Shortage of subbies hampers construction growth

Grant Prior 4 years ago
Share

Construction buyers have reported a near record decline in subcontractor availability.

Latest results for the bellwether IHS Markit/CIPS UK Construction PMI Total Activity Index show a lack of subcontractors and materials shortages hampered growth last month.

The index registered 58.7 in July – down sharply from June’s 24-year high of 66.3 but still well above the crucial 50.0 no-change threshold.

The latest decline in subcontractor availability was the second-fastest since the survey began in 1997, exceeded only by that seen  during the lockdown in April 2020.

Tim Moore, Economics Director at IHS Markit, said: “Long lead times for materials and shrinking subcontractor availability were cited as factors holding back work on site.

“Around two-thirds of the survey panel experienced longer wait times for supplier deliveries in July, while just 2% reported an improvement since the previous month.

“July data marked the first real slowdown in the construction recovery since the lockdown at the start of this year. It was unsurprising that UK construction companies  were unable to maintain output growth at the 24-year high seen in June, especially with widespread supply shortages and constrained capacity to take on additional orders.”

Duncan Brock, Group Director at the Chartered Institute of Procurement & Supply, added: “The pervasive weaknesses in supply chains along with a lack of staff and contractor availability were laid bare as construction lost some of its get-up-and-go.

“The rampant rise in prices for raw materials and transportation continued to be the construction’s heavy load along with historically long delivery times.

“Though there was a slight improvement in supplier performance from June’s record low, it was partly as a result of frustrated supply chain managers reining back on purchases that were unlikely to arrive when needed.

“Businesses were also unable to expand on staff capacity, where even the most prolific hiring periods since 2014 was insufficient for builders’ ability to complete work in hand.

“Faced with transport disruptions, shortages of essentials and Brexit delays, the initial spurt of activity this year is fast hitting the rocks.

“Building optimism was dampened to the lowest since January as it is difficult to foresee when all these challenges are likely to subside.”

Fraser Johns, finance director at construction firm Beard, said: “We know these are challenges that are not set to go away any time soon, so in order to move forward it’s going to be crucial to take a proactive approach.

“Working in collaboration with suppliers and subcontractors, including ensuring prompt payment, will go some way to mitigate the risk of projects falling through.

“But customers need to be aware of the issues facing the industry is facing as well. Being transparent at the point of submitting tenders about the need to order certain materials early to ensure delivery on time, using two stage procurement processes, will help to overcome some of these issues.”

Latest news

Six guilty of £2m bribery over Devon housing site deals

Corrupt building bosses and E.ON project chief and QS sentenced
19 hours ago

1,650 former ISG staff launch legal claims

Redundancy Payment Service facing payout of more than £9m
22 hours ago

Plans lodged for £1bn cancer research centre in Sutton

London Cancer Hub will deliver around 1m sq ft of lab and research space
4 hours ago

London Met Uni seeks firm for £284m estate revamp

Contractor wanted to deliver capital works and FM
4 hours ago

Delayed £2bn estate rebuild back on as Berkeley signs deal

Birmingham council development agreement paves way for 2028 Ladywood start
1 day ago

Tilbury Douglas boosts margin to 2.1% as profits double

Firm targets 3.5% margin by 2029 under new business plan
1 day ago

Subbies battle for fastest bricklayer title

Winchmore management team go back on the tools
1 day ago

Green light for revised McLaren Reading revamp

Mixed-use plans to transform Broad Street Mall site
4 hours ago

Three arrested in Blu-3 and Mace bribery probe

Serious fraud office swoops over alleged £3m bribes to former Mace associates
2 days ago

Scotland’s most complex A9 dualling job heads to market

Market testing starts for £205m Pitlochry to Killiecrankie 6.4km upgrade
2 days ago

Unite signs £390m student beds JV with Manchester Met

Construction at Cambridge Halls site to start next year
1 day ago

Turkish contractor Limak to build new Luton Town stadium

Construction to start this summer on 25,000-seater venue
2 days ago

Kitchen fitter crushed to death by concrete blocks

House builder goes into liquidation before court case
1 day ago

Mears clinches £230m renewal for key Milton Keynes housing deal

Housing upkeep contractor achieves 100% renewal rate in bust rebid period
1 day ago

Murphy on board at new £32m rail station

Construction to start next year at Golborne station
2 days ago

HS2 engineers finish UK’s heaviest bridge slide early

A46 Kenilworth Bypass reopens 30 hours earlier than planned
2 days ago

Bowmer + Kirkland to build £190m Oxford science scheme

Work to start at end of next month on 180,000 sq ft Fabrica scheme
2 days ago

New BAM leisure centre pool springs a leak

Contractor investigating "technical issues" delaying new £36m green leisure centre
3 days ago

United Living lands £250m HyNet pipeline deal

Firm wins deal to design and build over 34km of pipework to collect CO2
2 days ago

Hydrogen diggers get green light to use roads

JCB hails historic decision for advance of hydrogen-fuelled plant on sites
2 days ago

Go-ahead for McAleer & Rushe Glasgow student job

£100m funding deal paves way for 591-bed student tower
2 days ago

Fly-tippers to get their vehicles crushed

Drones will be used to identify cowboy construction waste operators
2 days ago

Green light for £150m West End office revamp

Shaftesbury Avenue office retrofit retains 75% of original building
3 days ago

Morgan Sindall lands £30m Brunswick Wharf scheme in Bideford

North Devon waterside project will provide 100 flats
3 days ago

Former Keltbray managers jailed after corruption trial

Jail sentences following bribery probe on jobs including Battersea Power Station
4 days ago

Lidl pumps £500m into store and logistics expansion

Discounter plans 40 new stores this year as expansion ramps up
3 days ago

JJ Rhatigan UK profit jumps as turnover tops £150m

Irish contractor's expansion in England gathers pace
3 days ago

Driverless digger to be used on Taylor Woodrow site

Autonomous excavator to work at Manchester Airport after successful trial
3 days ago

MCS Build lands Basingstoke warehouse scheme

Construction starts this month after £26m funding deal
3 days ago

Leeds United unveil stadium revamp design

Club has still to set a timeframe for staged Elland Road upgrade
4 days ago

Contractor services