Construction work complete at Farringdon Crossrail station

Grant Prior 3 years ago
Share

The Farringdon Elizabeth line station has become the first on the central London section of Crossrail to complete construction.

Crossrail confirmed on Monday that the station is substantially complete and is now 12 weeks away from being ready for handover to Transport for London (TfL).

Work at Farringdon will now focus on the extensive testing and commissioning of systems ahead of the Elizabeth line opening.

Main contractor the Bam, Ferrovial and Kier Joint Venture (BFK JV) can now start demobilising from the site and enables Crossrail to commence the process of handing the station over to TfL.

A reduced BFK JV team will remain at Farringdon until next year to continue to meet their duties as the principal contractor, which include providing care and custody maintenance of the station assets and systems and support the final handover process to TfL.

Paddington is expected to be the next station where construction activity will complete and will then be followed by a number of the central London station sites over the coming months.

Mark Wild, Crossrail Chief Executive, said: “This is an incredibly important landmark for both the team at Farringdon station and for the Crossrail project as a whole.

“We have now reached the end of the construction phase at the first of our central London stations and the start of the testing and safety assurance journey which will enable us to hand over the station to Transport for London and open the Elizabeth line to passengers.

“I am proud of everyone who has worked so hard to get this magnificent new railway station over the line and I know that when it is open to passengers it will become an important and much-loved addition to London’s transport network.”

Jose Antonio Pariente, Project Director, BAM Ferrovial Kier, said: “Being the first of the central London Elizabeth line stations to attain this status is a source of immense pride for the BFK team.

“In addition, having worked on Europe’s largest infrastructure scheme, with all the complexity involved and seeing the positive changes to the industry, as a result of the extraordinary work completed by the integrated delivery team, has been key for all concerned.

“The positive legacy of the Elizabeth line’s construction phase and its benefits will be felt by generations to come.

“I want to take this opportunity to thank all those involved across Crossrail, BFK and in our supply chain, who have shown great strength, commitment and passion at every stage.”

 

Latest news

Carpenter killed by falling timber frame panels

Court fines specialist contractor £8,000 after site tragedy
2 days ago

Road sweeper specialist files administration notice

Go Plant lodges court notice
2 days ago

Anglian Homes rides in to finish crashed Everest contracts

Rival doubled glazed window specialist commits to complete orders
2 days ago

Final work starts to connect super sewer to London system

End in sight with 1.5m thick concrete wall to be demolished to link-up to Lee Tunnel sewer system
2 days ago

Legal challenge launched against £1.5bn A66 dualling

Balfour Beatty, Kier and Keltbray must now await outcome of court challenge
2 days ago

John F Hunt wins 24-storey Battersea tower

Specialist to carry-out demolition, enabling works and RC frame construction
3 days ago

William Hare wins steelwork on £500m Broadgate towers

Specialist to work on 2 Finsbury Avenue with McAlpine
3 days ago

McAlpine appoints MD to grow ventures business

Owain Thomas will build on private rental and healthcare development successes
3 days ago

BAM Co-op Live Arena opening delayed yet again

Another gig cancelled last night amid last minute safety concerns
3 days ago

National Grid unveils winners for £9bn network upgrade

New 'enterprise model' to deliver infrastructure schemes quicker and cheaper
4 days ago

Turkish insulation panel maker to build £45m UK factory

Assan Panel to open first UK plant at Freeport East
3 days ago

Expanding consultant Stantec swoops for Hydrock

Stantec UK business expands by a third as 950 staff join from Bristol-based engineer
4 days ago

Contractors wanted for £800m highways deal

Bids invited for Eastern Highways Alliance Framework 4
3 days ago

Galliford Try names group head of infrastructure

David Lowery promoted to Divisional Managing Director – Infrastructure.
3 days ago

Chigwell Group looks at stock market listing

Essex contractor registers as Public Limited Company
4 days ago

A57 Mottram Bypass clears final legal challenge

Balfour Beatty to get go-ahead to start shortly
4 days ago

100 jobs axed as Geoffrey Osborne confirms administration

Chairman Andrew Osborne calls it a 'sad day' as board loses fight for survival
5 days ago

Midgard set for Notting Hill office tower overhaul

Landmark project edges towards final approval after 10-year planning saga
4 days ago

Cumbrian civils firm clinches £40m Sellafield contract

Civils specialist Stobbarts will support McAlpine on groundworks and concrete
4 days ago

Designers named for London 2000-bed student rooms job

Bouygues will build £400m London School of Economics student scheme next to Tate Modern
4 days ago

£117m-turnover contractor files administration notice

ARJ Construction lodges court notice
5 days ago

£1bn London Blackfriars tower blocks approved

Trio of buildings rising to 45, 40 and 22 storeys approved by Southwark Council
5 days ago

Council decides to end Balfour deal after 13 years

Contractor has been maintaining roads across Herefordshire since 2013
5 days ago

Six civils clients to switch to low carbon concrete and steel

National Highways, Northumbrian Water and Sellafield sign fresh decarbonising pledge
6 days ago

Fortem extends homes repair deal across Birmingham

Willmott Dixon owned firm adds another two years to deal worth £170m
5 days ago

Kier wins £118m civil service Darlington hub

Work is expected to start towards the end of this year
6 days ago

Green light for 34-storey Digbeth apartments tower

480 flats will be delivered for Clarion housing association
5 days ago

LHC starts race for major retrofit and decarb framework

Hunt starts for firms to help with 6.1m social homes upgrade target
6 days ago

Windows giant Everest crashes into administration

Around 350 jobs at risk while hunt starts for a buyer to salvage business
6 days ago

Green light for £500m Newcastle health complex

Mixed use scheme will promote healthy living across all stages of life
6 days ago

Contractor services