London office construction “in state of suspension”

Grant Prior 3 years ago
Share

The pandemic saw construction of new offices in central London drop by half in the six months to September 30.

Deloitte Real Estate’s latest London Office Crane Survey highlighted the seismic impact of Covid-19 on the capital.

Siobhan Godley, partner and head of Deloitte Real Estate, said the market was in a “state of suspension” while developers assess the long-term impact of working remotely on the office market.

Godley said: “As a bellwether of developer sentiment and future office supply in the capital, this crane survey shows a decline in new construction starts to just 2.6 million sq ft across central London.

“This is down significantly on our previous survey, but remains broadly in line with the survey’s long-term average.

“Notably, a higher than average 40% of new construction starts have already been pre-let, indicating less speculative construction.”

Total office space under construction in central London is now 15.1 million sq ft.

This is similar to the level recorded in the previous survey (15.3 million sq ft, the highest since 2002) as developments are now taking longer to complete.

Mike Cracknell, director at Deloitte Real Estate, said: “Our data reveals that 3.3 million sq ft of office construction was not completed as scheduled between April and September and remains under construction.

“Had these projects completed on time, the total volume under construction would be almost a quarter lower.”

The developers’ sentiment survey showed that 57% of respondents said letting conditions were either the same or worse when compared to the end of March this year.

Cracknell added: “Of the developers we surveyed, a clear majority – 85% – pointed to weak tenant demand as the major obstacle to starting any new development.

“Until there is more clarity about occupiers’ office plans, developers will hesitate to embark on new projects, particularly speculative ones.

“Nonetheless, the news about vaccines has already resulted in a re-rating of real estate stocks, and may see both a bigger shift back to the office in the short term, and a strengthening of investor demand in London offices over the medium term.”

This reluctance to embark on new construction, especially new builds, has led to a shift towards major refurbishments.

The survey found that more than two thirds of the new construction starts involved an extensive upgrade of existing office stock across 28 separate projects.

Cracknell said: “By transforming outdated buildings into Covid-safe, high-quality workspaces, developers are looking to upgrade and futureproof their offices in a market where occupational demand is increasingly discerning.”

The City of London, which dominated construction activity in previous surveys, has seen new construction activity fall by 60% to 1.2 million sq ft across 10 schemes.

This compares to 2.8 million sq ft across 16 schemes in the previous survey. Just under half of the City’s new construction starts are available to let suggesting a lower appetite for speculative development.

Latest news

Six civils clients to switch to low carbon concrete and steel

National Highways, Northumbrian Water and Sellafield sign fresh decarbonising pledge
3 hours ago

Kier wins £118m civil service Darlington hub

Work is expected to start towards the end of this year
6 hours ago

LHC starts race for major retrofit and decarb framework

Hunt starts for firms to help with 6.1m social homes upgrade target
11 hours ago

Windows giant Everest crashes into administration

Around 350 jobs at risk while hunt starts for a buyer to salvage business
11 hours ago

Green light for £500m Newcastle health complex

Mixed use scheme will promote healthy living across all stages of life
11 hours ago

Olympian Homes gets go-ahead for Bristol’s tallest building

Work on student and co-living towers to start this summer
10 hours ago

ISG gets nod to start £20m Glamorgan school job

Ysgol y Deri specialist needs school is to built at Cosmeston, near Penarth
10 hours ago

Walker Modular lands £5m bathroom pod contract

Specialist to work with Graham and Watkin Jones on major build-to-rent scheme
11 hours ago
Walker Modular Limited

Banned building boss jailed for fraud

Court hears how disqualified director siphoned off cash from new housing company
11 hours ago

Osborne staff start looking for new jobs

"Open to Work" flags appear on LinkedIn profiles
3 days ago

Plan rejected for 42-storey tower above historic building

Councillor describes as ludicrous plan to build 300 flats above Georgian mansion
3 days ago

Ventilation deal could hike product prices for contractors

Watchdogs at CMA launch probe after duct firm acquires rival
3 days ago

Tide gets go-ahead for London 412 student flats scheme

Volumetric developer secures planning for West Ealing project
3 days ago

Green light for £75m Friar Gate Goods Yard in Derby

Construction set to start this summer on revamp of historic buildings
3 days ago

Robertson to deliver £45m Newcastle NHS Trust works

Capital works will be focused on Freeman Hospital and the Royal Victoria Infirmary sites
3 days ago

Winners named for £2bn Healthy Homes framework

CHIC reveals line-up of over 40 firms for net zero and building safety works
3 days ago

Plan lodged for tallest skyscraper outside London

Developer Salboy submits plan for 76-storey Manchester resi tower
4 days ago

Curo starts £170m race for new homes framework

Bath housing association plans to build up to 300 homes a year
4 days ago

Gove approves major Cambridge North mixed-use scheme

Government backs controversial scheme of 424 flats and 600,000 sq ft of tech and lab space
4 days ago

Pontins holiday park to house Sizewell C builders

Suffolk holiday park to house 500 nuclear construction workers
4 days ago

Adrian Bloor targets 1,000 homes-a-year

Expansion plans after major investment into challenger house building business HarperCrewe
4 days ago

Housing firm fined £528,000 after cable strike

Maintenance workers given no information on underground services
4 days ago

Berkeley subbies face six weeks without payments

Introduction of new finance software means payment hiatus for suppliers
5 days ago

Pagabo reveals 56 winners of latest £1.6bn retrofit deal

Decarbonisation Solutions Framework launched: Full list of winners
5 days ago

Go-ahead for £100m Liverpool Love Lane flats

500-flat scheme will be built across four blocks in Vauxhall area of city
5 days ago

Unions win HS2 site access battle at Old Oak Common job

Skanska, Costain, Strabag JV now the last denying unions access to HS2 sites
5 days ago

Contractors jack 1,100t viaduct into place in 13-hour operation

158m-long composite deck structure jacked into place 10-hours ahead of schedule
5 days ago

Wates wins former Daily Mail printworks transformation

British Land advances major cultural venue at London’s Canada Water
6 days ago

Mace poaches Ramboll chief to be Head of Engineering

Martin Feakes will develop civil and structural engineering offer at Mace
6 days ago

Subcontractors form alliance for major civils jobs

Trio of specialists join forces to collaborate and offer Tier 1 contractors a turnkey solution
6 days ago

Contractor services