HS2 Chiltern tunnel launchpad ready for giant TBMs

Grant Prior 5 years ago
Share

Preparation for the arrival of HS2’s first giant tunnelling machines is now complete with construction of the 17m high headwall and ground reinforcement at what will become the south portal of the 10-mile long Chiltern tunnel.

Main works contractor Align JV – a joint venture formed of Bouygues Travaux Publics, Sir Robert McAlpine, and VolkerFitzpatrick – has spent seven months excavating more than 160,000 m3 of material in order to create a level surface from which the two enormous machines will launch early next year.

Weighing in at 2,000 tonne and stretching for 170m – the two tunnel boring machines (TBMs) are being built by German tunnelling specialists Herrenknecht – and due to arrive at the site, near to the M25, later in the year.

Alongside the excavation, a specialist team of subcontractors including Roadbridge and KV JV – formed from Keller Group plc and VSL International – also constructed a 17m high headwall through which the TBMs will break to begin their three-year long tunnel drive.

In order to reinforce the ground behind the headwall, more than 636 soil nails – some up to 20m long – were driven into the wall and connected to the concrete lining.

The nails, consisting of steel or glass fibre reinforced polymer tendons, were inserted using a specialised drilling rig in a delicate operation which can take up two hours.

This reinforcement is required to hold the ground and the surface of the wall in place as the TBMs begin to break through.

Welcoming the milestone, Mark Clapp, HS2 Ltd’s C1 Senior Project Manager said: “The completion of the headwall and ground reinforcement is a major step towards the start of tunnelling.

“Safety is of course our top priority. The new covid-19 processes and procedures put in place by Align ensured that we were able to keep to schedule while keeping everyone safe – and I’d like to thank the whole team for pulling together during what has been a difficult few months for the whole construction industry.”

Daniel Altier, the Align Project Director added: “The completion of the soil nailing is a very visual example of how we are preparing our South Portal site for the arrival of the TBMs later this year. It is now clear for all to see where the TBMs will start their journey.

“This has been a great team effort by all concerned, considering the challenges caused by Covid-19, including HS2, Align and our colleagues at Roadbridge and the KVJV.”

Align is delivering the C1 portion of HS2 phase 1 which includes the 10 mile long twin bore Chiltern tunnel and the 3.4km Colne Valley Viaduct. The work is being led by an integrated project team based at the site just inside the M25.

Work on site was paused for four days at the start of the coronavirus lockdown in order to deep clean the work site and put in place new hygiene and social distancing procedures in line with government advice and industry best practice.

Once work is complete, the whole construction site will be landscaped with material excavated from the tunnels and trees planted in order to blend it in with the surrounding countryside.

Latest news

80 energy projects unlocked as Ofgem backs grid expansion

£24bn energy networks deal gets green light from regulator
6 hours ago

Pinewood submits £1bn data centre plan

Studio giant adds green and learning spaces to tech hub blueprint
7 hours ago

Record results after TClarke goes private

Britain's biggest M&E contractor flourishes after de-listing
7 hours ago

Dalkia lands £200m nuclear maintenance deal

1,000 nuclear FM staff to join M&E contractor
6 hours ago

Construction comeback to outpace wider economy

Arcadis forecast fueled by spending review optimism
1 day ago

First steel goes up on giant car battery site

Severfield gets to work on McAlpine Somerset site
1 day ago

Permasteelisa wins cladding deal on Bovis city tower

Facade specialist lands package at 60 Gracechurch Street
6 hours ago

Fox buys recycled asphalt specialist Fisher

Acquisition adds major recycled asphalt capacity in north west
24 hours ago

Major Building Safety Regulator shake-up to end tower delays

HSE stripped of control and top fire chiefs brought in to fast-track stalled schemes
1 day ago

Hinkley trio sign Sizewell civils deal

Balfour,Bouygues and Laing O'Rourke form Civil Works Alliance for new power station
1 day ago

£3.9bn data centre plan for Ravenscraig steelworks

Green energy to power massive new steel to silicon AI campus
1 day ago

Breakthrough on HS2’s second longest tunnel

8.4 mile Northolt to Old Oak Common drive completes
1 day ago

Neilcott on fast-track to debt-free employee ownership

£22.5m loan nearly paid down after big profit year
1 day ago

TfL kicks off race for £700m Tube station upgrade

South Kensington and Elephant & Castle top the pipeline list
1 day ago

Corbyn Plant Hire fleet goes under the hammer

Kit to be sold off by sister firm to collapsed groundworks contractor
1 day ago

Government wields procurement stick on late payment

New rules would block slow payers from bidding on big public jobs
4 days ago

Hercules buys power line labour firm for £15.7m

Labour supply specialist snaps up Advantage NRG to tap booming electricity upgrade market
4 days ago

Universal bid to fast-track planning for theme park

Entertainment giant eyes 2026 start at Bedford site
4 days ago

Developer Breck to transform former Ibstock brick factory

Ravenhead works to become 300-home development
4 days ago

SP Energy Networks awards contracts worth £1.4bn

First round of awards under £5.4bn national electricity grid upgrade programme
5 days ago

Travelodge to convert Liverpool Street office building

Office-to-hotel conversion in City of London
4 days ago

Plans lodged for 1m sq ft City of London office

Barbican landmark building will reuse 40% of existing structure
5 days ago

PTSG acquires roofing specialist HD Sharman Group

Premier Technical Services Group expands building maintenance division
4 days ago

Balfour Beatty lands £833m carbon capture power plant job

Work to start later this year on Teesside carbon capture gas-fired power station
5 days ago

Svella agrees deal to save Cubby Construction

Solvent purchase set to save 214 jobs and protect supply chain
5 days ago

J Coffey holds line on margins despite £52m revenue slide

Pre-tax profit down 14% but firm eyes strong pipeline to bounce back
5 days ago

Consultants called up for £2.3bn NHS SBS panel reboot

Market asked for views ahead of next-gen procurement rollout
5 days ago

Hochtief launches new UK data centre division

German business model to be introduced for UK construction
6 days ago

Construction skills body launches with 100,000 worker target

Industry to work closer with Jobcentres to find new talent
5 days ago

Kier lands £42m Midlothian school and community hub

Contractor strengthens presence in Scotland with big education job
5 days ago