Spending watchdog demands greater HS2 scrutiny

Aaron Morby 5 years ago
Share

Parliament’s spending watchdog has demanded far greater scrutiny of HS2 costs and programme delivery in a damning report that accuses the transport department of hiding details of overspending and hold-ups.

Meg Hillier, the MP who chairs the PAC, says MPs are concerned about how open the Department and HS2 Ltd executives have been in their account of HS2
Meg Hillier, the MP who chairs the PAC, says MPs are concerned about how open the Department and HS2 Ltd executives have been in their account of HS2

The powerful public accounts committee slams the Department for Transport and HS2 for lack of transparency, warning it has undermined public confidence in the programme.

The critical report highlights serious concerns about the early failure to report that the project had gone badly off-course as the budget soared from £56bn to £88bn.

Committee MPs also said they were concerned that several years into the programme, huge uncertainty remained with the design and delivery of Euston station.

The report calls for DfT within six months to set out its plan for Euston, including how it will be delivered and how it will ensure effective working between all stakeholders.

They also questioned whether DfT and HS2 Ltd had the skills and capability they need now or in the future.

“A lack of capability continues to be an issue; HS2 Ltd recently assessed that while it had improved its capabilities in most areas, it still has gaps in key areas such as risk management and assurance, project management and project controls.

“Now that it is bearing more of the risk of cost increases, HS2 Ltd also needs to ensure that it has the right commercial skills to manage its revised contractual arrangements with its main construction contractors,” says the report.

In its recommendations to Government, the Committee is seeking new, formal assurances that DfT and HS2 Ltd have the capability to manage the programme and its supply chain, into construction and through to completion.

Committee chair Meg Hillier MP said: “In the six-monthly reports the Department has now agreed to give us, we want to see an honest, open account, and evidence of learning from past mistakes being applied to bring this project under control, to deliver it within the timeline and budget that have been agreed in justifying the project.”

Committee’s Deputy Chair Sir Geoffrey Clifton-Brown MP said: “This PAC report on HS2 is one of the most critical, in both the transparency of Government and the handling of a project, that I have seen in my nine years in total on the committee.

“The Permanent Secretary appeared before the committee in October 2018 and again in May 2019.

“In March 2019 HS2 Ltd formally told the Department it had breached the terms of the Development Agreement, and would be unable to deliver the programme to cost and schedule – yet the Permanent Secretary did not inform the committee on either appearance that the programme was in trouble.

“This is a serious breach of the department’s duty to Parliament and hence to the public, which as the report says, will undermine confidence.

“Furthermore, the PAC was in the dark about serious cost overruns and was therefore unable to do its duty to inform Parliament that value for money on the project was at risk.

“The cost overruns have been blamed partly on the speed that the hybrid Bill committee for Phase One proceeded with. I was a member of that committee, which lasted for 20 months: this is complete nonsense.”

Latest news

Hinkley contractors face prosecution over rebar mesh fall

Bouygues and Laing O'Rourke face action brought by the Office for Nuclear Regulation
6 hours ago

Farrans to build new £59m Paisley bridge

Work to start soon on transport project for Renfrewshire Council
24 minutes ago

Wates inks £100m deal on first new-design prison houseblocks

HMP Onley expansion leads roll-out of new standardised design
12 hours ago

£122m deal to unlock Newcastle’s last brownfield site

Land remediation funding paves way for 2,500-home Forth Yards neighbourhood
13 hours ago

McLaren lands Heathrow logistics deal

1.6 hectare airport site to be transformed into modern warehouses
14 hours ago

McAlpine veteran to lead T&T’s project management drive

Former Olympic Stadium lead Mike O’Donnell takes lead role with focus on major capital project delivery
14 hours ago

IES snaps up Nexus Power out of administration

Utilities group strengthens expertise in 400kV jointing and offshore markets
14 hours ago

Thames Water tenders £120m water main rehab deal

Company seeks 2–5 contractors for London and South East renewal works
14 hours ago

Lower Thames Crossing to lead green planning reforms

New system to avoid another £100m HS2 bat tunnel
14 hours ago

Mace lands latest 30-storey City of London tower

85 Gracechurch Street near Leadenhall Market to be transformed
2 days ago

Vinci gets go-ahead for £250m Stockport 8 scheme

Contractor to start first phase of 435 net zero homes next year
2 days ago

£80m bid race to convert Oxford Debenhams into labs

Crown Estate advance plan to convert former six storey department store
2 days ago

Bennett steps-in to finish Guinness Covent Garden brewery

Original fit-out contractor Beck Interiors fell into administration
2 days ago

Work-to-rule set to hit Sellafield clean-up

Action by 1,500 construction workers across 34 contractors
2 days ago

Aureos breaks ground on £45m Howden Relief Road

Yorkshire road will pave way for 2,000-home scheme
2 days ago

Oxford United win green light for £150m all-electric stadium

Planners back 16,000-seat Kidlington ground with hotel, plaza and community hub
5 days ago

Demolition record as eight cooling towers come down

Watch Brown & Mason set record at Cottam Power Station
5 days ago

Hitachi Energy named for EGL3 converter station deal

Firm to build major HVDC converter stations in Aberdeenshire and West Norfolk
5 days ago

PAS NW secures landmark £20m civils deal in Lancashire

Groundworks firm wins infrastructure for 429-home Wain Homes scheme
5 days ago

Subcontractors wanted for jobs across the South West

Register now for latest Constructionline event in Bristol
5 days ago

Profits double at Octavius as road and rail work grows

Recent acquisitions add to turnover growth at infrastructure specialist
5 days ago

Quarterly construction output growth masks orders slide

New orders down by over 8% driven by fall in infrastructure and offices
6 days ago

Vinci UK swings back into profit after group restructure

£166m cash injected to strengthen building and facilities operations balance sheets
6 days ago

Staged procurement to make comeback as pricing risk bites

Developers turn to staged deals to control costs on big-ticket commercial jobs
6 days ago

McGee profit halves as project start delays hit

Revenue up 24% but profits fall on higher carry costs
6 days ago

Vistry to deliver 2,300 homes at Rugeley power station site

139-acre brownfield site has already been extensively remediated
6 days ago

Andrew Scott wins role on Swansea’s next big office build

Contractor appointed for detailed design of 800-desk city centre hub.
6 days ago

Knights Brown to start £29m Poole flood wall job

1.5km barrier to protect homes and unlock regeneration plans
6 days ago

Kier lands £16m first ECI job with Southern Water

Design deal covers nitrogen cut and UV upgrade at Hampshire wastewater sites
6 days ago

Watkin Jones seals deal on 200-bed student scheme

Bristol project will involve four brick buildings rising to seven storeys
6 days ago