McAlpine £350m Deutsche Bank job delayed four months

Aaron Morby 4 years ago
Share

Developer Landsec has revealed that its flagship £350m Deutsche Bank HQ project in London has been delayed by another four months because of Covid restricted working.

Extra costs at Moorfield project are within original contingency budgets
Extra costs at Moorfield project are within original contingency budgets

Main contractor Sir Robert McAlpine originally was due to finish the 564,000 sq ft City office scheme above Crossrail’s Liverpool Street Moorgate ticket office by November this year.

This slipped before the pandemic to March 2022 and now has been pushed back once more to July.

McAlpine doubled the facility space for construction workers in order to accommodate more workers in a Covid-secure way at the 21 Moorfields site.

Weekend working was also introduced to mitigate some of the delays resulting from lower on-site capacity, but as a result of lower on-site capacity, practical completion has now been put back to July 2022.

It three other schemes in construction – Lucent (Piccadilly), The Forge (Southwark) and n2 (Victoria) – are now fully committed to after Landsec initially negotiated break options with contractors to give flexibility around capital spending

Completion dates at The Forge, Lucent and n2 are June 2022, December 2022 and June 2023 respectively.

Landsec said that additional costs resulting from the impact of Covid-19 had been accommodated within the contingency allowances of the schemes’ total development costs.

It was are already reported occupier interest in its three speculative schemes which it will continue to work towards securing pre-lets on.

Three pipeline schemes awaiting pre-lets


At Portland House, SW1, strip out and design works continued through to the end of April. We are currently assessing the potential timing of the scheme and are likely to pause to manage development exposure.

Laing O’Rourke has signed a PCSA deal for the £195m Timber Square job in Bankside

At Timber Square in Southwark, demolition of the existing building is due to commence by the end of May 2021 with a decision on development of the zero carbon office building to be taken by the autumn.

Existing building at development site

At 55 Old Broad Street, EC2, we will continue to work towards vacant possession in December 2024. In the meantime, we will be working up development plans while protecting short-term income.

Latest news

Civils winners revealed for £12bn National Grid high voltage work

Contractor wins complete £59bn investment programme
10 hours ago

United Living quits new-build housing as costs mount

£136m-turnover housing arm to wind down as focus shifts to core infrastructure
13 hours ago

Fight looms for £3bn West Midlands building framework

Galliford Try, Morgan Sindall and others face fight to keep CWM seats
14 hours ago

Industry anger over sudden CITB funding changes

Smaller contractors lose funding route worth £10,000 a year
14 hours ago

Plans in to transform former GSK London HQ with 2,300 homes

Landmark 13-acre scheme set to transform Brentford Great West Road campus
13 hours ago

Watch Murphy near completion of major new rail bridge

Latest video reveals progress on Greek Street bridge during 21-day train suspension
13 hours ago

Mount Anvil’s in-house builder drives results in testing market

Group development pipeline holds steady at 3,384 homes despite dip in profit
15 hours ago

Costain margin heads for 4.5% after half-year profit rise

Roads and HS2 rephasing hit transport revenues but £5.6bn forward book to support growth
2 days ago

Hinkley contractors face prosecution over rebar mesh fall

Bouygues and Laing O'Rourke face action brought by the Office for Nuclear Regulation
2 days ago

Farrans to build new £59m Paisley bridge

Work to start soon on transport project for Renfrewshire Council
2 days ago

Crown Estate hires Olympics village veteran to lead delivery push

John Nicholson to oversee £16bn portfolio’s major UK development pipeline.
2 days ago

Henry Boot gets green light for 2,500 new homes

Hallam Land division sees signs planning system is speeding-up
2 days ago

Wates inks £100m deal on first new-design prison houseblocks

HMP Onley expansion leads roll-out of new standardised design
3 days ago

£122m deal to unlock Newcastle’s last brownfield site

Land remediation funding paves way for 2,500-home Forth Yards neighbourhood
3 days ago

McLaren lands Heathrow logistics deal

1.6 hectare airport site to be transformed into modern warehouses
3 days ago

McAlpine veteran to lead T&T’s project management drive

Former Olympic Stadium lead Mike O’Donnell takes lead role with focus on major capital project delivery
3 days ago

IES snaps up Nexus Power out of administration

Utilities group strengthens expertise in 400kV jointing and offshore markets
3 days ago

Thames Water tenders £120m water main rehab deal

Company seeks 2–5 contractors for London and South East renewal works
3 days ago

Lower Thames Crossing to lead green planning reforms

New system to avoid another £100m HS2 bat tunnel
3 days ago

Mace lands latest 30-storey City of London tower

85 Gracechurch Street near Leadenhall Market to be transformed
4 days ago

Vinci gets go-ahead for £250m Stockport 8 scheme

Contractor to start first phase of 435 net zero homes next year
4 days ago

£80m bid race to convert Oxford Debenhams into labs

Crown Estate advance plan to convert former six storey department store
4 days ago

Bennett steps-in to finish Guinness Covent Garden brewery

Original fit-out contractor Beck Interiors fell into administration
4 days ago

Work-to-rule set to hit Sellafield clean-up

Action by 1,500 construction workers across 34 contractors
4 days ago

Aureos breaks ground on £45m Howden Relief Road

Yorkshire road will pave way for 2,000-home scheme
4 days ago

Oxford United win green light for £150m all-electric stadium

Planners back 16,000-seat Kidlington ground with hotel, plaza and community hub
7 days ago

Demolition record as eight cooling towers come down

Watch Brown & Mason set record at Cottam Power Station
1 week ago

Hitachi Energy named for EGL3 converter station deal

Firm to build major HVDC converter stations in Aberdeenshire and West Norfolk
7 days ago

PAS NW secures landmark £20m civils deal in Lancashire

Groundworks firm wins infrastructure for 429-home Wain Homes scheme
7 days ago

Subcontractors wanted for jobs across the South West

Register now for latest Constructionline event in Bristol
7 days ago