Crossrail can’t find enough managers to complete project

Grant Prior 6 years ago
Share

Crossrail bosses are struggling to find project managers to complete the delayed scheme.

A damning report from the National Audit Office has revealed that Crossrail currently has 143 unfilled vacancies at its central delivery team “including project delivery teams to work with main contractors to deliver the programme.”

There are also 33 further vacancies across the orgnaisation as it battles to hit a revised opening deadline of between October 2020 and March 2021.

Crossrail scaled down its central management team as the job approached its original December 2018 opening date.

The NAO report said: “In order to be able to manage programme risks and the complex contractual arrangements effectively, Crossrail Ltd needs to rebuild its capability and capacity in a number of disciplines.

“During 2018, Crossrail Ltd reduced the number of staff in its central functions, such as risk management, planning and contract and commercial management, as it pursued its demobilisation plans in accordance with its aim to meet the December 2018 deadline.

“All of these functions are critical to completing the programme efficiently and effectively.

“The company now recognises that it still needs skills and has started to recruit.

“It has hired a head of risk and plans to increase the team from one person to five, and has reinstated its audit and assurance committee, which it disbanded in 2018.

“It has increased the size of the planning team by 15 to 34. It is also re-establishing its external affairs team.

“Crossrail Ltd has, however, struggled to recruit the skills it needs. Its capacity to manage the programme effectively remains a key risk.”

The revelation is among a catalogue of management blunders highlighted in the NAO report which have resulted in the project running two years late and £2.8bn over budget.

It details how Crossrail chiefs lost control of contractors and made a series of operational mistakes in a desperate attempt to hit the doomed original deadline.

The report blames cost increases on:

  • Crossrail Ltd’s delivery and commercial strategy
  • the build-up of delays, dependencies and interfaces between contracts and projects
  • not changing course when there were clear signs that the programme was not on track

The NAO believes major problems were evident on the project as early as 2015 and resulted in changes required to the design and to contractors’ delivery schedules which increased costs on most of the 36 main contracts.

It said: “Between February 2017 and December 2018, for example, the forecast final cost of the contract to install track and key systems in the tunnels increased by 80% from £532 million to £956 million.

“Crossrail Ltd also made decisions that drove unnecessary cost.

“In early 2018, Crossrail Ltd began carrying out train testing and construction activity in alternating time periods, to allow for early sight of potential train and signalling system issues.

“However, this testing was of limited use and took any spare time and space from construction workers on site.

“Crossrail Ltd also reduced the size of its central programme and risk management teams during 2018, in anticipation of the programme reaching completion in December 2018.

“It is currently attempting to rehire these personnel. ”

NAO head Amyas Morse said: “There have been a number of choices made in the course of this project that have clearly damaged public value.”

The extent of cost increases on major contracts laid bare in the report:

Latest news

Breakthrough for HS2 as first Birmingham tunnel section dug

Balfour Beatty VINCI completes 3.5km TBM drive in 652 days drive
7 hours ago

HS2 Curzon Street station redesign approved as timber roof axed

Change to meet stricter fire safety rules and cut maintenance costs
11 hours ago

Care home fire trial collapses

Prosecution withdrawn against four firms including Morgan Sindall Property Services
1 day ago

Leicester rebids £22m station revamp after failed tender race

Council opts for ECI route after receiving one bid for project
11 hours ago

Kier wins East Coast College rebuild job in Great Yarmouth

Work to start this summer for 1,300-student college
12 hours ago

R G Carter wins £28m hospital car park job in King’s Lynn

MSCP paves way for £1.5bn Queen Elizabeth Hospital rebuild in 2027
12 hours ago

London to relax green belt building rules

Sadiq Khan shifts position on planning
12 hours ago

Willmott Dixon wins Great Yarmouth waterfront deal

North Quay 10.5 acres mixed-use scheme to advance
1 day ago

SIG chief quits to join Travis Perkins

Gavin Slark to leave by the end of this year
12 hours ago

Eight take key spots on £250m Prosper framework

Housing and public building upkeep deal for North East awarded
1 day ago

Early call-out for £150m Ebbsfleet Garden City infrastructure

Bidders day to set out plan for Ebbsfleet Central commercial scheme
2 days ago

McLaren storms April contracts league with flurry of wins

Cardiff Bay Arena job headlines a series of big contract wins
1 day ago

Balfour Beatty lifts cash forecast after strong first quarter

Contractor set to hit £1bn average monthly net cash in 2025
2 days ago

Goldman Sachs-owned Adler & Allan buys 180-strong civils outfit

West Country's Glanville Environmental gets new owner
1 day ago

Caddick lands first contract for £200m Skelmersdale revamp

Developer gets green light for masterplan
2 days ago

Van Elle sells HGV fleet to haulage firm

WS Specialist Logistics pays £2.9m to take on fleet and drivers
2 days ago

Buyers more bullish about prospects for year ahead

Residential "resilient" but commercial work a weak spot
2 days ago

Council backs first Brutalist car park-to-flats scheme

Newcastle-under-Lyme multi-storey car park to be reborn as pioneering homes scheme
2 days ago

Hinkley Point C hits peak build with 26,000 jobs

3,000 more workers to join as fit-out work ramps up
2 days ago

Over 40 firms win Wessex Water M&E minor works deal

Broad sweep of specialists picked for AMP8 programme
2 days ago

Spencer lands Scottish bridge hat-trick

Steelwork, gantries and bearing upgrades on Kessock, Forth and Tay crossings
3 days ago

Winners revealed for £1.5bn decarbonisation deal

Fusion21 confirms places for 40 firms: Full list
2 days ago

Cladding firm fined £225,000 after fatal fall

Court hears how cherry picker didn't reach all parts of repair job
3 days ago

Completed buildings caught-up in Gateway 2 chaos

Developer distraught after dealing with Building Safety Regulator
4 days ago

Aviva submits plans for 34-storey City office tower

Subject to planning work to start in autumn 2027
3 days ago

Murphy takes 40% stake in Aussie civils contractor

Firm enters Australasian market with stake in Sydney-based contractor Abergeldie
4 days ago

Moat seeks firm for £420m repairs and maintenance deal

15-year deal to upkeep 20,000 south east homes
3 days ago

Lynch takes over hotel for Sizewell plant operators

Hire giant now in the hotel business to guarantee accommodation for workers
4 days ago

Subcontractors wanted across Scotland

Latest Constructionline event in Glasgow: Register now
3 days ago

Six guilty of £2m bribery over Devon housing site deals

Corrupt building bosses and E.ON project chief and QS sentenced
1 week ago

Contractor services