HS2 Euston needs full design reset as costs set to double

Aaron Morby 2 years ago
Share

The public spending watchdog has called for an urgent total design rethink of the Euston terminus of HS2 as costs soar.

National Audit Offcie calls for full project review to develop a design that is deliverable and value for money.
National Audit Offcie calls for full project review to develop a design that is deliverable and value for money.

A new National Audit Office report into the station warns that forecast project costs have continued to balloon despite attempts to simplify the project.

The original £2.6bn station budget is now reckoned to have soared to £4.8bn, even with the cost-cutting decision to trim back platforms from 11 to 10.

Spending to date on advanced works has already hit £548m.

NAO experts warn that the Government’s latest two-year pause in new construction can only inflate long-term costs further.

This is due to costs associated with demobilising and then remobilising teams, contractual changes, and managing the project for longer.

It has called on the Government to use the two-year pause to go back to the drawing board and develop a design that is affordable, deliverable and value for money.

The NAO’s report recommends the DfT works with stakeholders: Euston Partnership, HS2 Ltd, Network Rail, Lendlease and local partners to reassess the expectations for the HS2 Euston project, its budget, and the public benefits.

Gareth Davies, the head of the NAO said: “Government is once again having to revise plans for Euston HS2.

“Clearly, the 2020 reset of the station design has not succeeded.

“DfT and HS2 Ltd have not been able to develop an affordable scope that is integrated with other activity at Euston, despite their focus on costs and governance since 2020. Recent high inflation has added to the challenge.

“The March 2023 announcement by the Transport Secretary pausing new construction work should now give DfT and HS2 Ltd the necessary time to put the HS2 Euston project on a more realistic and stable footing.

“However, the deferral of spending to manage inflationary pressures will lead to additional costs and potentially a more expensive project overall, and that will need to be managed closely.”

Meg Hillier MP, Chair of the Committee of Public Accounts. added: “Attempts to reset the High Speed 2 Euston Station have failed.

“It is still unaffordable and no further forward than it was three years ago.

“Today’s NAO report shows that the redesigned station would have cost nearly double what was budgeted.

“Department for Transport and High Speed Two Ltd have wasted enough time and money. They must get Euston right next time or risk squandering what benefits remain.”

Euston Station cost reality check


  • In January 2020, the NAO reported that the work at Euston was more complex than originally anticipated and that there was uncertainty over the HS2 station design.
  • The following month the Oakervee Review 2 raised concerns about the design of the HS2 Euston station and concluded that the existing design was unsatisfactory.
  • In April 2020, HS2 Ltd set the station budget at £2.6bn, but by June 2020 it estimated that it could cost as much as £4.4bn.
  • In November 2020, the DfT instructed HS2 Ltd to pause construction on the 11-platform design to begin work on a new 10-platform plan.
  • These new plans are now £0.4bn more expensive than the previous 11-platform design.
  • In Autumn 2021 the Department also directed HS2 Ltd to integrate more closely with Network Rail’s redevelopment of the existing rail station and confirmed the extent of the surrounding commercial and residential developments.
  • Much of the previous design work was then scrapped, at a cost of £106m to the taxpayer, despite DfT’s efforts to minimise this.
  • To help with this integration, and in response to the Oakervee recommendations, in December 2021 the DfT formally established the Euston Partnership to bring together the different bodies involved with projects on the Euston site, including delivery of HS2 Euston station.
  • Following the Transport Secretary’s announcement to delay works in March 2023, the DfT will now need to consider how best to control the budget.
  • By the end of December 2022 HS2 Ltd had spent more than £2bn on the HS2 Euston station and its approaches, including design, land, and preparatory works.
  • The land purchases and preparatory works cost £1.5bn and were funded from the wider HS2 budget.

Latest news

Six guilty of £2m bribery over Devon housing site deals

Corrupt building bosses and E.ON project chief and QS sentenced
4 days ago

1,650 former ISG staff launch legal claims

Redundancy Payment Service facing payout of more than £9m
4 days ago

Plans lodged for £1bn cancer research centre in Sutton

London Cancer Hub will deliver around 1m sq ft of lab and research space
3 days ago

London Met Uni seeks firm for £284m estate revamp

Contractor wanted to deliver capital works and FM
3 days ago

Delayed £2bn estate rebuild back on as Berkeley signs deal

Birmingham council development agreement paves way for 2028 Ladywood start
4 days ago

Tilbury Douglas boosts margin to 2.1% as profits double

Firm targets 3.5% margin by 2029 under new business plan
4 days ago

Subbies battle for fastest bricklayer title

Winchmore management team go back on the tools
4 days ago

Green light for revised McLaren Reading revamp

Mixed-use plans to transform Broad Street Mall site
3 days ago

Three arrested in Blu-3 and Mace bribery probe

Serious fraud office swoops over alleged £3m bribes to former Mace associates
4 days ago

Scotland’s most complex A9 dualling job heads to market

Market testing starts for £205m Pitlochry to Killiecrankie 6.4km upgrade
4 days ago

Unite signs £390m student beds JV with Manchester Met

Construction at Cambridge Halls site to start next year
4 days ago

Turkish contractor Limak to build new Luton Town stadium

Construction to start this summer on 25,000-seater venue
5 days ago

Kitchen fitter crushed to death by concrete blocks

House builder goes into liquidation before court case
4 days ago

Mears clinches £230m renewal for key Milton Keynes housing deal

Housing upkeep contractor achieves 100% renewal rate in bust rebid period
4 days ago

Murphy on board at new £32m rail station

Construction to start next year at Golborne station
5 days ago

HS2 engineers finish UK’s heaviest bridge slide early

A46 Kenilworth Bypass reopens 30 hours earlier than planned
5 days ago

Bowmer + Kirkland to build £190m Oxford science scheme

Work to start at end of next month on 180,000 sq ft Fabrica scheme
5 days ago

New BAM leisure centre pool springs a leak

Contractor investigating "technical issues" delaying new £36m green leisure centre
6 days ago

United Living lands £250m HyNet pipeline deal

Firm wins deal to design and build over 34km of pipework to collect CO2
5 days ago

Hydrogen diggers get green light to use roads

JCB hails historic decision for advance of hydrogen-fuelled plant on sites
5 days ago

Go-ahead for McAleer & Rushe Glasgow student job

£100m funding deal paves way for 591-bed student tower
5 days ago

Fly-tippers to get their vehicles crushed

Drones will be used to identify cowboy construction waste operators
5 days ago

Green light for £150m West End office revamp

Shaftesbury Avenue office retrofit retains 75% of original building
6 days ago

Morgan Sindall lands £30m Brunswick Wharf scheme in Bideford

North Devon waterside project will provide 100 flats
6 days ago

Former Keltbray managers jailed after corruption trial

Jail sentences following bribery probe on jobs including Battersea Power Station
6 days ago

Lidl pumps £500m into store and logistics expansion

Discounter plans 40 new stores this year as expansion ramps up
6 days ago

JJ Rhatigan UK profit jumps as turnover tops £150m

Irish contractor's expansion in England gathers pace
6 days ago

Driverless digger to be used on Taylor Woodrow site

Autonomous excavator to work at Manchester Airport after successful trial
6 days ago

MCS Build lands Basingstoke warehouse scheme

Construction starts this month after £26m funding deal
6 days ago

Leeds United unveil stadium revamp design

Club has still to set a timeframe for staged Elland Road upgrade
6 days ago

Contractor services