Galliford Try construction hit by more Aberdeen bypass losses

Aaron Morby 6 years ago
Share

Galliford Try has suffered further losses on its delayed Aberdeen Bypass project in Scotland, plunging the construction arm into the red in the first half of its financial year.

Galliford Try chief Peter Truscott says firm has presumed the successful outcome of significant claims on the bypass project
Galliford Try chief Peter Truscott says firm has presumed the successful outcome of significant claims on the bypass project

This morning the contractor reported that it had taken a further £26m hit on the Aberdeen Wester Peripheral Route project.

The latest setback presumes the successful outcome of major claims on the project by the firm.

Work on the troubled £745m  road project is now complete, but has not been accepted for handover because client Transport Scotland is demanding assurances about future maintenance after cracks previously appeared in parts of the road surface.

Chief executive Peter Truscott said: “Our estimated final costs to complete the AWPR contract have increased as a result of higher than anticipated direct costs, and further delay to completion.

“Constructive dialogue with the client on the significant claims in respect of the contract are continuing.

“Our provisioning for the loss on this project reflects our current estimate of the final costs, and is reduced by an estimate of our share of significant claims against the client and others, which are yet to be agreed and concluded.”

He added: “This inherent uncertainty will be resolved only when the project is complete and the claims finally settled.”

The project tarnished a better performance from the construction division in the half year to December.

Truscott said otherwise construction’s performance continued to be encouraging, particularly on newer contracts, reflecting the business’s careful approach to project selection and risk management.

He said: “We continue to prioritise the quality of each opportunity over volume. We are seeing projects deferred as a result of macro uncertainty, but with 96% of revenue secured for the current financial year and 66% secured for the following year the business has confidence in its prospects.”

Across the group pre-tax profit slipped 4% to £54m on revenue down 5% to £1.42bn.

At the housing business Linden Homes revenue slipped 10% to £392m, as the softening market saw average selling prices fall 5%.

Profits fell 5% as a result to£77m.

The partnerships and regeneration arm continued its expansion, enjoying profit up a third to nearly £15m from revenue also up to £285m from £223m in the same period previously.

A strong focus on cash management saw average debt over the six months fall to £126m, down from £203m before.

Latest news

Council backs first Brutalist car park-to-flats scheme

Newcastle-under-Lyme multi-storey car park to be reborn as pioneering homes scheme
1 hour ago

Hinkley Point C hits peak build with 26,000 jobs

3,000 more workers to join as fit-out work ramps up
39 minutes ago

Over 40 firms win Wessex Water M&E minor works deal

Broad sweep of specialists picked for AMP8 programme
1 hour ago

Spencer lands Scottish bridge hat-trick

Steelwork, gantries and bearing upgrades on Kessock, Forth and Tay crossings
16 hours ago

Winners revealed for £1.5bn decarbonisation deal

Fusion21 confirms places for 40 firms: Full list
55 minutes ago

Cladding firm fined £225,000 after fatal fall

Court hears how cherry picker didn't reach all parts of repair job
2 hours ago

Early call-out for Ebbsfleet Garden City infrastructure

Bidders day to set out plan for Ebbsfleet Central commercial scheme
1 hour ago

Completed buildings caught-up in Gateway 2 chaos

Developer distraught after dealing with Building Safety Regulator
1 day ago

Aviva submits plans for 34-storey City office tower

Subject to planning work to start in autumn 2027
1 day ago

Murphy takes 40% stake in Aussie civils contractor

Firm enters Australasian market with stake in Sydney-based contractor Abergeldie
1 day ago

Moat seeks firm for £420m repairs and maintenance deal

15-year deal to upkeep 20,000 south east homes
1 day ago

Lynch takes over hotel for Sizewell plant operators

Hire giant now in the hotel business to guarantee accommodation for workers
1 day ago

Subcontractors wanted across Scotland

Latest Constructionline event in Glasgow: Register now
1 day ago

Six guilty of £2m bribery over Devon housing site deals

Corrupt building bosses and E.ON project chief and QS sentenced
6 days ago

1,650 former ISG staff launch legal claims

Redundancy Payment Service facing payout of more than £9m
6 days ago

Plans lodged for £1bn cancer research centre in Sutton

London Cancer Hub will deliver around 1m sq ft of lab and research space
5 days ago

London Met Uni seeks firm for £284m estate revamp

Contractor wanted to deliver capital works and FM
5 days ago

Delayed £2bn estate rebuild back on as Berkeley signs deal

Birmingham council development agreement paves way for 2028 Ladywood start
6 days ago

Tilbury Douglas boosts margin to 2.1% as profits double

Firm targets 3.5% margin by 2029 under new business plan
6 days ago

Subbies battle for fastest bricklayer title

Winchmore management team go back on the tools
6 days ago

Green light for revised McLaren Reading revamp

Mixed-use plans to transform Broad Street Mall site
5 days ago

Three arrested in Blu-3 and Mace bribery probe

Serious fraud office swoops over alleged £3m bribes to former Mace associates
6 days ago

Scotland’s most complex A9 dualling job heads to market

Market testing starts for £205m Pitlochry to Killiecrankie 6.4km upgrade
6 days ago

Unite signs £390m student beds JV with Manchester Met

Construction at Cambridge Halls site to start next year
6 days ago

Turkish contractor Limak to build new Luton Town stadium

Construction to start this summer on 25,000-seater venue
7 days ago

Kitchen fitter crushed to death by concrete blocks

House builder goes into liquidation before court case
6 days ago

Mears clinches £230m renewal for key Milton Keynes housing deal

Housing upkeep contractor achieves 100% renewal rate in bust rebid period
6 days ago

Murphy on board at new £32m rail station

Construction to start next year at Golborne station
7 days ago

HS2 engineers finish UK’s heaviest bridge slide early

A46 Kenilworth Bypass reopens 30 hours earlier than planned
7 days ago

Bowmer + Kirkland to build £190m Oxford science scheme

Work to start at end of next month on 180,000 sq ft Fabrica scheme
1 week ago

Contractor services