M1 fraud probe exposes contract management problems

Aaron Morby 2 years ago
Share

A National Highways fraud probe revealed by the Enquirer last year has found a string of concerning management issues on the M1 J13-16 smart motorway scheme.

The investigation by the agency’s in-house counter fraud squad has now concluded and found that National Highway has suffered financial loss.

But the national roads agency has decided not to pursue any criminal prosecution due to ‘insufficient conclusive evidence’, according to the final report seen by the Enquirer.

The investigation was launched into the Costain Galliford Try joint venture job after multiple accusations were leveled between 18 September 2020 and 2 February 2021, each alleging wrongdoing on the project.

These implied procurement fraud, theft of assets and collusion leading to false claims.

This scheme for a stretch between Milton Keynes and Northampton was awarded to the CGT JV with an agreed budget of £297m. This has ballooned to £453m.

Investigators for National Highways found £320,000 of central barrier scrap metal was ‘missing from the records and unaccounted for’ .

But after failing to secure any reliable witness testimony, the probe team said they were unable to prove the allegation of theft.

The investigation also failed to find hard evidence to support allegations of the use of ghost workers on the job, and bribes for subcontract work or business favours.

While labour supply on the project soared from £362,000 to around £9.5m, an investigation by the CGT JV uncovered no evidence to support whistleblowers claims, says the report.

In response to allegations of “brown envelopes” being passed around, National Highways investigators said that, although there was evidence cash-filled envelopes changed hands, it accepted the explanation that the money was requested from subcontractors to contribute to project staff parties.

Investigators also looked at a large package contract, which jumped from an original order value of £28m to a forecast end cost of £68m.

This was due for the most part to 1,389 compensation events, which were accepted as resulting from a number of complex underlying reasons.

National Highways’ commercial assurance partners have worked with the internal project team to understand the causes for the overspends and to challenge the escalating costs where appropriate.

In the final report, investigators did raise several concerns that ‘presented an increased risk of fraud and further possible accusations of bribery or corruption’ if not addressed.

These included poor contract management, in relation to escalating costs and proper implementation of the compensation events process.

They also highlighted a lack of record-keeping supporting key decisions during a live procurement and to validate ongoing subcontractor costs throughout the life-cycle of the project.

The team also red-flagged lack of governance around single-source procurement decisions.

A CGT JV spokesperson said: “The CGT JV responded comprehensively to all the issues brought to light with a detailed and thorough investigation, with appropriate action taken and further strengthening of its compliance procedures.

“Both companies in the JV have strong policies and procedures in place, fully promote a culture of transparency and encourage potential whistle-blowers to come forward.

“Both the CGT JV and National Highways investigations confirmed that there is no connection between any of the allegations and increased costs of the M1 junction 13-16 project.

“Any inference that the two are connected in any way or that the alleged activities that were under investigation have incurred a cost to the taxpayer is incorrect. Project scopes can evolve as was the case here, and those changes have the support of all parties involved.”

National Highways smart motorways programme director David Bray said: “We take any suggestion of criminal behaviour on our projects extremely seriously and investigate every allegation thoroughly. 

“We investigated, working collaboratively with our contractors, the allegations around the M1 and M6 schemes and prevented the payment of any amounts that we were not fully satisfied with.” 

Latest news

Stonehenge tunnel hit by another legal delay

Court upholds latest appeal against £1.7bn scheme by campaigners
8 hours ago

Plans go in for huge Olympic Park construction hub

Bow Goods Yard could deliver 3.5m tonnes of materials a year to sites across London
12 hours ago

40% affordable homes target for Labour’s new towns

Labour pledges to select new town sites by end of first year
10 hours ago

Plan for £100m Liverpool Baltic station

Construction work could begin next year
16 hours ago

Surgo Construction went down owing £4.5m

Biggest creditor is Bellway Homes after dispute on housing job
15 hours ago

Vistry seals £157m West London housing deal

Around 575 homes to be built at Merrick Place scheme in Ealing
14 hours ago

Streamlined Watkin Jones returns to profit in first half

Multi-room specialist sees secured work pipeline hit £1.4bn
15 hours ago

Bellway hires ex-brickie as group construction chief

James Griffin to oversee move to the Future Homes Standard and timber frame.
15 hours ago

Persimmon under fire for delays to £10m relief road

West Suffolk Council serves Breach of Condition Notices after timetable slips again
15 hours ago

BAM wins £33m Kent secondary school job

Replacement Swanley academy to be built at live school site
15 hours ago

Aluminium cladding specialist collapses

Melton Mowbray-based firm worked for several main contractors
2 days ago

Brickwork contractor Lee Marley returns to profit

Affordable and rental homes demand lifts brickwork contractor
2 days ago

Housing contractor Durkan suffers second year of losses

More fire safety provisions tip firm into £3.9m loss
2 days ago

Farrans makes breakthrough on tricky tunnel job

Tunnel under Tees latest part of new £155m water pipeline job
2 days ago

Heidelberg buys aggregates and earthworks specialist B&A

Latest deal follows acquisition of Mick George
2 days ago

Flagship biodiversity net gain scheme flawed

NAO warns Government's flagship green development scheme at risk of failure
5 days ago

Plan in for £3bn Lincolnshire mega data centre

3.3m sq ft Humber Tech Park will be one of Europe's largest data centres
5 days ago

Green light for Digbeth 1,300 homes scheme

Warner’s Fields scheme to start with excavation and landscaping of the River Rea
5 days ago

£210m M3 Junction 9 upgrade gains consent

VolkerFitzpatrick to start work in early 2025 on Winnall roundabout, near Winchester
5 days ago

United Living wins 14-year L&Q homes repairs deal

Trafford housing upkeep deal worth £205m
5 days ago

£400m Lewisham resi-led scheme advances

Land deal paves way for Amro Partners' 1,000-home London scheme
5 days ago

McLaren gets go-ahead for Grade II listed Leeds student scheme

Springfield House to be revamped and two new wings added
5 days ago

Piling giant to fit people alarms on all rigs

Cementation Skanska upgrades site safety systems
5 days ago

Vistry to make £800m profit after subcontractor cost cuts

House builder bullish about shareholder returns after asking suppliers for discounts
6 days ago

Shareholders approve £2.5bn Barratt and Redrow merger

Final hurdle is for the competition regulator to approve the deal.
6 days ago

Green light for £80m Leith waterfront revamp

Build-to-rent homes and student accommodation scheme to be built
6 days ago

Tilbury Douglas clears Interserve legacy jobs to return to profit

Revenue tops £500m in first year as standalone contractor
6 days ago

Land deal paves way for Manchester civil service office hub

Government buys five acres at former Central Retail Park
6 days ago

Speller Metcalfe wins Wolverhampton library upgrade

Full works are due to start in the autumn
6 days ago

Skills shortage puts big infrastructure projects at risk

Government failing as an intelligent client and now over-reliant on consultancies
7 days ago

Contractor services