Crossrail told to wrap-up expensive Tier 1 contracts

Aaron Morby 4 years ago
Share

Public account committee MPs are warning that there is still no real certainty to the Elizabeth Line cost and opening schedule just four months before the first central section trains are due to operate services for the public.

Watchdog MPs have highlighted that Canary Wharf and Bond Street have had significant issues in the past and are yet to be completed.

While Bond Street has been taken off the critical path for limited first opening, MPs are still concerned about the full opening of Canary Wharf and a significant software update that is needed for the final stage of testing.

To bring greater cost certainty Crossrail Ltd also has been told to wrap up its expensive Tier 1 contracts as a matter of urgency.

The programme was spending £56m a month in the six months to March 2021, so any delay to the programme remains a significant risk to the eventual cost of the Elizabeth Line, warns in the latest Public Accounts Committee report published today.

“Crossrail Ltd must end the expensive Tier 1 contracts as soon as possible. 

“By July 2021, Crossrail Ltd expected to have updated its plans to reflect progress and risks remaining, which would inform its range of potential opening dates and costs. This has been delayed by up to two months,” it said.

The report warns that even with the Government bailout, the collapse in passenger numbers owing to the pandemic leaves the project with a potential £150m funding shortfall.

On present management estimates, the project is expected to cost £18.9bn compared to it initial budget of £14.8 in 2010.

Crossrail will still not provide a fixed opening date for the project.

It expects the central tunnelled section to open between February and June 2022 and will operate a shuttle service between Abbey Wood and Paddington. Full east-west services are not expected until December 2022.

Dame Meg Hillier MP, Chair of the Public Accounts Committee, said “We are finally, thankfully seeing a clearer sense of ownership, responsibility, and determination to complete the Crossrail programme from those in charge but there remains a serious, £150 million funding gap to finish the programme. There must be a focus now on finding real solutions to this.

“With fares down because of the ongoing impact of Covid we also need more clarity on the plans and timescale for repaying the significant government loans.”

MPs also complained that the Department for Transport has still not demonstrated that it is embedding lessons learned into its major programmes.

The report said: “This Committee has examined many major transport programmes, such as HS2, Great Western route modernisation and Thameslink, many of which have had significant problems in their delivery.

“We have told the Department many times that it needs to learn lessons, from Crossrail and from other major transport projects, so that it does not repeat the same mistakes.”

But they complain that the Department has still failed to explain in practical terms what it was doing differently, nor the real-world impact its changes have had on delivering major programmes.  

The Committee has called for a full report before November detailing what it has changed in its approach to delivering major programmes with its arms-length bodies.

 

 

Latest news

80 energy projects unlocked as Ofgem backs grid expansion

£24bn energy networks deal gets green light from regulator
12 hours ago

Pinewood submits £1bn data centre plan

Studio giant adds green and learning spaces to tech hub blueprint
13 hours ago

Record results after TClarke goes private

Britain's biggest M&E contractor flourishes after de-listing
13 hours ago

Dalkia lands £200m nuclear maintenance deal

1,000 nuclear FM staff to join M&E contractor
12 hours ago

Construction comeback to outpace wider economy

Arcadis forecast fueled by spending review optimism
1 day ago

First steel goes up on giant car battery site

Severfield gets to work on McAlpine Somerset site
1 day ago

Permasteelisa wins cladding deal on Bovis city tower

Facade specialist lands package at 60 Gracechurch Street
12 hours ago

Fox buys recycled asphalt specialist Fisher

Acquisition adds major recycled asphalt capacity in north west
1 day ago

Major Building Safety Regulator shake-up to end tower delays

HSE stripped of control and top fire chiefs brought in to fast-track stalled schemes
2 days ago

Hinkley trio sign Sizewell civils deal

Balfour,Bouygues and Laing O'Rourke form Civil Works Alliance for new power station
2 days ago

£3.9bn data centre plan for Ravenscraig steelworks

Green energy to power massive new steel to silicon AI campus
2 days ago

Breakthrough on HS2’s second longest tunnel

8.4 mile Northolt to Old Oak Common drive completes
2 days ago

Neilcott on fast-track to debt-free employee ownership

£22.5m loan nearly paid down after big profit year
2 days ago

TfL kicks off race for £700m Tube station upgrade

South Kensington and Elephant & Castle top the pipeline list
2 days ago

Corbyn Plant Hire fleet goes under the hammer

Kit to be sold off by sister firm to collapsed groundworks contractor
2 days ago

Government wields procurement stick on late payment

New rules would block slow payers from bidding on big public jobs
4 days ago

Hercules buys power line labour firm for £15.7m

Labour supply specialist snaps up Advantage NRG to tap booming electricity upgrade market
5 days ago

Universal bid to fast-track planning for theme park

Entertainment giant eyes 2026 start at Bedford site
5 days ago

Developer Breck to transform former Ibstock brick factory

Ravenhead works to become 300-home development
5 days ago

SP Energy Networks awards contracts worth £1.4bn

First round of awards under £5.4bn national electricity grid upgrade programme
5 days ago

Travelodge to convert Liverpool Street office building

Office-to-hotel conversion in City of London
5 days ago

Plans lodged for 1m sq ft City of London office

Barbican landmark building will reuse 40% of existing structure
5 days ago

PTSG acquires roofing specialist HD Sharman Group

Premier Technical Services Group expands building maintenance division
5 days ago

Balfour Beatty lands £833m carbon capture power plant job

Work to start later this year on Teesside carbon capture gas-fired power station
6 days ago

Svella agrees deal to save Cubby Construction

Solvent purchase set to save 214 jobs and protect supply chain
6 days ago

J Coffey holds line on margins despite £52m revenue slide

Pre-tax profit down 14% but firm eyes strong pipeline to bounce back
6 days ago

Consultants called up for £2.3bn NHS SBS panel reboot

Market asked for views ahead of next-gen procurement rollout
6 days ago

Hochtief launches new UK data centre division

German business model to be introduced for UK construction
6 days ago

Construction skills body launches with 100,000 worker target

Industry to work closer with Jobcentres to find new talent
6 days ago

Kier lands £42m Midlothian school and community hub

Contractor strengthens presence in Scotland with big education job
6 days ago