Client and contractor fall out at £12m arts centre

Grant Prior 12 years ago
Share

A war of words has broken out between a contractor and its Scottish client over a £12m arts centre which will open a year late.

Client Shetland Arts issued a statement yesterday expressing its “frustration” and “disappointment” over the latest delays to the Mareel centre being  built by contractor DITT in North Ness.

Work started in May 2009 and was originally due to be completed in spring 2011.

Shetland Arts was working to a revised opening date of May 25 but that is not now expected to be met following a progress report at a site meeting last week.

The organisation said: “The Board of Shetland Arts has concluded that it cannot confirm any dates in relation to the opening of Mareel or subsequent events until DITT Construction Ltd hand over a fully completed building.

“This difficult decision comes after carefully reviewing the information available and taking into account previous multiple assurances of completion dates followed by notification of significant delays.

“There are many rumours circulating regarding reasons for construction delays, including recent claims by DITT Construction Ltd on specific aspects of the construction.

“It is the view of Shetland Arts that it is unprofessional to play out contractual issues within the public arena.

“Such issues should be dealt with either pre or post completion of the contract through due process between Shetland Arts, our professional advisers, and our contractor.”

The statement sparked an immediate response from DITT who claim the delays are down to numerous design changes.

DITT director Peter Tait told the Shetland Times: “Shetland Arts state that they do not wish to play out contractual issues within the public arena, but by their actions today have chosen to do so.

“Whilst a date was given to Shetland Arts regarding a completion date, the arts trust have conveniently chosen to ignore the fact that the date was subject to no further instructions or additional works being instructed by their design team.

“Disappointingly for the progress of the project, since 14th November a number of significant changes have been instructed. Design changes at this stage of a project inevitably impact on the completion date.”

Latest news

100 jobs axed as Geoffrey Osborne confirms administration

Chairman Andrew Osborne calls it a 'sad day' as board loses fight for survival
4 hours ago

£117m-turnover contractor files administration notice

ARJ Construction lodges court notice
10 hours ago

£1bn London Blackfriars tower blocks approved

Trio of buildings rising to 45, 40 and 22 storeys approved by Southwark Council
11 hours ago

Council decides to end Balfour deal after 13 years

Contractor has been maintaining roads across Herefordshire since 2013
11 hours ago

Six civils clients to switch to low carbon concrete and steel

National Highways, Northumbrian Water and Sellafield sign fresh decarbonising pledge
1 day ago

Fortem extends homes repair deal across Birmingham

Willmott Dixon owned firm adds another two years to deal worth £170m
10 hours ago

Kier wins £118m civil service Darlington hub

Work is expected to start towards the end of this year
1 day ago

Green light for 34-storey Digbeth apartments tower

480 flats will be delivered for Clarion housing association
11 hours ago

LHC starts race for major retrofit and decarb framework

Hunt starts for firms to help with 6.1m social homes upgrade target
1 day ago

Windows giant Everest crashes into administration

Around 350 jobs at risk while hunt starts for a buyer to salvage business
1 day ago

Green light for £500m Newcastle health complex

Mixed use scheme will promote healthy living across all stages of life
1 day ago

Olympian Homes gets go-ahead for Bristol’s tallest building

Work on student and co-living towers to start this summer
1 day ago

ISG gets nod to start £20m Glamorgan school job

Ysgol y Deri specialist needs school is to built at Cosmeston, near Penarth
1 day ago

Walker Modular lands £5m bathroom pod contract

Specialist to work with Graham and Watkin Jones on major build-to-rent scheme

Banned building boss jailed for fraud

Court hears how disqualified director siphoned off cash from new housing company
1 day ago

Osborne staff start looking for new jobs

"Open to Work" flags appear on LinkedIn profiles
4 days ago

Plan rejected for 42-storey tower above historic building

Councillor describes as ludicrous plan to build 300 flats above Georgian mansion
4 days ago

Ventilation deal could hike product prices for contractors

Watchdogs at CMA launch probe after duct firm acquires rival
4 days ago

Tide gets go-ahead for London 412 student flats scheme

Volumetric developer secures planning for West Ealing project
4 days ago

Green light for £75m Friar Gate Goods Yard in Derby

Construction set to start this summer on revamp of historic buildings
4 days ago

Robertson to deliver £45m Newcastle NHS Trust works

Capital works will be focused on Freeman Hospital and the Royal Victoria Infirmary sites
4 days ago

Winners named for £2bn Healthy Homes framework

CHIC reveals line-up of over 40 firms for net zero and building safety works
4 days ago

Plan lodged for tallest skyscraper outside London

Developer Salboy submits plan for 76-storey Manchester resi tower
5 days ago

Curo starts £170m race for new homes framework

Bath housing association plans to build up to 300 homes a year
5 days ago

Gove approves major Cambridge North mixed-use scheme

Government backs controversial scheme of 424 flats and 600,000 sq ft of tech and lab space
5 days ago

Pontins holiday park to house Sizewell C builders

Suffolk holiday park to house 500 nuclear construction workers
5 days ago

Adrian Bloor targets 1,000 homes-a-year

Expansion plans after major investment into challenger house building business HarperCrewe
5 days ago

Housing firm fined £528,000 after cable strike

Maintenance workers given no information on underground services
5 days ago

Berkeley subbies face six weeks without payments

Introduction of new finance software means payment hiatus for suppliers
6 days ago

Pagabo reveals 56 winners of latest £1.6bn retrofit deal

Decarbonisation Solutions Framework launched: Full list of winners
6 days ago

Contractor services