Bristol Uni puts back £300m Temple Quarter start to 2022

Aaron Morby 3 years ago
Share

Bristol University has delayed for a second time main construction of its major £300m campus development in the Temple Quarter and St Philip’s Marsh areas.

Main academic building design by Feilden Clegg Bradley Studios on the Cattle Market Road site.
Main academic building design by Feilden Clegg Bradley Studios on the Cattle Market Road site.

The University blamed both Covid and Brexit’s impact on the supply chain as well revisiting designs to introduce greater flexibility and future-proofing spaces to be more adaptable.

As a result of recalibrating the Temple Quarter Enterprise Campus programme, main construction of the Cattle Market Road site will start in the summer of 2022 with the anticipated opening of the new campus during the second half of 2025.

Adjacent to the Cattle Market Road site, the University is working to open new research facilities in the existing buildings on Avon Street early in 2022.

Site enabling works as part of the new campus development have continued over the past year in line with Government guidance.

The Temple Quarter Enterprise Campus will be home to 3,000 students and 800 university staff as well as provide accommodation for nearly 100 students in a cluster of high rise blocks.

Planned student room tower blocks

 

As part of the campus rethink the University is also exploring the possibility of relocating some specialist facilities and supporting hub spaces into the two stone buildings on Avon Street, previously the Vauxhall Drive workshop, which had formed part of longer term development plans for the area.

Outline plans has just gone in for longterm term development of Wales & West Utilities and Vauxhall and Kawasaki Drive sites and Plot 1 Silverthorne Lane.

The University has also just submitted outline planning for the Wales and West Utilities and Vauxhall and Kawasaki Drive sites on Avon Street and Gas Lane.

Barra Mac Ruairí, the University’s Chief Property Officer, said: “We are committed to Temple Quarter. We have taken on a challenging site in a challenging time with a scheme which is unique in terms of its activity.

“A project of this scale and ambition comes with a range of complexities, which have been exacerbated by the ongoing pandemic. However, we have pushed forward and will use this time to recalibrate and make the project even stronger and add more resilience.”

He added: “Our ambition is clear but any delay is disappointing, our vision for the Temple Quarter Enterprise Campus has not changed and we remain 100 per cent committed to contribute to the research, innovation and skills required to drive the city and region’s post-COVID recovery and help regenerate and deliver the future vision for Temple Quarter and St Philip’s Marsh.”

 

Latest news

Expanding consultant Stantec swoops for Hydrock

Stantec UK business expands by a third as 950 staff join from Bristol-based engineer
9 hours ago

National Grid unveils winners for £9bn network upgrade

New 'enterprise model' to deliver infrastructure schemes quicker and cheaper
11 hours ago

Chigwell Group looks at stock market listing

Essex contractor registers as Public Limited Company
17 hours ago

A57 Mottram Bypass clears final legal challenge

Balfour Beatty to get go-ahead to start shortly
18 hours ago

100 jobs axed as Geoffrey Osborne confirms administration

Chairman Andrew Osborne calls it a 'sad day' as board loses fight for survival
1 day ago

Midgard set for Notting Hill office tower overhaul

Landmark project edges towards final approval after 10-year planning saga
17 hours ago

Cumbrian civils firm clinches £40m Sellafield contract

Civils specialist Stobbarts will support McAlpine on groundworks and concrete
16 hours ago

Designers named for London 2000-bed student rooms job

Bouygues will build £400m London School of Economics student scheme next to Tate Modern
17 hours ago

£117m-turnover contractor files administration notice

ARJ Construction lodges court notice
2 days ago

£1bn London Blackfriars tower blocks approved

Trio of buildings rising to 45, 40 and 22 storeys approved by Southwark Council
2 days ago

Council decides to end Balfour deal after 13 years

Contractor has been maintaining roads across Herefordshire since 2013
2 days ago

Six civils clients to switch to low carbon concrete and steel

National Highways, Northumbrian Water and Sellafield sign fresh decarbonising pledge
2 days ago

Fortem extends homes repair deal across Birmingham

Willmott Dixon owned firm adds another two years to deal worth £170m
2 days ago

Kier wins £118m civil service Darlington hub

Work is expected to start towards the end of this year
3 days ago

Green light for 34-storey Digbeth apartments tower

480 flats will be delivered for Clarion housing association
2 days ago

LHC starts race for major retrofit and decarb framework

Hunt starts for firms to help with 6.1m social homes upgrade target
3 days ago

Windows giant Everest crashes into administration

Around 350 jobs at risk while hunt starts for a buyer to salvage business
3 days ago

Green light for £500m Newcastle health complex

Mixed use scheme will promote healthy living across all stages of life
3 days ago

Olympian Homes gets go-ahead for Bristol’s tallest building

Work on student and co-living towers to start this summer
3 days ago

ISG gets nod to start £20m Glamorgan school job

Ysgol y Deri specialist needs school is to built at Cosmeston, near Penarth
3 days ago

Walker Modular lands £5m bathroom pod contract

Specialist to work with Graham and Watkin Jones on major build-to-rent scheme

Banned building boss jailed for fraud

Court hears how disqualified director siphoned off cash from new housing company
3 days ago

Osborne staff start looking for new jobs

"Open to Work" flags appear on LinkedIn profiles
6 days ago

Plan rejected for 42-storey tower above historic building

Councillor describes as ludicrous plan to build 300 flats above Georgian mansion
6 days ago

Ventilation deal could hike product prices for contractors

Watchdogs at CMA launch probe after duct firm acquires rival
6 days ago

Tide gets go-ahead for London 412 student flats scheme

Volumetric developer secures planning for West Ealing project
6 days ago

Green light for £75m Friar Gate Goods Yard in Derby

Construction set to start this summer on revamp of historic buildings
6 days ago

Robertson to deliver £45m Newcastle NHS Trust works

Capital works will be focused on Freeman Hospital and the Royal Victoria Infirmary sites
6 days ago

Winners named for £2bn Healthy Homes framework

CHIC reveals line-up of over 40 firms for net zero and building safety works
6 days ago

Plan lodged for tallest skyscraper outside London

Developer Salboy submits plan for 76-storey Manchester resi tower
7 days ago

Contractor services