NAO raises alarm over cost of finishing Carillion hospitals

Aaron Morby 5 years ago
Share

Spending watchdog the National Audit Office has sounded the alarm about the risk of further significant cost increases finishing Carillion’s two major hospital projects.

Contract to replace cladding at the Royal Liverpool is now out to bid
Contract to replace cladding at the Royal Liverpool is now out to bid

Investigators are particularly concerned about the risks of rectifying the badly-built Royal Liverpool hospital.

An in-depth report into both the Midlands Metropolitan and Royal Liverpool projects blames the disastrous outcomes on Carillion pricing the jobs too low to meet specifications.

On present estimates, both hospitals will cost double the original budgets to build and will complete between three and five years late.

Going forward the report raises concerns about Laing O’Rourke’s remediation and finishing agreement with the local Liverpool NHS Trust because of an absence of contractual incentives to control costs.

At the Midland Metropolitan, the Sandwell Trust has negotiated a ‘target price’ for Balfour Beatty.

The report hopes that prices should not rise on this hospital unless the Trust changes the scope of the project or there are unforeseen problems with Carillion’s work.

Construction of the Royal Liverpool is now expected to cost at least £724m compared with the original £350m budget. This includes the current estimate of £293m for remedial work to the structure and to complete the construction.

The construction of the Midland Metropolitan is now expected to cost at least £663m compared with £350m in the original business case. This includes £315m still to be spent to complete.

The report reveals the background behind the discovery of cracked concrete beams, first highlighted by the Enquirer in a story on the 13 January 2017.

Carillion investigated while work continued during 2017 and found cracks in three beams.

By December 2017, just before Carillion went into liquidation, the hospital was at a late stage of construction, with interior fit-out almost complete.

Carillion told the Trust that the issues with the beams would be fixed by February 2018 and estimated that the build should be complete by mid-April 2018, 13 months late.

The full extent of the building’s problems then started to be unearthed as Arup surveyed the building.

By October 2018, the number of parts of the structure that required significant rectification had increased to about 100.

This required some interior walls, wiring, piping, and heavy machinery and equipment to be stripped out, mainly across three floors of the hospital.

Costs kept soaring as Arup also discovered large parts of the building’s cladding did not conform to the relevant fire regulations.

The cost of fixing the cladding was first put at £5m.

Further work has since revealed that the cost of fixing the cladding will be about 10 times this initial estimate and that there may also be deficiencies in the internal fire protection and the mechanical, electrical and plumbing systems.

Remedial costs soar as extent of building faults uncovered


The cost of maintaining both hospitals has also risen due to changes in the market since the PFI contracts were signed, and the delays have also led to cost increases on other projects.

The use of PFI means that the private sector will end up paying most of the cost increase, and the public sector is only expected to pay 1% more in real terms across both projects than was originally expected.

Latest news

Three arrested in Blu-3 and Mace bribery probe

Serious fraud office swoops over alleged £3m bribes to former Mace associates
3 hours ago

Scotland’s most complex A9 dualling job heads to market

Market testing starts for £205m Pitlochry to Killiecrankie 6.4km upgrade
2 hours ago

Turkish contractor Limak to build new Luton Town stadium

Construction to start this summer on 25,000-seater venue
12 hours ago

Murphy on board at new £32m rail station

Construction to start next year at Golborne station
10 hours ago

HS2 engineers finish UK’s heaviest bridge slide early

A46 Kenilworth Bypass reopens 30 hours earlier than planned
10 hours ago

Bowmer + Kirkland to build £190m Oxford science scheme

Work to start at end of next month on 180,000 sq ft Fabrica scheme
17 hours ago

New BAM leisure centre pool springs a leak

Contractor investigating "technical issues" delaying new £36m green leisure centre
1 day ago

United Living lands £250m HyNet pipeline deal

Firm wins deal to design and build over 34km of pipework to collect CO2
18 hours ago

Hydrogen diggers get green light to use roads

JCB hails historic decision for advance of hydrogen-fuelled plant on sites
18 hours ago

Go-ahead for McAleer & Rushe Glasgow student job

£100m funding deal paves way for 591-bed student tower
18 hours ago

Fly-tippers to get their vehicles crushed

Drones will be used to identify cowboy construction waste operators
18 hours ago

Green light for £150m West End office revamp

Shaftesbury Avenue office retrofit retains 75% of original building
2 days ago

Morgan Sindall lands £20m Brunswick Wharf scheme in Bideford

North Devon waterside project will provide 100 flats
1 day ago

Former Keltbray managers jailed after corruption trial

Jail sentences following bribery probe on jobs including Battersea Power Station
2 days ago

Lidl pumps £500m into store and logistics expansion

Discounter plans 40 new stores this year as expansion ramps up
2 days ago

JJ Rhatigan UK profit jumps as turnover tops £150m

Irish contractor's expansion in England gathers pace
2 days ago

Driverless digger to be used on Taylor Woodrow site

Autonomous excavator to work at Manchester Airport after successful trial
2 days ago

MCS Build lands Basingstoke warehouse scheme

Construction starts this month after £26m funding deal
2 days ago

Leeds United unveil stadium revamp design

Club has still to set a timeframe for staged Elland Road upgrade
2 days ago

Bowmer & Kirkland boosts margins as profits surge to £69m

Revenue nudges up towards £1.3bn in year of expansion
3 days ago

Offshore construction starts on £4bn windfarm

Foundations for first of 95 turbines installed: Watch video
3 days ago

AECOM buys civils consultant Allen Gordon

Global giant acquires Scottish water and energy specialist
3 days ago

Plans in for £1bn Northern Gateway site in Manchester

Plan for 500-acre manufacturing and logistic park advance
3 days ago

RED wins £31m London Shoreditch student digs job

Two extra floors will be added to Willen House scheme
3 days ago

Deconstruct handed £12m Grenfell demolition

Firm maintaining building awarded job without bid race to speed process
3 days ago

Sizewell site workers get made to measure PPE

Bespoke fitting service on offer at new Bryson branch
3 days ago

Comment: Gateway is acting like a barricade

Contractors left banging their heads on an (unbuilt) brick wall
6 days ago

Final phase of £1.5bn Elephant and Castle revamp hits planning

Get Living submits revised plan for 500 homes and 450-bed student block
7 days ago

Ealing backs final phase of £1.3bn estate rebuild

Friary Park estate rebuild in Acton reaches end stage
6 days ago

Green light for scaled-down Nottingham student tower

Glasshouse Street scheme will deliver 247 student rooms
6 days ago

Contractor services