

Construction at Cambridge Halls site to start next year
24 minutes ago

Turkish contractor Limak to build new Luton Town stadium

Construction to start this summer on 25,000-seater venue
17 hours ago

Kitchen fitter crushed to death by concrete blocks

House builder goes into liquidation before court case
10 minutes ago

Mears clinches £230m renewal for key Milton Keynes housing deal

Housing upkeep contractor achieves 100% renewal rate in bust rebid period
13 seconds ago

Murphy on board at new £32m rail station

Construction to start next year at Golborne station
16 hours ago

HS2 engineers finish UK’s heaviest bridge slide early

A46 Kenilworth Bypass reopens 30 hours earlier than planned
15 hours ago

Bowmer + Kirkland to build £190m Oxford science scheme

Work to start at end of next month on 180,000 sq ft Fabrica scheme
23 hours ago

New BAM leisure centre pool springs a leak

Contractor investigating "technical issues" delaying new £36m green leisure centre
2 days ago

United Living lands £250m HyNet pipeline deal

Firm wins deal to design and build over 34km of pipework to collect CO2
23 hours ago

Hydrogen diggers get green light to use roads

JCB hails historic decision for advance of hydrogen-fuelled plant on sites
24 hours ago

Go-ahead for McAleer & Rushe Glasgow student job

£100m funding deal paves way for 591-bed student tower
24 hours ago

Fly-tippers to get their vehicles crushed

Drones will be used to identify cowboy construction waste operators
24 hours ago

Green light for £150m West End office revamp

Shaftesbury Avenue office retrofit retains 75% of original building
2 days ago

Morgan Sindall lands £20m Brunswick Wharf scheme in Bideford

North Devon waterside project will provide 100 flats
2 days ago

Former Keltbray managers jailed after corruption trial

Jail sentences following bribery probe on jobs including Battersea Power Station
2 days ago

Lidl pumps £500m into store and logistics expansion

Discounter plans 40 new stores this year as expansion ramps up
2 days ago

JJ Rhatigan UK profit jumps as turnover tops £150m

Irish contractor's expansion in England gathers pace
2 days ago

Driverless digger to be used on Taylor Woodrow site

Autonomous excavator to work at Manchester Airport after successful trial
2 days ago

MCS Build lands Basingstoke warehouse scheme

Construction starts this month after £26m funding deal
2 days ago

Leeds United unveil stadium revamp design

Club has still to set a timeframe for staged Elland Road upgrade
2 days ago

Bowmer & Kirkland boosts margins as profits surge to £69m

Revenue nudges up towards £1.3bn in year of expansion
3 days ago

Offshore construction starts on £4bn windfarm

Foundations for first of 95 turbines installed: Watch video
3 days ago

AECOM buys civils consultant Allen Gordon

Global giant acquires Scottish water and energy specialist
3 days ago

Plans in for £1bn Northern Gateway site in Manchester

Plan for 500-acre manufacturing and logistic park advance
3 days ago

RED wins £31m London Shoreditch student digs job

Two extra floors will be added to Willen House scheme
3 days ago

Deconstruct handed £12m Grenfell demolition

Firm maintaining building awarded job without bid race to speed process
3 days ago

Sizewell site workers get made to measure PPE

Bespoke fitting service on offer at new Bryson branch
3 days ago

Comment: Gateway is acting like a barricade

Contractors left banging their heads on an (unbuilt) brick wall
6 days ago

Contractor services