Morrisroe Group suffers its first trading loss

Aaron Morby 2 years ago
Share

Diversified concrete, demolition and piling contractor Morrisroe has suffered its first major trading loss as a group after concrete and rebar price hikes squeezed fixed-price jobs.

CEO Brian Morrisroe says the group was caught by exceptional material and labour cost hikes on fixed-price jobs last year
CEO Brian Morrisroe says the group was caught by exceptional material and labour cost hikes on fixed-price jobs last year

Traditionally star performers within the group A J Morrisroe & Sons, Kingscote Plant and GSS Piling all plunged into the red.

Turnover at the Hertfordshire-based group remained broadly static at around £204m in the year to October 2022.

But materials price inflation caught Morrisroe on fixed-price work and dragged the group to pre-tax loss of £6.9m, after a £2.4m profit in the prior year.

Chief executive Brian Morrisroe said that over the period primary materials which represented 40% of contract sums skyrocketed with the cost of rebar soaring 130%, concrete jumping 26% and plywood up 25%.

He said the group’s integrated offer from demolition to foundations and concrete frame was gaining traction with Tier 1 contractors.

Based on a present group pipeline of £388m of work, he predicted Morrisroe revenue would resume growth this year reaching around £225m

Morrisroe said: “I am positive about the future, with our exposure to fixed price contracts signed in 2021 and 2022 having been completed in the trading period or expected to be completed in the period ending October 2024.

“In future we expect our integrated offer to generate growth in revenue for both our demolition and piling businesses and we will continue to take measured risk to facilitate sustainable growth in other areas of the business.”

He added: “Our ability to see key trends and opportunities and respond quickly gives us confidence in our ability to weather the economic downturn in the UK and the resulting slowdown in some sectors of the property and construction market.

“We are correctly positioned for the new growth areas having demonstrated a strong capability for sustainable design and construction, particularly in relation to retrofit projects as well as projects with ambitious and innovative reuse and repurposing objectives.

“We have been able to convert a number of opportunities in the commercial office sector as well as in the health sector.”

Over the course of the testing year, cash at bank slipped to £27m from £38m.

 

 

Latest news

Cheetham Hill Construction sold to staff

Howard Chamberlain to step-back from MD role after nearly 60 years
16 hours ago

Buyers see sharpest fall in activity for five years

Grim July for construction as all sectors slump
20 hours ago

Cardiff to get 50-storey skyscraper in bold new tower plan

Developer ups height to 50 storeys for BTR landmark near Principality Stadium
23 hours ago

Bid race starts for Manchester £1.6bn light rail infrastructure work

Up to ten bidders wanted to compete for Metrolink work
23 hours ago

Competitive brick market sees Ibstock struggle to increase prices

Revenue rises but profits dip at materials giant
22 hours ago

Collins starts major London city fringe office retrofit

30 Finsbury Square refurb scheme will transform office block
23 hours ago

Civils boss banned over classic car sales

Director sold assets cheaply to sister company before folding
2 days ago

Ex-Kier director joins Stepnell to grow specialist units

Mike Smedley steps in as strategic director to lead growth push
22 hours ago

Clegg wins £80m Leeds office scheme

Eight-storey office project to rise on former Wellington Plaza site
2 days ago

Avant Homes takes £107m fire safety hit as losses mount

Builder led by Jeff Fairburn lifts provision by £39m for legacy cladding repairs
2 days ago

Profit recovery continues at Laing O’Rourke

CEO Cathal O’Rourke vows to "push the boundaries of what’s possible, in service of humanity"
3 days ago

Torsion clears Gateway 2 for Leeds student scheme

Firm to share lessons from the Gateway 2 process on Kirkstall Road 10-storey job
2 days ago

Bouygues chosen to build new children’s hospital

Construction to start within next 18 months on Cambridge site
2 days ago

Firms readied for £145m Welsh bridge race

Bidding to start this month for River Dee bridge replacement job
3 days ago

Cladding training boost to accelerate remediation work

Free courses for installers and supervisors to help accelerate post-Grenfell work
2 days ago

JRL replaces Ardmore on £150m City landmark revamp

Malaysian developer IJM calls in part-owned contractor for 25 Finsbury Circus job
3 days ago

Green light for Bristol Brabazon over-station office block

YTL to start eight-storey HQ building above new train station ticket office
3 days ago

£200m funding deal for hydrogen from waste plant

Tilbury site will be first stage of national network for green fuel
3 days ago

Go-ahead for London major hospital-to-resi scheme

Developer TT Group to deliver 140 homes and 65-bed care home on historic site
3 days ago

Civil specialist M Lambe slips into the red

Firm predicts bounce back this year as social housing recovers
3 days ago

Pickstock plans to revamp derelict Birmingham site

Developer looks to transform Soho Hill in the city
3 days ago

Retentions could be banned in late payment crackdown

Government considers abolition of hated system in construction
6 days ago

Heathrow Airport unveils £49bn ‘superhub’ expansion

Airport operator says it is ready to start design and supply chain activity this year
6 days ago

National Grid names contractors for £8bn of substation work

Regional deals will give firms first refusal on work in their area
6 days ago

Keltbray names Ferrovial’s Karl Goose as new CEO

New boss to take over in December as Vince Corrigan retires
6 days ago

Green light for first 880 homes at Manchester Mayfield

Four blocks rising to 28 storeys set to cost around £250m to build
6 days ago

Fit-out trade body hits back at bloated contracts

Dry walling and interiors body backs 500-word contract in fight against legal traps
6 days ago

Arora and Bechtel pitch rival Heathrow expansion plan

New Terminal 6 and runway said to be faster, greener and cheaper option
7 days ago

Major delays hit £4.8bn Levelling Up project programme

Whitehall admits most projects still stuck in design or planning phase
7 days ago

London new home starts slump 59% as safety regime bites

National rise masks capital’s fall amid BSR delays and social housing slowdown
7 days ago