Plan finalised to fix Liverpool hospital concrete beams

Aaron Morby 6 years ago
Share

Laing O’Rourke has finalised detailed plans to fix major structural problems with cracked concrete beams at the mothballed Royal Liverpool Hospital project.

NHS Trust board hopes to sign off final Royal Liverpool hospital finishing plan next month
NHS Trust board hopes to sign off final Royal Liverpool hospital finishing plan next month

The Royal Liverpool NHS Trust said that with a detailed plan to carry out remedial works in place it was on track to submit a business case next month for extra funding to complete the hospital.

A meeting of the NHS Trust board yesterday was warned that the works would be complex due to the advanced nature of the building and would take time to complete.

The structural problems with existing transfer beams are the biggest challenge facing Laing O’Rourke, which is in place to complete Carillion’s stalled hospital project.

The firm’s plan involves strengthening existing beams and reducing the loads that are causing structural issues.

Board papers also reveal that the Trust is procuring 141 works packages covering everything from structural works to taps.

Laing O’Rourke is set to submit a final programme for the hospital shortly allowing the trust to finalise its business case.

This will go before the Trust board next month before going to NHS Improvement/England for final approval.

More than £3m had to be spent on essential maintenance costs on the new Royal last year.

This included flushing the water system to providing power and heating in order to ensure future safety and maintenance of systems, fixtures and finishes.

The Trust said: “Whilst these costs are significant, the cost of replacing degraded systems could be far higher and funding is in place for this ongoing essential maintenance.”

Latest news

Former Hewlett civils firm fails amid director blame game

£17m turnover CORE Special Projects ceases trading after 10 years
2 hours ago

Problem job sinks Mace construction profits

Consultancy arm now making more money than larger construction division
24 hours ago

Acciona heads May contracts league with water job

Mace displaces Sir Robert McAlpine at the top of the annualised rankings
2 hours ago

Cardo swoops for wall insulation specialist SERS

Building maintenance group continues rapid growth spree with takeover of retrofit expert
2 hours ago

New finance chief at Laing O’Rourke

Accountant Ilze Williamson joins from architecture practice
2 hours ago

United Living acquires civils specialist Glenelly

Latest move in the power infrastructure sector
2 hours ago

Gloom slowly lifting from construction buyers

"Worst phase of spending cutbacks may have passed"
24 hours ago

Over 1,300 finished flats lying empty in Gateway 3 logjam

Final safety sign-off stalls occupation and pushes developers to the brink
1 day ago

Modular specialist Elements Europe falls into administration

Move into main contracting sinks pod specialist
1 day ago

Magrock lands first job with Big Yellow Self Storage

Construction to start this summer on Kentish Town site
21 hours ago

Van Elle hit by BSR delays as £134m revenue falls short

Building Safety Regulator logjam delays major resi piling jobs
1 day ago

ECF seals £1bn deal for Northampton town revamp

Development agreement for 25-acre town centre reboot
1 day ago

Demolition starts revamp of 16 acre Luton site

Construction to start by end of year on major industrial and logistics scheme
1 day ago

Anglian Water ramps up pipeline rollout with fresh 260km deal

More drought-busting pipeline work flows to Strategic Pipeline Alliance firms
1 day ago

Framework winners named on Peel Ports £750m deal

Graham and Mclaughlin & Harvey share major works lot
1 day ago

Reeves pledges £15.6bn for regional transport

Chancellor to unveil big spending package today for Metro mayors
2 days ago

Kier ditches diesel for hydrogen in green major site power trial

Trial shows over 20,000 litres of diesel already saved at Bridgwater Tidal Barrier
2 days ago

Plans unveiled for 1million sq ft commercial scheme

Design & build opportunities available at Scunthorpe site
2 days ago

Bouygues seals £119m deal for twin college builds in Wales

Work starts this month on Barry Waterfront and Cardiff Airport tech hubs
2 days ago

MPs back Sellafield delivery shake-up but costs spiralling to £136bn

Four out of five recent projects now on track, but wider site faces growing risks
2 days ago

Fraudster ordered to pay back £80k to contractors

Office worker embezzled £516,000 from two construction companies
3 days ago

Wates gets start date for Victoria Tower restoration

Work to begin this summer and last to 2031
2 days ago

Kier upgrades margin target as order book holds firm

Contractor eyes 4.5% margin as bid discipline pays off
3 days ago

Willmott Dixon bags hat-trick of leisure centre energy retrofits

£15.8m North Herts Council deal includes replacing boilers for air source heat pumps
3 days ago

Drylining giant takes bold step on accepting design risk

Siniat liability pledge designed to stop risk being pushed down supply chain
3 days ago

Section 106 agreements now taking an average of 16 months

Planning departments cannot cope with workloads leading to more house building delays
3 days ago

Winvic starts £200m Towcester Park logistics scheme

IM Properties presses ahead with 1.1m sq ft Midlands logistics park
4 days ago

Safety regulatory drag takes toll on Getjar turnover

Revenue slumps 42% as firm adapts to slower resi job starts
4 days ago

Erith seals early works for £300m London City Road tower

Demolition to start this summer for landmark Old Street roundabout job
4 days ago

Galliford gets sign-off to start Wigan Galleries job

Fettlers scheme starts with £44m market hall and basement build
4 days ago

Contractor services