NAO raps MoD for starting nuclear building jobs too early

Aaron Morby 6 years ago
Share

The Ministry of Defence has been criticised for its poor management of construction projects needed for Britain’s nuclear weapons programme.

MENSA nuclear warhead assembly facility at AWE's Burghfield site near Reading originally costed at £1.8bn
MENSA nuclear warhead assembly facility at AWE's Burghfield site near Reading originally costed at £1.8bn

According to the government spending watchdog decisions to start construction before final designs were signed off has led to delays of between one and six years, with costs increasing by £1.3bn.

The National Audit Office looked at three Defence Nuclear Estate projects together budgeted at £2.5bn.

  • MENSA: a new nuclear warhead assembly and disassembly facility, valued at £1.8bn, at Burghfield in Reading.
  • Core production capability facilities: upgraded facilities, costing at least £474m, at the Rolls Royce-operated site in Raynesway, Derby
  • Primary build facility: new facilities at the dockyard in Barrow-in-Furness, costing £240m to upgrade aging facilities and support improved submarine construction techniques.

Problems in the earlier and riskier stages of these projects caused delays and cost increases.

It said some of the designs may have been more costly than necessary, mainly as a result of construction starting before the requirements or designs were fully developed, and changes to the project management or commercial approach.

The way that the MoD set up the contracts also meant that it must foot the bill rather than share it with the contractors.

The NAO recognised unique challenges with the projects, including the need to comply with additional nuclear-related regulations, the limited pool of suppliers and the complexity of the designs.

But it said the MoD should have learnt more from the early stages of other nuclear infrastructure projects concluded in the UK and elsewhere.

Gareth Davies, the head of the NAO, said: “While these infrastructure projects are complex, the MoD has encountered similar challenges before in its nuclear work.

“Although it has recently introduced changes to enhance its oversight of the projects and improve its contracts with suppliers, it should have learnt earlier from past mistakes and the experience of others in the nuclear sector.

“Instead, the MoD’s failure to mitigate commercial and delivery risks early on has led to project delays and cost increases, as well as impacting its wider work.”

Similar challenges arose for the MoD in the 1980s and 1990s, as well as in American defence projects and UK civil nuclear projects, such as at Sellafield.

Latest news

Retentions could be banned in late payment crackdown

Government considers abolition of hated system in construction
2 days ago

Heathrow Airport unveils £49bn ‘superhub’ expansion

Airport operator says it is ready to start design and supply chain activity this year
1 day ago

National Grid names contractors for £8bn of substation work

Regional deals will give firms first refusal on work in their area
1 day ago

Keltbray names Ferrovial’s Karl Goose as new CEO

New boss to take over in December as Vince Corrigan retires
1 day ago

Green light for first 880 homes at Manchester Mayfield

Four blocks rising to 28 storeys set to cost around £250m to build
1 day ago

Fit-out trade body hits back at bloated contracts

Dry walling and interiors body backs 500-word contract in fight against legal traps
1 day ago

Arora and Bechtel pitch rival Heathrow expansion plan

New Terminal 6 and runway said to be faster, greener and cheaper option
2 days ago

Major delays hit £4.8bn Levelling Up project programme

Whitehall admits most projects still stuck in design or planning phase
2 days ago

London new home starts slump 59% as safety regime bites

National rise masks capital’s fall amid BSR delays and social housing slowdown
2 days ago

Maidstone seeks builder for £50m flats project

10-storey tower part of council’s Springfield Library redevelopment plans
2 days ago

Former Lambeth council office to become Premier Inn

Developer Whitbread looking for contractor for latest conversion project
2 days ago

Construction to start on UK’s first floating padel courts

Liverpool Waters gets green light for unique leisure complex
2 days ago

Bombshell cavity barrier defects wipe out Taylor Wimpey profits

Fresh £222m provision for fire safety failings behind brick facades
3 days ago

39 firms win £3bn South East schools framework

LCP panel covers new build, retrofit and fire safety upgrade work
4 days ago

Esh boss bullish as profits and prospects rise

North of England contractor looking forward to continued growth
4 days ago

Government sets up Platform4 to build 40,000 homes on rail land

Former Lendlease Development chief Bek Seeley to head Platform4
3 days ago

Race starts for £858m London highways consultancy deal

Ealing Council is leading the launch of a major new highways and transport consultancy framework
3 days ago

Bridge parts set sail for £20m Murphy Stockport site

"Dress rehearsal" bridge assembly ahead of three week rail closure
3 days ago

22 firms win Prosper £500m new build homes framework

Deal designed with input from Believe Housing, Gentoo and Karbon Homes
4 days ago

Civils contractor Galldris sold to staff

£125m turnover firm transitions to Employee Ownership Trust
4 days ago

Fit-out firepower drives Morgan Sindall to record half-year

£390m cash pile supports push on partnerships and frameworks
4 days ago

Grid delays now rival planning as chief threat to project delivery

Turner & Townsend flags urgent need to prioritise electricity connections on projects
4 days ago

Forterra to shut down two divisions

Materials giant exiting Formpave block paving and Bison Bespoke precast businesses
4 days ago

Vistry and Kier team up again for Wokingham homes plan

Third major partnership kicks off first phase of 1,400-home Berkshire plan
5 days ago

Wates preps £200m Middlesbrough regen site

Work begins on landmark Crown Square project with hotel, student flats and homes
5 days ago

BAM Nuttall rail boss to join Balfour

Richard Watts to become Managing Director of UK Rail business
1 week ago

Peel Ports unveils £60m expansion plan for Yarmouth

New Southern Terminal to target big infrastructure and offshore energy schemes
5 days ago

£1bn beach defence mega-framework up for grabs

Environment Agency seeks two marine contractors to protect England’s coastlines
5 days ago

Bovis set for £220m tower job near British Museum

John F Hunt to start demolition work for big West End scheme
5 days ago

Carnell poaches another National Highways director

Maintenance contractor becomes latest private firm to lure public sector chief
5 days ago