Britain’s biggest road project opens to traffic eight months early

Aaron Morby 5 years ago
Share

The £1.5bn A14 Cambridge to Huntingdon scheme is opening for traffic eight months ahead of schedule.

Building the new road took 14 million construction hours
Building the new road took 14 million construction hours

Essential work on the upgrade has continued throughout the coronavirus outbreak, with new sections of road opened as quickly as possible, to ensure vital goods were able to travel through.

The 21-mile upgrade project has been delivered by joint venture main contractors Balfour Beatty, Costain and Skanska and is being hailed as a landmark for client-led integrated team working.

Yesterday Highways England confirmed the work has largely been completed, which means the permanent roadworks have been removed and the national 70mph speed limit has been restored. The upgraded road was originally planned to open to traffic by December 2020.

Highways England chief executive Jim O’Sullivan said: “Being able to open it more than six months early and on budget shows what the UK construction industry can achieve with an integrated client team, common goals and targets, and a shared vision of success.

“I would like to thank everyone across Highways England and our supply chain for their contribution to this project.”

Work on the project began in November 2016. The project has employed over 14,000 people in total, with up to 2,500 working on site at peak.

Building the new road took 14m construction hours – the equivalent of almost 1,600 years.

A stretch of the 21-mile scheme – a new 12-mile bypass south of Huntingdon – was opened in December 2019.

Further work in the road verges, including completing landscaping as well as cycle, horse riding and pedestrian paths, will continue.

To carry out the remaining work safely, some temporary overnight closures or off-peak daytime lane closures will be needed.

Work to transform the old A14 for local journeys in and around Huntingdon, including taking down the 45-year-old Huntingdon viaduct, is also continuing as planned and should be completed by 2022.

Work began to dismantle the 16,400 tonne A14 Huntingdon Railway Viaduct following the opening of the Huntingdon southern bypass, and more than half a mile of new link roads are being built into the town.

 

Latest news

Hinkley contractors face prosecution over rebar mesh fall

Bouygues and Laing O'Rourke face action brought by the Office for Nuclear Regulation
29 minutes ago

Wates inks £100m deal on first new-design prison houseblocks

HMP Onley expansion leads roll-out of new standardised design
6 hours ago

£122m deal to unlock Newcastle’s last brownfield site

Land remediation funding paves way for 2,500-home Forth Yards neighbourhood
7 hours ago

McLaren lands Heathrow logistics deal

1.6 hectare airport site to be transformed into modern warehouses
8 hours ago

McAlpine veteran to lead T&T’s project management drive

Former Olympic Stadium lead Mike O’Donnell takes lead role with focus on major capital project delivery
8 hours ago

IES snaps up Nexus Power out of administration

Utilities group strengthens expertise in 400kV jointing and offshore markets
8 hours ago

Thames Water tenders £120m water main rehab deal

Company seeks 2–5 contractors for London and South East renewal works
8 hours ago

Lower Thames Crossing to lead green planning reforms

New system to avoid another £100m HS2 bat tunnel
8 hours ago

Mace lands latest 30-storey City of London tower

85 Gracechurch Street near Leadenhall Market to be transformed
1 day ago

Vinci gets go-ahead for £250m Stockport 8 scheme

Contractor to start first phase of 435 net zero homes next year
1 day ago

£80m bid race to convert Oxford Debenhams into labs

Crown Estate advance plan to convert former six storey department store
1 day ago

Bennett steps-in to finish Guinness Covent Garden brewery

Original fit-out contractor Beck Interiors fell into administration
1 day ago

Work-to-rule set to hit Sellafield clean-up

Action by 1,500 construction workers across 34 contractors
1 day ago

Aureos breaks ground on £45m Howden Relief Road

Yorkshire road will pave way for 2,000-home scheme
1 day ago

Oxford United win green light for £150m all-electric stadium

Planners back 16,000-seat Kidlington ground with hotel, plaza and community hub
4 days ago

Demolition record as eight cooling towers come down

Watch Brown & Mason set record at Cottam Power Station
5 days ago

Hitachi Energy named for EGL3 converter station deal

Firm to build major HVDC converter stations in Aberdeenshire and West Norfolk
4 days ago

PAS NW secures landmark £20m civils deal in Lancashire

Groundworks firm wins infrastructure for 429-home Wain Homes scheme
4 days ago

Subcontractors wanted for jobs across the South West

Register now for latest Constructionline event in Bristol
4 days ago

Profits double at Octavius as road and rail work grows

Recent acquisitions add to turnover growth at infrastructure specialist
5 days ago

Quarterly construction output growth masks orders slide

New orders down by over 8% driven by fall in infrastructure and offices
5 days ago

Vinci UK swings back into profit after group restructure

£166m cash injected to strengthen building and facilities operations balance sheets
6 days ago

Staged procurement to make comeback as pricing risk bites

Developers turn to staged deals to control costs on big-ticket commercial jobs
5 days ago

McGee profit halves as project start delays hit

Revenue up 24% but profits fall on higher carry costs
5 days ago

Vistry to deliver 2,300 homes at Rugeley power station site

139-acre brownfield site has already been extensively remediated
5 days ago

Andrew Scott wins role on Swansea’s next big office build

Contractor appointed for detailed design of 800-desk city centre hub.
5 days ago

Knights Brown to start £29m Poole flood wall job

1.5km barrier to protect homes and unlock regeneration plans
5 days ago

Kier lands £16m first ECI job with Southern Water

Design deal covers nitrogen cut and UV upgrade at Hampshire wastewater sites
6 days ago

Watkin Jones seals deal on 200-bed student scheme

Bristol project will involve four brick buildings rising to seven storeys
6 days ago

Severfield brings in new CEO from Laing O’Rourke ranks

Everton Stadium job chief Paul McNerney to take the helm in the autumn
6 days ago