NAO raps MoD for starting nuclear building jobs too early

Aaron Morby 5 years ago
Share

The Ministry of Defence has been criticised for its poor management of construction projects needed for Britain’s nuclear weapons programme.

MENSA nuclear warhead assembly facility at AWE's Burghfield site near Reading originally costed at £1.8bn
MENSA nuclear warhead assembly facility at AWE's Burghfield site near Reading originally costed at £1.8bn

According to the government spending watchdog decisions to start construction before final designs were signed off has led to delays of between one and six years, with costs increasing by £1.3bn.

The National Audit Office looked at three Defence Nuclear Estate projects together budgeted at £2.5bn.

  • MENSA: a new nuclear warhead assembly and disassembly facility, valued at £1.8bn, at Burghfield in Reading.
  • Core production capability facilities: upgraded facilities, costing at least £474m, at the Rolls Royce-operated site in Raynesway, Derby
  • Primary build facility: new facilities at the dockyard in Barrow-in-Furness, costing £240m to upgrade aging facilities and support improved submarine construction techniques.

Problems in the earlier and riskier stages of these projects caused delays and cost increases.

It said some of the designs may have been more costly than necessary, mainly as a result of construction starting before the requirements or designs were fully developed, and changes to the project management or commercial approach.

The way that the MoD set up the contracts also meant that it must foot the bill rather than share it with the contractors.

The NAO recognised unique challenges with the projects, including the need to comply with additional nuclear-related regulations, the limited pool of suppliers and the complexity of the designs.

But it said the MoD should have learnt more from the early stages of other nuclear infrastructure projects concluded in the UK and elsewhere.

Gareth Davies, the head of the NAO, said: “While these infrastructure projects are complex, the MoD has encountered similar challenges before in its nuclear work.

“Although it has recently introduced changes to enhance its oversight of the projects and improve its contracts with suppliers, it should have learnt earlier from past mistakes and the experience of others in the nuclear sector.

“Instead, the MoD’s failure to mitigate commercial and delivery risks early on has led to project delays and cost increases, as well as impacting its wider work.”

Similar challenges arose for the MoD in the 1980s and 1990s, as well as in American defence projects and UK civil nuclear projects, such as at Sellafield.

Latest news

Six guilty of £2m bribery over Devon housing site deals

Corrupt building bosses and E.ON project chief and QS sentenced
22 hours ago

1,650 former ISG staff launch legal claims

Redundancy Payment Service facing payout of more than £9m
1 day ago

Plans lodged for £1bn cancer research centre in Sutton

London Cancer Hub will deliver around 1m sq ft of lab and research space
7 hours ago

London Met Uni seeks firm for £284m estate revamp

Contractor wanted to deliver capital works and FM
8 hours ago

Delayed £2bn estate rebuild back on as Berkeley signs deal

Birmingham council development agreement paves way for 2028 Ladywood start
1 day ago

Tilbury Douglas boosts margin to 2.1% as profits double

Firm targets 3.5% margin by 2029 under new business plan
1 day ago

Subbies battle for fastest bricklayer title

Winchmore management team go back on the tools
1 day ago

Green light for revised McLaren Reading revamp

Mixed-use plans to transform Broad Street Mall site
8 hours ago

Three arrested in Blu-3 and Mace bribery probe

Serious fraud office swoops over alleged £3m bribes to former Mace associates
2 days ago

Scotland’s most complex A9 dualling job heads to market

Market testing starts for £205m Pitlochry to Killiecrankie 6.4km upgrade
2 days ago

Unite signs £390m student beds JV with Manchester Met

Construction at Cambridge Halls site to start next year
1 day ago

Turkish contractor Limak to build new Luton Town stadium

Construction to start this summer on 25,000-seater venue
2 days ago

Kitchen fitter crushed to death by concrete blocks

House builder goes into liquidation before court case
1 day ago

Mears clinches £230m renewal for key Milton Keynes housing deal

Housing upkeep contractor achieves 100% renewal rate in bust rebid period
1 day ago

Murphy on board at new £32m rail station

Construction to start next year at Golborne station
2 days ago

HS2 engineers finish UK’s heaviest bridge slide early

A46 Kenilworth Bypass reopens 30 hours earlier than planned
2 days ago

Bowmer + Kirkland to build £190m Oxford science scheme

Work to start at end of next month on 180,000 sq ft Fabrica scheme
2 days ago

New BAM leisure centre pool springs a leak

Contractor investigating "technical issues" delaying new £36m green leisure centre
3 days ago

United Living lands £250m HyNet pipeline deal

Firm wins deal to design and build over 34km of pipework to collect CO2
2 days ago

Hydrogen diggers get green light to use roads

JCB hails historic decision for advance of hydrogen-fuelled plant on sites
2 days ago

Go-ahead for McAleer & Rushe Glasgow student job

£100m funding deal paves way for 591-bed student tower
2 days ago

Fly-tippers to get their vehicles crushed

Drones will be used to identify cowboy construction waste operators
2 days ago

Green light for £150m West End office revamp

Shaftesbury Avenue office retrofit retains 75% of original building
3 days ago

Morgan Sindall lands £30m Brunswick Wharf scheme in Bideford

North Devon waterside project will provide 100 flats
3 days ago

Former Keltbray managers jailed after corruption trial

Jail sentences following bribery probe on jobs including Battersea Power Station
4 days ago

Lidl pumps £500m into store and logistics expansion

Discounter plans 40 new stores this year as expansion ramps up
3 days ago

JJ Rhatigan UK profit jumps as turnover tops £150m

Irish contractor's expansion in England gathers pace
3 days ago

Driverless digger to be used on Taylor Woodrow site

Autonomous excavator to work at Manchester Airport after successful trial
3 days ago

MCS Build lands Basingstoke warehouse scheme

Construction starts this month after £26m funding deal
3 days ago

Leeds United unveil stadium revamp design

Club has still to set a timeframe for staged Elland Road upgrade
4 days ago

Contractor services