Grenfell: 75% of unsafe blocks still to be reclad

Aaron Morby 6 years ago
Share

Two years after the Grenfell disaster three-quarters of high rise buildings identified with unsafe cladding still need to be retrofitted.

Grenfell Campaigners project fire safety warning onto a Manchester block (Credit: Grenfell United)
Grenfell Campaigners project fire safety warning onto a Manchester block (Credit: Grenfell United)

Just 105 private and public buildings over 18m have completed remediation works from the 433 identified to have been fitted by unsafe aluminium cladding.

Slow progress and lack of ambition to make buildings more resistant to fire has been thrown into the spotlight by Grenfell campaigners who have projected warnings on tower blocks in London, Manchester and Newcastle.

Also industry fire protection chiefs have warned that even the Government’s fresh planned changes to building regulations don’t go far enough.

Jonathan O’Neill, managing director, Fire Protection Association, said he wanted to see a total ban on combustible building materials on all high-risk buildings, such as schools, hospitals, nursing homes, blocks of flats – not just those buildings over 18m.

“We also want a ban on single staircases in all tall buildings, because in the event of a fire you need at least one staircase for people to be able to evacuate the building, and a second staircase for the fire and rescue services for entry,” he said.

There is also growing concern about the performance of other cladding materials like high-pressure laminates.

It is estimated that a further 340 high rises are clad with these sort of materials. Last month the Government commissioned the FPA to carry out tests on HPLs.

328 buildings to be remediated (progress)


  • 102 are social sector residential buildings; (81 started)
  • 163 are private sector residential buildings; (17 started)
  • 27 are student accommodation buildings; (4 started)
  • 29 are hotels: (3 started)
  • 7 are publicly owned buildings, all health buildings (2 started)

Also in May, the government committed to fund the remediation of high-rise private sector residential buildings with ACM but funding guidance criteria will not be published until July.

So far the government has placed a ban on combustible materials on new high-rise homes, which came into force on 21 December with a two-month transitional period.

Last week the government published consultation on recommendations set out in the Hackitt Review for a new safety regime for designing and building high-rise homes.

Latest news

Ardmore Construction Ltd falls into administration

Move isolates fire safety claims, leaving main Ardmore group free to grow profitability
2 days ago

Aston Villa gets go-ahead for £100m North Stand expansion

Project to modernise 1897-built ground ahead of EURO 2028
2 days ago

Quartet wins £1.75bn Midlands Rail Hub upgrade deal

VolkerRail, Laing O’Rourke, AtkinsRéalis and Siemens team up on Birmingham upgrade
3 days ago

McLaren confirmed for £250m Cardiff arena

Robertson Property secures planning green light for 16,500-capacity venue
3 days ago

John F Hunt starts work on £150m West End office revamp

Six month strip out deal at 125 Shaftesbury Avenue
2 days ago

Former Skanska vice president to join Galliford Try

Thomas Faulkner to head up specialist services division
2 days ago

Bowmer + Kirkland snaps up office fit-out firm Denton

Acquisition gives £40m turnover interiors specialist firepower to chase bigger jobs
3 days ago

Contractors sought for £667m Welsh Water mega project

Utility tests appetite for design, build and finance for twin water treatment jobs
3 days ago

Worker killed on Mace London site

Fatal accident on major site in Brent
3 days ago

Willmott Dixon veteran takes construction COO role

Former trainee Stewart Brundell promoted after nearly 40 years at the firm
4 days ago

BSR delays dent margins at OHOB despite record sales

Turnover up 18% to £369m as pre-tax profit nudges £22m
3 days ago

Plans go in for 30-storey Preston tower

£40m scheme will be tallest residential building in Lancashire
3 days ago

Former Laing O’Rourke leader to join Skanska

James Davies to oversee key defence and health projects
3 days ago

Green light for £10bn data hub prep works in Northumberland

Enabling works to roll out over 16 months on former Blyth Power Station site
4 days ago

VolkerWessels UK profits jump as rail and marine work surges

Infrastructure contractor posts £48m pre-tax profit and stronger order book
4 days ago

Groundworks boss wins payout over gagging order

Subcontractor raised fears over asbestos on housing sites
4 days ago

B+K to start £50m rebuild of Northumberland school

Cramlington Learning Village redevelopment contract signed off
4 days ago

New Homes Accelerator targets six new major sites

Construction to be sped-up on another 12,000 homes
4 days ago

Network Rail spend down as CP7 shift bites contractors

Firms warn of inflation squeeze and reprofiled workbanks
5 days ago

Wall of six towers planned for North London strip site

Hendon Goods Yard site plan for line of resi blocks rising to 29 storeys
5 days ago

SCF opens door to single stage tenders for first time

Gen-6 Southern Construction Framework to widen scope for smaller jobs
5 days ago

M&J Evans lifts profits as eastward regional push pays off

Groundworks specialist sharpens tender strike rate and grows pipeline to £504m
5 days ago

CHIC confirms 33 winners on £1bn housing framework

Equans, Guildmore, Seddon and Wates land spots on new four-year deal
5 days ago

Trade body joins attack on CITB over funding changes

Fit out specialists describe move as a "kick in the teeth"
5 days ago

Carey demolition cartel claim settled with developer

Legal action withdrawn after both sides agree settlement
1 week ago

Strabag seals financial close for £3bn HARP project

Work to start next year on North West's Haweswater aqueduct upgrade
1 week ago

Civils winners revealed for £12bn National Grid high voltage work

Contractor wins complete £59bn investment programme
1 week ago

Watch giant HS2 bridge move complete ahead of schedule

Video highlights engineering feat in Birmingham
1 week ago

Lee Marley posts record revenue despite project delays

Brickwork contractor weathers hiatus in high-rise starts to deliver fifth year of growth
1 week ago

Latest contract winners in military living revamp

First phase sites allocated under new approach to Single Living Accommodation
1 week ago