Willmott Dixon Group Chief Executive Rick Willmott has hailed the “phenomenal team effort” from staff and suppliers during the Covid-19 pandemic.

The contractor only shut three sites during lockdown but is now braced for rising costs and project delays due to new working procedures.

Willmott was speaking after the firm unveiled its latest results for 2019 showing pre-tax profit down to £31.3m from £37.5m last time on turnover of £1.246bn compared to £1.32bn in 2018.

Pre-tax margins dipped slightly to 2.5% from 2.8% and the company ended the year with £93m cash in the bank.

Willmott said:  “Our performance in 2019 has provided a good platform for our company to continue delivering projects for customers during the challenges created by Covid-19.

“It’s been a phenomenal team effort from our people as we have adjusted our business to maintain operations during Covid-19.

“Our people quickly embraced the changes required to adhere to the Construction Leadership Council’s Site Operating Procedures, with projects and processes reconfigured to provide a safe working environment for our people and supply chain partners, whose support has been brilliant over the past few months.

“We now expect all sites to remain open, although Covid-19 related safety measures and availability of materials will mean that output levels will be reduced compared to before the pandemic.

“While this will inevitably impact upon pre-pandemic expectations in terms of timescales and budgets, I really appreciate how supportive our customers are being on this issue.

“While we have a healthy forward order book that stands at over £1bn, it’s inevitable that some projects may be delayed or postponed owing to the current economic situation created by Covid-19.

“I think we need to be realistic that output reductions linked to social distancing measures, coupled with a possible lag in the supply of some materials from overseas, will inevitably have a continued impact on project prices and programme timings in the short to medium term.

“We are working closely with our supply chain partners and customers to mitigate this as much as possible, while ensuring that projects starting this year now take into account the likely Covid effect.”

Latest news

80 energy projects unlocked as Ofgem backs grid expansion

£24bn energy networks deal gets green light from regulator
8 hours ago

Pinewood submits £1bn data centre plan

Studio giant adds green and learning spaces to tech hub blueprint
9 hours ago

Record results after TClarke goes private

Britain's biggest M&E contractor flourishes after de-listing
9 hours ago

Dalkia lands £200m nuclear maintenance deal

1,000 nuclear FM staff to join M&E contractor
9 hours ago

Construction comeback to outpace wider economy

Arcadis forecast fueled by spending review optimism
1 day ago

First steel goes up on giant car battery site

Severfield gets to work on McAlpine Somerset site
1 day ago

Permasteelisa wins cladding deal on Bovis city tower

Facade specialist lands package at 60 Gracechurch Street
9 hours ago

Fox buys recycled asphalt specialist Fisher

Acquisition adds major recycled asphalt capacity in north west
1 day ago

Major Building Safety Regulator shake-up to end tower delays

HSE stripped of control and top fire chiefs brought in to fast-track stalled schemes
1 day ago

Hinkley trio sign Sizewell civils deal

Balfour,Bouygues and Laing O'Rourke form Civil Works Alliance for new power station
1 day ago

£3.9bn data centre plan for Ravenscraig steelworks

Green energy to power massive new steel to silicon AI campus
1 day ago

Breakthrough on HS2’s second longest tunnel

8.4 mile Northolt to Old Oak Common drive completes
1 day ago

Neilcott on fast-track to debt-free employee ownership

£22.5m loan nearly paid down after big profit year
1 day ago

TfL kicks off race for £700m Tube station upgrade

South Kensington and Elephant & Castle top the pipeline list
1 day ago

Corbyn Plant Hire fleet goes under the hammer

Kit to be sold off by sister firm to collapsed groundworks contractor
1 day ago

Government wields procurement stick on late payment

New rules would block slow payers from bidding on big public jobs
4 days ago

Hercules buys power line labour firm for £15.7m

Labour supply specialist snaps up Advantage NRG to tap booming electricity upgrade market
4 days ago

Universal bid to fast-track planning for theme park

Entertainment giant eyes 2026 start at Bedford site
4 days ago

Developer Breck to transform former Ibstock brick factory

Ravenhead works to become 300-home development
4 days ago

SP Energy Networks awards contracts worth £1.4bn

First round of awards under £5.4bn national electricity grid upgrade programme
5 days ago

Travelodge to convert Liverpool Street office building

Office-to-hotel conversion in City of London
4 days ago

Plans lodged for 1m sq ft City of London office

Barbican landmark building will reuse 40% of existing structure
5 days ago

PTSG acquires roofing specialist HD Sharman Group

Premier Technical Services Group expands building maintenance division
4 days ago

Balfour Beatty lands £833m carbon capture power plant job

Work to start later this year on Teesside carbon capture gas-fired power station
5 days ago

Svella agrees deal to save Cubby Construction

Solvent purchase set to save 214 jobs and protect supply chain
5 days ago

J Coffey holds line on margins despite £52m revenue slide

Pre-tax profit down 14% but firm eyes strong pipeline to bounce back
5 days ago

Consultants called up for £2.3bn NHS SBS panel reboot

Market asked for views ahead of next-gen procurement rollout
5 days ago

Hochtief launches new UK data centre division

German business model to be introduced for UK construction
6 days ago

Construction skills body launches with 100,000 worker target

Industry to work closer with Jobcentres to find new talent
5 days ago

Kier lands £42m Midlothian school and community hub

Contractor strengthens presence in Scotland with big education job
5 days ago