HS2 potential construction cost pressures hit £1.2bn

Grant Prior 4 years ago
Share

A slower than expected start to main civils works has created more potential cost pressures of up to £1.2bn at HS2.

Phase one works are budgeted to cost £40.3bn with a government-retained contingency of £4.3bn.

But HS2 minister Andrew Stephenson has revealed further “cost pressures” in his latest six-monthly report on the project to Parliament.

Stephenson said £400m of extra costs are looming “predominately due to slower than expected mobilisation of main works civils contractors, associated with delays to approvals of designs, planning consents, protestor action and some Covid-19 impacts.”

These are on top of previously identified extras of £400m for work at Euston station and £400m more to be spent on enabling works.

Stephenson said the extra money would come from a £5.6bn contingency fund set aside for HS2 phase one.

His report added: “Other pressures will arise as the programme progresses, some of which may crystallise into additional costs that will need to be covered from the contingency within the existing budget, and some of which will be mitigated or avoided.”

HS2 bosses are currently looking at ways of keeping a lid on Euston Station costs including building it in a single construction stage and potential design changes.

So far on phase one around £11bn has been spent to date, including land and property provisions. Approximately £12.6bn has additionally been contracted, with the remaining amount yet to be contracted.

A DfT spokesperson said: “HS2 Phase One remains within its schedule and budget. Delivering a major project on the scale and ambition of HS2 will always be challenging but, as mentioned in today’s Parliamentary Report, current cost pressures are well covered within our existing budget.

“This project is at the heart of our plans to build back better, supporting more than 15,000 jobs and 500 apprenticeships. We are committed to a tight control of costs and HS2 Ltd continues to identify areas across the project where savings and efficiencies can be made.”

Latest news

Six guilty of £2m bribery over Devon housing site deals

Corrupt building bosses and E.ON project chief and QS sentenced
3 days ago

1,650 former ISG staff launch legal claims

Redundancy Payment Service facing payout of more than £9m
3 days ago

Plans lodged for £1bn cancer research centre in Sutton

London Cancer Hub will deliver around 1m sq ft of lab and research space
2 days ago

London Met Uni seeks firm for £284m estate revamp

Contractor wanted to deliver capital works and FM
2 days ago

Delayed £2bn estate rebuild back on as Berkeley signs deal

Birmingham council development agreement paves way for 2028 Ladywood start
3 days ago

Tilbury Douglas boosts margin to 2.1% as profits double

Firm targets 3.5% margin by 2029 under new business plan
3 days ago

Subbies battle for fastest bricklayer title

Winchmore management team go back on the tools
3 days ago

Green light for revised McLaren Reading revamp

Mixed-use plans to transform Broad Street Mall site
2 days ago

Three arrested in Blu-3 and Mace bribery probe

Serious fraud office swoops over alleged £3m bribes to former Mace associates
3 days ago

Scotland’s most complex A9 dualling job heads to market

Market testing starts for £205m Pitlochry to Killiecrankie 6.4km upgrade
3 days ago

Unite signs £390m student beds JV with Manchester Met

Construction at Cambridge Halls site to start next year
3 days ago

Turkish contractor Limak to build new Luton Town stadium

Construction to start this summer on 25,000-seater venue
4 days ago

Kitchen fitter crushed to death by concrete blocks

House builder goes into liquidation before court case
3 days ago

Mears clinches £230m renewal for key Milton Keynes housing deal

Housing upkeep contractor achieves 100% renewal rate in bust rebid period
3 days ago

Murphy on board at new £32m rail station

Construction to start next year at Golborne station
4 days ago

HS2 engineers finish UK’s heaviest bridge slide early

A46 Kenilworth Bypass reopens 30 hours earlier than planned
4 days ago

Bowmer + Kirkland to build £190m Oxford science scheme

Work to start at end of next month on 180,000 sq ft Fabrica scheme
4 days ago

New BAM leisure centre pool springs a leak

Contractor investigating "technical issues" delaying new £36m green leisure centre
5 days ago

United Living lands £250m HyNet pipeline deal

Firm wins deal to design and build over 34km of pipework to collect CO2
4 days ago

Hydrogen diggers get green light to use roads

JCB hails historic decision for advance of hydrogen-fuelled plant on sites
4 days ago

Go-ahead for McAleer & Rushe Glasgow student job

£100m funding deal paves way for 591-bed student tower
4 days ago

Fly-tippers to get their vehicles crushed

Drones will be used to identify cowboy construction waste operators
4 days ago

Green light for £150m West End office revamp

Shaftesbury Avenue office retrofit retains 75% of original building
5 days ago

Morgan Sindall lands £30m Brunswick Wharf scheme in Bideford

North Devon waterside project will provide 100 flats
5 days ago

Former Keltbray managers jailed after corruption trial

Jail sentences following bribery probe on jobs including Battersea Power Station
5 days ago

Lidl pumps £500m into store and logistics expansion

Discounter plans 40 new stores this year as expansion ramps up
5 days ago

JJ Rhatigan UK profit jumps as turnover tops £150m

Irish contractor's expansion in England gathers pace
5 days ago

Driverless digger to be used on Taylor Woodrow site

Autonomous excavator to work at Manchester Airport after successful trial
5 days ago

MCS Build lands Basingstoke warehouse scheme

Construction starts this month after £26m funding deal
5 days ago

Leeds United unveil stadium revamp design

Club has still to set a timeframe for staged Elland Road upgrade
5 days ago

Contractor services