Skanska Costain Strabag completes latest HS2 base slab

Grant Prior 3 years ago
Share

The Skanska Costain STRABAG joint venture (SCS JV) has completed the base slab construction of the HS2 Victoria Road ancillary shaft in Acton.

The first permanent works began at the site in February 2021 when the team poured a 160m3 concrete collar around the ancillary shaft.

They then built the first 11m of the 25m internal diameter shaft using precast concrete segments, produced by FP McCann Ltd, before completing the final 19metre depth using the sprayed concrete lining technique.

The team of around 30 engineers and operatives have since completed the shaft with a 3.3m thick base slab constructed in three different pours.

The main pour of around 1,000 m3 of concrete took place at the end of 2021, and the second and third completed by the end of January 2022 adding another 740 m3 of concrete.

The site will provide critical infrastructure for the operation of HS2. As well as the 25m internal diameter shaft, which will provide ventilation and emergency access to the Northolt Tunnels, SCS JV is building a crossover box on the site that will let trains switch tracks on the way in and out of Old Oak Common station.

HS2’s Project Client, Malcolm Codling said: “The team at Victoria Road have made huge strides, completing the base slab of the ancillary shaft, and preparing the site for the launch of two tunnel boring machines.  As we move into the next phase of work. It won’t be long until we begin to see where the railway will run through the site, taking it from our detailed construction plans to reality.”

Skanska Costain STRABAG Joint Venture’s Managing Director, James Richardson added: “We’re constructing eight ventilation shafts along our 13 miles of twin bore tunnels in London and this vent shaft is the first to advance to this stage.

“Work is progressing well at all our other shaft sites so that they are ready for the tunnel boring machines to travel through them as our huge tunnelling programme progresses over the next three years.”

The site at Victoria Road also has a crucial role to play in construction.

SCS JV will use it to assemble and launch two tunnel boring machines (TBMs) that will dig the 3.4-mile eastern section of the Northolt tunnels. The TBMs are due to arrive in early 2023 and will begin the 12 month programme of tunnelling later that year.

The site will also be connected to the Logistics Hub located at the Willesden Euroterminal by a conveyor system that will remove spoil excavated for the tunnels.

The conveyor system, which also connects the Logistics Hub to Old Oak Common station site, will become operational later this year and will contribute to reducing lorry movements for HS2, removing around 1million lorries from the road.

Latest news

Civils winners revealed for £12bn National Grid high voltage work

Contractor wins complete £59bn investment programme
10 hours ago

United Living quits new-build housing as costs mount

£136m-turnover housing arm to wind down as focus shifts to core infrastructure
13 hours ago

Fight looms for £3bn West Midlands building framework

Galliford Try, Morgan Sindall and others face fight to keep CWM seats
14 hours ago

Industry anger over sudden CITB funding changes

Smaller contractors lose funding route worth £10,000 a year
14 hours ago

Plans in to transform former GSK London HQ with 2,300 homes

Landmark 13-acre scheme set to transform Brentford Great West Road campus
13 hours ago

Watch Murphy near completion of major new rail bridge

Latest video reveals progress on Greek Street bridge during 21-day train suspension
13 hours ago

Mount Anvil’s in-house builder drives results in testing market

Group development pipeline holds steady at 3,384 homes despite dip in profit
15 hours ago

Costain margin heads for 4.5% after half-year profit rise

Roads and HS2 rephasing hit transport revenues but £5.6bn forward book to support growth
2 days ago

Hinkley contractors face prosecution over rebar mesh fall

Bouygues and Laing O'Rourke face action brought by the Office for Nuclear Regulation
2 days ago

Farrans to build new £59m Paisley bridge

Work to start soon on transport project for Renfrewshire Council
2 days ago

Crown Estate hires Olympics village veteran to lead delivery push

John Nicholson to oversee £16bn portfolio’s major UK development pipeline.
2 days ago

Henry Boot gets green light for 2,500 new homes

Hallam Land division sees signs planning system is speeding-up
2 days ago

Wates inks £100m deal on first new-design prison houseblocks

HMP Onley expansion leads roll-out of new standardised design
3 days ago

£122m deal to unlock Newcastle’s last brownfield site

Land remediation funding paves way for 2,500-home Forth Yards neighbourhood
3 days ago

McLaren lands Heathrow logistics deal

1.6 hectare airport site to be transformed into modern warehouses
3 days ago

McAlpine veteran to lead T&T’s project management drive

Former Olympic Stadium lead Mike O’Donnell takes lead role with focus on major capital project delivery
3 days ago

IES snaps up Nexus Power out of administration

Utilities group strengthens expertise in 400kV jointing and offshore markets
3 days ago

Thames Water tenders £120m water main rehab deal

Company seeks 2–5 contractors for London and South East renewal works
3 days ago

Lower Thames Crossing to lead green planning reforms

New system to avoid another £100m HS2 bat tunnel
3 days ago

Mace lands latest 30-storey City of London tower

85 Gracechurch Street near Leadenhall Market to be transformed
4 days ago

Vinci gets go-ahead for £250m Stockport 8 scheme

Contractor to start first phase of 435 net zero homes next year
4 days ago

£80m bid race to convert Oxford Debenhams into labs

Crown Estate advance plan to convert former six storey department store
4 days ago

Bennett steps-in to finish Guinness Covent Garden brewery

Original fit-out contractor Beck Interiors fell into administration
4 days ago

Work-to-rule set to hit Sellafield clean-up

Action by 1,500 construction workers across 34 contractors
4 days ago

Aureos breaks ground on £45m Howden Relief Road

Yorkshire road will pave way for 2,000-home scheme
4 days ago

Oxford United win green light for £150m all-electric stadium

Planners back 16,000-seat Kidlington ground with hotel, plaza and community hub
7 days ago

Demolition record as eight cooling towers come down

Watch Brown & Mason set record at Cottam Power Station
1 week ago

Hitachi Energy named for EGL3 converter station deal

Firm to build major HVDC converter stations in Aberdeenshire and West Norfolk
7 days ago

PAS NW secures landmark £20m civils deal in Lancashire

Groundworks firm wins infrastructure for 429-home Wain Homes scheme
7 days ago

Subcontractors wanted for jobs across the South West

Register now for latest Constructionline event in Bristol
7 days ago