Hinkley construction costs increase by up to £2.9bn

Grant Prior 5 years ago
Share

The cost of building Hinkley Point C is set to increase by up to £2.9bn.

The view south across the Hinkley Point C Construction Site showing the main excavations and pipework for the cooling water systems of unit 1
The view south across the Hinkley Point C Construction Site showing the main excavations and pipework for the cooling water systems of unit 1

A construction update by client EDF Energy confirmed revised project completion costs of between £21.5bn and £22.5bn – an increase of £1.9bn to £2.9bn on previous estimates.

EDF said the exact increase “depends on the effectiveness of action plans to be delivered in partnership with contractors.”

The client added: “Cost increases reflect challenging ground conditions which made earthworks more expensive than anticipated, revised action plan targets and extra costs needed to implement the completed functional design, which has been adapted for a first-of-a-kind application in the UK context.”

Main contractor the BYLOR joint venture between Laing O’Rourke and Bouygues has successfully delivered the nuclear island “common raft” known as J-0.

Its completion in June was a major milestone which prompted a detailed review of the project’s costs, schedule and organisation.

The review also confirmed that the risk of previously announced delays of 15 months and nine months to the completion of the main Unit 1 and 2 structures had “increased”.

Latest news

Construction recovery rained-off in first quarter

Sharp rise in commercial orders offers hope for Summer recovery
4 hours ago

Skanska tops April contract wins ranking

London office and data centre projects lift Skanska
5 hours ago

Modular builder TopHat managing director departs

Andrew Shepherd leaves Goldman-Sachs backed volumetric business
21 hours ago

Balfour wins major Rolls-Royce Derby campus expansion

Masterplan involving 14 building projects will take eight years to complete
4 hours ago

Graham nets £60m stands revamp at Lord’s

Construction to start this summer at the home of cricket
23 hours ago

Contractors face mental health quiz to win work

Prequalification specialist pushing for mental health questions in assessments
4 hours ago

Building boss banned for covid loan abuse

Latest investigation into £50,000 Bounce Back Loan
4 hours ago

Ready mix concrete giant files administration notice

Mixit Concrete Limited lodges court notice
1 day ago

Dual student towers plan for Birmingham Gun Quarter

Sama Investments goes to public consultation on 50-storey scheme
1 day ago

15 win £3.5bn Eastern Route Partnership railway deal

Amco, BAM, Morgan Sindall and Story among winners on Eastern Routes Partnership
1 day ago

Expanding Caddick Group tops £500m turnover

Construction drives revenue growth and returns to profit
1 day ago

Structure Tone returns to profit

Contractor confident about prospects in London fit out and refurb market
1 day ago

33 firms secure spots on £3.6bn Northumbrian Water framework

Applebridge, Galliford, Esh and Keltbray may
1 day ago

Construction boss in court over dodgy van deals

Suspended jail sentence after court hears how millions in unexplained payments went through Leeds contractor
1 day ago

Development firm fails hitting London building team for £2.6m

Luxury flats builder Ant Yapi was contracted to redevelop Westminster Tower site
2 days ago

Government set to fund £1bn final HS2 London tunnel drive

Final tunnel drive to be taxpayer funded upfront with cash recouped later
2 days ago

Amazon fires up Big-Box market with £500m job

Next generation triple floor super-shed to be built near Northampton
2 days ago

Stricken road sweeper specialist rescued

Parts of hire specialist Go Plant bought out of administration by Sweeptech
2 days ago

Costain highways lead joins Buro Happold

Paula Gough appointed to UK Development Director for Infrastructure
2 days ago

G&H Group lands £20m+ M&E package from JJ Rhatigan

100-strong specialist team to start on West London site next week
2 days ago

Bidding open for £800m professional services deal

Procure Partnerships encourages SMEs to bid with 9 regional lots
2 days ago

Construction buyers see fastest growth for 14 months

Commercial building work leads the way in April
3 days ago

Go Modular Technologies files administration notice

Southampton bespoke volumetric specialist employs around 60 staff
3 days ago

Cladding firm went down owing supply chain £7.7m

Debts revealed at Everton stadium cladding contractor Alucraft Systems Ltd
3 days ago

Rydon dogged by legacy fire safety remediation costs

£19m spent on fire safety remediation work to date
3 days ago

Carpenter killed by falling timber frame panels

Court fines specialist contractor £8,000 after site tragedy
7 days ago

Trio of builders win King’s Award for sustainability

Henry Brothers, Willmott Dixon and ZED Pods recognised for sustainability
3 days ago

Kent police seize huge haul of stolen site tools

Hunt for power drill fitted with tracker busts tool theft ring
3 days ago

Robertson names new Northern construction chiefs

Ian Phillips promoted and Ricky Brown joins from Morgan Sindall
3 days ago

Road sweeper specialist files administration notice

Go Plant lodges court notice
1 week ago

Contractor services