Piling starts on pioneering double composite HS2 viaduct

Aaron Morby 3 years ago
Share

HS2’s EKFB joint venture has started piling work on the pioneering low-carbon Wendover Dean Viaduct project that aims to more than halve the amount of embedded carbon in the structure.

Double composite structure uses significantly less carbon-intensive concrete and steel in comparison to a more traditional design.
Double composite structure uses significantly less carbon-intensive concrete and steel in comparison to a more traditional design.

At 450m-long, the viaduct will be the first major railway bridge in the UK to be built with a ‘double composite’ structure, using significantly less carbon-intensive concrete and steel in comparison to a more traditional design.

The ‘double composite’ approach was inspired by structures on the latest French high-speed TGV lines.

It was developed by the Eiffage, Kier, Ferrovial Construction and BAM Nuttall (EKFB)consortium, working with design JV partner Arcadis, Setec and COWI (ASC), and specialist architects Moxon.

Over the summer, an expert team of ground engineers will construct 63 concrete piles to form the foundations for the structure.

Later piers – some of which will be up to 14m high – will be cast as shells before being assembled on site and filled with concrete. This will reduce the amount of work on site and cut disruption for residents.

The first ‘double composite’ beams will be installed next year.

Instead of using solid pre-stressed concrete beams to form the bridge spans, the viaduct will use two steel girders sandwiched between two layers of reinforced concrete to create a super strong but lightweight hollow span.

This approach is set to save an estimated 7,433 tons of carbon – the equivalent of 20,500 return flights from London to Edinburgh – and help HS2 achieve its goal of halving the amount of embedded carbon in construction.

Peter Oosterveer, CEO of Arcadis, said:  “Transport accounts for nearly a third of global carbon emissions, and it is crucial that our industry continues to pioneer new ideas and approaches that support carbon reduction.

“Being able to draw on best practice examples from all around the world is critical when it comes to ensuring the long-term social, environmental and economic sustainability of all the projects in which we are involved.”

HS2 Project Client Rohan Perin, said: “We’re also serious about reducing the amount of carbon we use during construction, and Wendover Dean is a great example of how we’re using the latest engineering techniques to do just that.”

Latest news

Buyers more bullish about prospects for year ahead

Residential "resilient" but commercial work a weak spot
2 hours ago

Council backs first Brutalist car park-to-flats scheme

Newcastle-under-Lyme multi-storey car park to be reborn as pioneering homes scheme
4 hours ago

Hinkley Point C hits peak build with 26,000 jobs

3,000 more workers to join as fit-out work ramps up
4 hours ago

Over 40 firms win Wessex Water M&E minor works deal

Broad sweep of specialists picked for AMP8 programme
4 hours ago

Spencer lands Scottish bridge hat-trick

Steelwork, gantries and bearing upgrades on Kessock, Forth and Tay crossings
19 hours ago

Winners revealed for £1.5bn decarbonisation deal

Fusion21 confirms places for 40 firms: Full list
4 hours ago

Cladding firm fined £225,000 after fatal fall

Court hears how cherry picker didn't reach all parts of repair job
5 hours ago

Early call-out for Ebbsfleet Garden City infrastructure

Bidders day to set out plan for Ebbsfleet Central commercial scheme
4 hours ago

Completed buildings caught-up in Gateway 2 chaos

Developer distraught after dealing with Building Safety Regulator
1 day ago

Aviva submits plans for 34-storey City office tower

Subject to planning work to start in autumn 2027
1 day ago

Murphy takes 40% stake in Aussie civils contractor

Firm enters Australasian market with stake in Sydney-based contractor Abergeldie
2 days ago

Moat seeks firm for £420m repairs and maintenance deal

15-year deal to upkeep 20,000 south east homes
1 day ago

Lynch takes over hotel for Sizewell plant operators

Hire giant now in the hotel business to guarantee accommodation for workers
1 day ago

Subcontractors wanted across Scotland

Latest Constructionline event in Glasgow: Register now
1 day ago

Six guilty of £2m bribery over Devon housing site deals

Corrupt building bosses and E.ON project chief and QS sentenced
6 days ago

1,650 former ISG staff launch legal claims

Redundancy Payment Service facing payout of more than £9m
6 days ago

Plans lodged for £1bn cancer research centre in Sutton

London Cancer Hub will deliver around 1m sq ft of lab and research space
5 days ago

London Met Uni seeks firm for £284m estate revamp

Contractor wanted to deliver capital works and FM
5 days ago

Delayed £2bn estate rebuild back on as Berkeley signs deal

Birmingham council development agreement paves way for 2028 Ladywood start
6 days ago

Tilbury Douglas boosts margin to 2.1% as profits double

Firm targets 3.5% margin by 2029 under new business plan
6 days ago

Subbies battle for fastest bricklayer title

Winchmore management team go back on the tools
6 days ago

Green light for revised McLaren Reading revamp

Mixed-use plans to transform Broad Street Mall site
5 days ago

Three arrested in Blu-3 and Mace bribery probe

Serious fraud office swoops over alleged £3m bribes to former Mace associates
7 days ago

Scotland’s most complex A9 dualling job heads to market

Market testing starts for £205m Pitlochry to Killiecrankie 6.4km upgrade
7 days ago

Unite signs £390m student beds JV with Manchester Met

Construction at Cambridge Halls site to start next year
6 days ago

Turkish contractor Limak to build new Luton Town stadium

Construction to start this summer on 25,000-seater venue
7 days ago

Kitchen fitter crushed to death by concrete blocks

House builder goes into liquidation before court case
6 days ago

Mears clinches £230m renewal for key Milton Keynes housing deal

Housing upkeep contractor achieves 100% renewal rate in bust rebid period
6 days ago

Murphy on board at new £32m rail station

Construction to start next year at Golborne station
7 days ago

HS2 engineers finish UK’s heaviest bridge slide early

A46 Kenilworth Bypass reopens 30 hours earlier than planned
7 days ago

Contractor services