MPs demand to know who is responsible for Crossrail chaos

Grant Prior 6 years ago
Share

Watchdog MPs are demanding details of exactly who is responsible for delays and cost overruns on Crossrail.

A damning report from the Public Accounts Committee has slammed the Department for Transport, Transport for London and Crossrail for not clearly identifying the reasons for busting the budget by £2.8bn.

The committee fears that even more money will be needed to finish the project and its revised opening date of 2020 will not be hit.

It said: “New train services were due to start in December 2018 but have been badly delayed.

“Until a revised opening schedule has been agreed, we are not convinced that new services will start to run in 2020 as now hoped, nor that the additional £2.8 billion of funding provided will be enough.”

The committee is now demanding a letter from the DfT, Crossrail and Transport for London by the end of this month “clearly articulating” who is responsible for the project problems.

Chair Meg Hillier added the letter “must and set out clearly what consequences there have been for well-rewarded officials whose costly failures are paid for by taxpayers.”

The Enquirer has previously reported on handsome performance bonuses paid to project chiefs.

The committee attacked previous managers for ignoring warning signs that the project was in trouble.

Hillier said: “It is clear that the delivery deadline of December 2018 had been unrealistic for some time.

“But the Department for Transport, Transport for London and Crossrail Limited continued to put a positive face on the programme long after mounting evidence should have prompted changes.

“Wishful thinking is no basis for spending public money and there remain serious risks to delivering this programme, with a revised schedule and costings for completing the work still to be agreed.

“It is unacceptable that Parliament and the public still do not know the root causes of the failures that beset this project.

“Nor will we accept the Department and Crossrail Limited’s description of these serious problems as ‘systems failures’.”

Latest news

Bombshell cavity barrier defects wipe out Taylor Wimpey profits

Fresh £222m provision for fire safety failings behind brick facades
15 hours ago

39 firms win £3bn South East schools framework

LCP panel covers new build, retrofit and fire safety upgrade work
1 day ago

Esh boss bullish as profits and prospects rise

North of England contractor looking forward to continued growth
1 day ago

Government sets up Platform4 to build 40,000 homes on rail land

Former Lendlease Development chief Bek Seeley to head Platform4
16 hours ago

Race starts for £858m London highways consultancy deal

Ealing Council is leading the launch of a major new highways and transport consultancy framework
16 hours ago

Bridge parts set sail for £20m Murphy Stockport site

"Dress rehearsal" bridge assembly ahead of three week rail closure
15 hours ago

22 firms win Prosper £500m new build homes framework

Deal designed with input from Believe Housing, Gentoo and Karbon Homes
1 day ago

Civils contractor Galldris sold to staff

£125m turnover firm transitions to Employee Ownership Trust
2 days ago

Fit-out firepower drives Morgan Sindall to record half-year

£390m cash pile supports push on partnerships and frameworks
2 days ago

Grid delays now rival planning as chief threat to project delivery

Turner & Townsend flags urgent need to prioritise electricity connections on projects
2 days ago

Forterra to shut down two divisions

Materials giant exiting Formpave block paving and Bison Bespoke precast businesses
2 days ago

Vistry and Kier team up again for Wokingham homes plan

Third major partnership kicks off first phase of 1,400-home Berkshire plan
2 days ago

Wates preps £200m Middlesbrough regen site

Work begins on landmark Crown Square project with hotel, student flats and homes
3 days ago

BAM Nuttall rail boss to join Balfour

Richard Watts to become Managing Director of UK Rail business
5 days ago

Peel Ports unveils £60m expansion plan for Yarmouth

New Southern Terminal to target big infrastructure and offshore energy schemes
3 days ago

£1bn beach defence mega-framework up for grabs

Environment Agency seeks two marine contractors to protect England’s coastlines
3 days ago

Bovis set for £220m tower job near British Museum

John F Hunt to start demolition work for big West End scheme
3 days ago

Carnell poaches another National Highways director

Maintenance contractor becomes latest private firm to lure public sector chief
3 days ago

Plans go in for Warrington logistics site revamp

Outdated units to be replaced at Hawleys Lane
3 days ago

Morgan Sindall site closed after fatal accident

Tragedy at £90m Mill Yard job in Cambridge
6 days ago

DfE signs off £148m school rebuild trio

B+K and Bouygues land major academy projects across England
6 days ago

Contract race starts for £205m A9 dualling job

Latest deal involves building or upgrading nine bridges
6 days ago

Higgins to turn former care home site into council houses

Construction to start early next year on Buckinghamshire scheme
6 days ago

Green light for £1.7bn Edgware town centre revamp

Ballymore to deliver 3,365 new homes
6 days ago

Work to start on £40m Blackpool Multiversity build

Morgan Sindall to start demolition for five-storey education campus
6 days ago

Bridge faults plunge Severfield into £18m loss

Firm cuts staff by 6% and raises option to sell part of stake in Indian arm
7 days ago

BAM UK Construction back in the black after Co-op woes

Nuttall civils arm powers up profits with margin topping 5%
7 days ago

Mace sells consulting business to Goldman Sachs

Sale gives construction bosses "opportunity to refresh and simplify" operation
1 week ago

Vinci gets green light for £35m St Helens transport hub

New interchange set to anchor wider town centre revamp
7 days ago

National Highways major projects chief to join Skanska

Dean Sporn to become Operations Director at infrastructure business
7 days ago