Size of construction disputes drops by half

Aaron Morby 5 years ago
Share

The average value of construction disputes in the UK fell by 47% last year as the industry started to make headway with early resolution of problems on contracts.

According to analysis of global disputes, the UK leads the way in dispute resolution, typically with low dispute values and quick resolution times, compared with global averages.

The UK takes the shortest average length of time to solve a dispute – 12.8 months. Although, this is 28% longer than last year and consistent with the global trend, whereby disputes are taking longer on average to resolve.

The analysis by consultant Arcadis shows contractors are now seeking to resolve contractual disputes as they arise rather than letting them build up into large final account rows.

The report uncovered a reduction in the use of adjudications and an increase in negotiation as the preferred method of dispute resolution.

This could be after a Court of Appeal ruling reducing the use of ‘smash ‘n’ grab’ adjudications, said Arcadis, or concerns about the growing cost of the adjudication process and a tendency for significant extensions to the prescribed 28-day statutory period for a decision.

Adrain Bell, partner at legal firm CMS Cameron McKenna Nabarro Olswang, said: “Parties are now generally preferring to try to resolve disputes as they arise contemporaneously during a project and/or to split disputes into more manageable bite-sized chunks.

“It is not a sign, unfortunately, that the UK construction industry is becoming any less contentious.”

He said that the drive to resolve rows earlier was being supported by the drafters of standard form contracts.

“Many of these contracts now contain elaborate provisions to ensure the early notification of claims and regimes that facilitate early discussion of them between the contracting parties,” said Bell.

“They also support rapid recourse to a third party neutral if their intervention is required.”

But with standard contract forms becoming longer and more complex, failure to properly administer the contract is the primary cause of disputes.

Gary Kitt, Head of UK Contract Solutions at Arcadis, said:  “In some cases, it could be argued construction contracts are simply too complex for administrators to understand, and better training for everyone involved would go some way towards avoiding disputes as they arise.

“However, our results show the UK to be a world leader in effective avoidance and mitigation strategies.

“As we continue to transition towards greater use of digital technologies like BIM and 4-, 5- or 6D modelling, we are likely to see an improvement in risk allocation much earlier on in the process. This could help all parties to collaboratively resolve any difficulties before cost and time pressures start to escalate.”

Latest news

LHC starts race for major retrofit and decarb framework

Hunt starts for firms to help with 6.1m social homes upgrade target
2 hours ago

Windows giant Everest crashes into administration

Around 350 jobs at risk while hunt starts for a buyer to salvage business
2 hours ago

Green light for £500m Newcastle health complex

Mixed use scheme will promote healthy living across all stages of life
2 hours ago

Olympian Homes gets go-ahead for Bristol’s tallest building

Work on student and co-living towers to start this summer
1 hour ago

ISG gets nod to start £20m Glamorgan school job

Ysgol y Deri specialist needs school is to built at Cosmeston, near Penarth
1 hour ago

Walker Modular lands £5m bathroom pod contract

Specialist to work with Graham and Watkin Jones on major build-to-rent scheme

Banned building boss jailed for fraud

Court hears how disqualified director siphoned off cash from new housing company
2 hours ago

Osborne staff start looking for new jobs

"Open to Work" flags appear on LinkedIn profiles
3 days ago

Plan rejected for 42-storey tower above historic building

Councillor describes as ludicrous plan to build 300 flats above Georgian mansion
3 days ago

Ventilation deal could hike product prices for contractors

Watchdogs at CMA launch probe after duct firm acquires rival
3 days ago

Tide gets go-ahead for London 412 student flats scheme

Volumetric developer secures planning for West Ealing project
3 days ago

Green light for £75m Friar Gate Goods Yard in Derby

Construction set to start this summer on revamp of historic buildings
3 days ago

Robertson to deliver £45m Newcastle NHS Trust works

Capital works will be focused on Freeman Hospital and the Royal Victoria Infirmary sites
3 days ago

Winners named for £2bn Healthy Homes framework

CHIC reveals line-up of over 40 firms for net zero and building safety works
3 days ago

Plan lodged for tallest skyscraper outside London

Developer Salboy submits plan for 76-storey Manchester resi tower
4 days ago

Curo starts £170m race for new homes framework

Bath housing association plans to build up to 300 homes a year
4 days ago

Gove approves major Cambridge North mixed-use scheme

Government backs controversial scheme of 424 flats and 600,000 sq ft of tech and lab space
4 days ago

Pontins holiday park to house Sizewell C builders

Suffolk holiday park to house 500 nuclear construction workers
4 days ago

Adrian Bloor targets 1,000 homes-a-year

Expansion plans after major investment into challenger house building business HarperCrewe
4 days ago

Housing firm fined £528,000 after cable strike

Maintenance workers given no information on underground services
4 days ago

Berkeley subbies face six weeks without payments

Introduction of new finance software means payment hiatus for suppliers
5 days ago

Pagabo reveals 56 winners of latest £1.6bn retrofit deal

Decarbonisation Solutions Framework launched: Full list of winners
5 days ago

Go-ahead for £100m Liverpool Love Lane flats

500-flat scheme will be built across four blocks in Vauxhall area of city
5 days ago

Unions win HS2 site access battle at Old Oak Common job

Skanska, Costain, Strabag JV now the last denying unions access to HS2 sites
5 days ago

Contractors jack 1,100t viaduct into place in 13-hour operation

158m-long composite deck structure jacked into place 10-hours ahead of schedule
5 days ago

Wates wins former Daily Mail printworks transformation

British Land advances major cultural venue at London’s Canada Water
6 days ago

Mace poaches Ramboll chief to be Head of Engineering

Martin Feakes will develop civil and structural engineering offer at Mace
6 days ago

Subcontractors form alliance for major civils jobs

Trio of specialists join forces to collaborate and offer Tier 1 contractors a turnkey solution
6 days ago

Fear of supply chain failures boosting collaboration

Procurement survey also reveals project bank account use is rising
6 days ago

Wates sets up business to target 160,000 mouldy social homes

Healthy Homes service will be offered to social landlords across England
6 days ago

Contractor services