Terry Morgan expects Crossrail problems to cost him HS2 job

Aaron Morby 5 years ago
Share

Acclaimed engineer Sir Terry Morgan is bracing himself to be dismissed from both his Crossrail and HS2 chairman jobs.

Chairman of Crossrail and HS2 expects to hear fate in days
Chairman of Crossrail and HS2 expects to hear fate in days

Sir Terry revealed that he expected to be forced from his HS2 job by Government because of concerns about ballooning costs at Crossrail.

Speaking to the BBC Radio 4 PM programme on Saturday after leaks to the Financial Times about reports of his looming dismissal, he said: “I did get confirmation late yesterday afternoon that that was a leak.

“As far as I’m concerned, I’m expecting that to be confirmed more formally in the next few days.”

Sir Terry went on to claim that he had told London Mayor Sadiq Khan that Crossrail would be delayed more than a month before it was finally announced at the end of August.

He also said train commissioning, which was not the responsibility of Crossrail, was also well behind programme, inferring this too would have caused delays

On his dismissal, he said that he had mixed feelings.

“I do feel a sense of responsibility for contributing to the position on Crossrail. On HS2, I have a lot of experience and knowledge to give to that programme but disappointed that now I will not have the opportunity to do this.”

On Crossrail, he said he remained very disappointed there were so many challenges so late in the programme, particularly on system integration.

“And that’s because there are some tremendously gifted engineers who built what I know will be a fantastic programme,” he added.

Sir Terry challenged accounts of when delays were first reported to the London Mayor, claiming Crossrail red-flagged the need to delay completion from 2018 to 2019 a month before this was revealed to the public.

“There’s been some unfortunate comment about who knew what and when about whether the programme on Crossrail was running late.

“I’m very confident that Crossrail behaved properly. There will be and there are plenty of documents that set out exactly what happened and when.

“And I do hope that these documents will be released soon for others to understand. I don’t understand why all the comments that have been made, have been made as they are, because some of them are just factually not correct.

”Obviously it’s insinuation that says in the detail, although the station build did run a little late, what most people don’t realise is that the rolling stock, the trains, are a contract that is not a Crossrail contract, they’re a Transport for London contract, I’m not responsible for the rolling stock and nor are any of the executive.

“I personally now realise that TfL were advised that this train contract was running 18 months late and had known that for at least eight months and that to me, today, still feels to be the case.

“We still have not got train testing underway.”

TfL maintains that it was not until 29 August that they were told that the opening of central section would be definitely delayed until Autumn 2019.

Latest news

John F Hunt wins 24-storey Battersea tower

Specialist to carry-out demolition, enabling works and RC frame construction
4 hours ago

William Hare wins steelwork on £500m Broadgate towers

Specialist to work on 2 Finsbury Avenue with McAlpine
5 hours ago

McAlpine appoints MD to grow ventures business

Owain Thomas will build on private rental and healthcare development successes
2 hours ago

BAM Co-op Live Arena opening delayed yet again

Another gig cancelled last night amid last minute safety concerns
8 hours ago

National Grid unveils winners for £9bn network upgrade

New 'enterprise model' to deliver infrastructure schemes quicker and cheaper
1 day ago

Turkish insulation panel maker to build £45m UK factory

Assan Panel to open first UK plant at Freeport East
8 hours ago

Expanding consultant Stantec swoops for Hydrock

Stantec UK business expands by a third as 950 staff join from Bristol-based engineer
1 day ago

Contractors wanted for £800m highways deal

Bids invited for Eastern Highways Alliance Framework 4
8 hours ago

Galliford Try names group head of infrastructure

David Lowery promoted to Divisional Managing Director – Infrastructure.
9 hours ago

Chigwell Group looks at stock market listing

Essex contractor registers as Public Limited Company
1 day ago

A57 Mottram Bypass clears final legal challenge

Balfour Beatty to get go-ahead to start shortly
1 day ago

100 jobs axed as Geoffrey Osborne confirms administration

Chairman Andrew Osborne calls it a 'sad day' as board loses fight for survival
2 days ago

Midgard set for Notting Hill office tower overhaul

Landmark project edges towards final approval after 10-year planning saga
1 day ago

Cumbrian civils firm clinches £40m Sellafield contract

Civils specialist Stobbarts will support McAlpine on groundworks and concrete
1 day ago

Designers named for London 2000-bed student rooms job

Bouygues will build £400m London School of Economics student scheme next to Tate Modern
1 day ago

£117m-turnover contractor files administration notice

ARJ Construction lodges court notice
2 days ago

£1bn London Blackfriars tower blocks approved

Trio of buildings rising to 45, 40 and 22 storeys approved by Southwark Council
2 days ago

Council decides to end Balfour deal after 13 years

Contractor has been maintaining roads across Herefordshire since 2013
2 days ago

Six civils clients to switch to low carbon concrete and steel

National Highways, Northumbrian Water and Sellafield sign fresh decarbonising pledge
3 days ago

Fortem extends homes repair deal across Birmingham

Willmott Dixon owned firm adds another two years to deal worth £170m
2 days ago

Kier wins £118m civil service Darlington hub

Work is expected to start towards the end of this year
3 days ago

Green light for 34-storey Digbeth apartments tower

480 flats will be delivered for Clarion housing association
2 days ago

LHC starts race for major retrofit and decarb framework

Hunt starts for firms to help with 6.1m social homes upgrade target
3 days ago

Windows giant Everest crashes into administration

Around 350 jobs at risk while hunt starts for a buyer to salvage business
3 days ago

Green light for £500m Newcastle health complex

Mixed use scheme will promote healthy living across all stages of life
3 days ago

Olympian Homes gets go-ahead for Bristol’s tallest building

Work on student and co-living towers to start this summer
3 days ago

ISG gets nod to start £20m Glamorgan school job

Ysgol y Deri specialist needs school is to built at Cosmeston, near Penarth
3 days ago

Walker Modular lands £5m bathroom pod contract

Specialist to work with Graham and Watkin Jones on major build-to-rent scheme

Banned building boss jailed for fraud

Court hears how disqualified director siphoned off cash from new housing company
3 days ago

Osborne staff start looking for new jobs

"Open to Work" flags appear on LinkedIn profiles
6 days ago

Contractor services