‘Marathon’ bridge build completed on HS2

Grant Prior 2 years ago
Share

Contractors on HS2 have completed a ‘marathon’ bridge build at Streethay near Lichfield involving 18 specialist construction companies.

Work involved excavating 14,000 tonnes of earth, building a 140 metre retaining wall and moving a 2,600 tonne bridge deck 130 metres into place under the South Staffordshire freight railway.

The work was carried out during a 10 week blockade. It was completed by HS2’s civils contractor in the West Midlands, Balfour Beatty VINCI, and designers Mott MacDonald as part of a Design Joint Venture with SYSTRA (MMSDJV), together with teams from 18 specialist supply chain companies.

At the end of July, the 2,600 tonne bridge deck, which had been cast on land adjacent to the railway was moved 130 metres into position using self-propelled modular transporters.

Since then, each side of the bridge was backfilled, the rail tracks were reinstated, with the railway line was successfully handed back to Network Rail last week and now reopened.

The 25 metres long and 18 metres wide Streethay overbridge sits within HS2’s Streethay cutting and will enable HS2 trains to travel under the existing railway between Birmingham and Crewe.

Through design development, Mott MacDonald engineers were able to reduce the total length of wall structures for the railway at Streethay from 1.6 kilometres to 420 metres, meaning 80% less concrete is needed – saving around 420,000 tonnes of carbon, supporting HS2’s ambition to cut carbon on the project.

The Streethay bridge sits on top of the larger 420 metre long retaining wall structure which will have two additional bridges crossing it – the south bound A38 slip road bridge, and the Rykneld Bridge which carries the A38 north bound slip road and the A38 north and south bound carriageway.

At its peak, over 150 people worked on the complex construction operation, with teams from 18 specialist companies, delivering design, surveys, piling works, bridge build, concrete pouring, crane operations, reinforcements, modular transportation, track and systems removal and reinstatement.

The work was delivered in parallel to the construction of the nearby Fulfen Wood bridge, which involved moving a giant 6,200 tonne single span structure under the West Coast Main Line – the UK’s heaviest drive to install an intersection bridge.

David Millar, Rail Interface Manager at Balfour Beatty VINCI said: “The successful delivery of this complex and challenging piece of engineering near Lichfield is another proud moment for Balfour Beatty VINCI on the HS2 project.

“It’s only been possible thanks to the skill, dedication and support shown by the project team over the past few years, including our supply chain. Together, we’ve had to work around existing transport infrastructure, including the South Staffordshire freight railway and the A38, making this achievement even more rewarding.”

Prior to the railway blockade, retaining walls were installed on either side of the railway, enabling the areas to be excavated. The bridge deck was constructed on land adjacent to the existing railway, 130 metres from its final position.

Once the railway was closed to freight trains, the track and embankment were removed. Bachy Soletanche Balfour Beatty Ground Engineering joint venture then installed an additional 76 secant piles measuring 1.3 metres diameter and 30 metres deep, linking to the piles they installed prior to the blockade, to create two retaining walls which act as the walls for the bridge.

A concrete capping beam was installed over the retaining walls, then the bridge was moved into place using self-propelled modular transporters with 344 wheels. Concrete was poured to attach the deck to the capping beam, the embankment was back filled using 2,500 tonnes of structural backfill, on either side of the bridge, before the railway line was reinstated.

The 18 companies which delivered the project were:

  • J. Murphy & Sons constructed the bridge deck and the concrete elements during the blockade
  • Bachy Soletanche Balfour Beatty Ground Engineering JV (SB3) undertook all piling works, both before and during the blockade
  • The bridge parapets were made by Explore precast
  • Podtrak and RSS Infrastructure delivered rail systems work
  • Balfour Beatty VINCI delivered earthworks
  • Pile break-down was by Pile Breaking Systems UK Ltd
  • Trackway supplied by TPA
  • Jacking the structure and modular transportation by Mammoet UK
  • Survey works track monitoring by Aecom
  • Crane supply by King Lifting supported by BBV lifting teams
  • Concrete provided by CEMEX
  • Reinforcement by ROM – specialist reinforcement manufacturers
  • Temporary works by RMD
  • Permanent works design by Design JV (Mott Macdonald and Systra)
  • Temporary works design by Taylor Woodrow

Latest news

Barking build to rent towers face rebuild

Major remedial work needed on resi scheme built by Shapoorji Pallonji UK Ltd
2 hours ago

London new home starts plunge 38% as Building Safety Act bites

Capital only region to see Q1 fall in NHBC new home registrations
21 hours ago

Sureserve swoops for rival compliance outfit Kinovo in £56m deal

Recommended cash offer will take AIM listed contractor private
2 hours ago

Crown Golf tees up £1bn plan to build 3,000 homes on course land

Major housing plan for spare land on eight UK courses
1 hour ago

Green light for Peterborough Station Quarter £48m revamp

First phase to start before the end of the year
2 hours ago

Morgan Sindall starts £38m Caerphilly leisure hub

New swimming pool and health suite forms part of town regeneration plan
1 hour ago

145 firms win places on £800m building safety framework

Fusion21 confirms latest winners: Full list
17 hours ago

Higgins Homes and site workers face manslaughter charges

Contractor and four site staff charged after woman killed by falling pallet of bricks
2 days ago

Operator spots cracked mast on Hinkley tower crane

Hinkley Point C contractor hit with safety notice over failed mast pin and cracks
1 day ago

Countdown starts for £1bn Birmingham highways bid race

Council will break-up mega framework into five lots
1 day ago

Acciona wins £400m Thames waterworks upgrade

Lea Valley Coppermills water treatment works to get full overhaul
1 day ago

Pension giants pledge £25bn for infrastructure push

Seventeen pension providers pledge to invest in projects
1 day ago

Safety row over London tower ducking fire regs by 30cm

Fire union calls on Mayor to block Bromley flats plan over single staircase
1 day ago

Midgard lands £145m deal to build Edition Birmingham

Construction to start shortly on twin residential towers
2 days ago

McAleer & Rushe set to break £500m turnover barrier

Pre-tax profit jumped 16% to £46m last year
2 days ago

Top design team picked for £2.5bn York Central scheme

Massive city centre regen scheme moves to detailed design
2 days ago

MoD to bid £100m command HQ enabling works

Hertfordshire joint forces command centre expansion advances
2 days ago

Failed shed specialist Marbank owed suppliers £10m

Contractor was facing a string of adjudication claims
2 days ago

New scaffolding training trade body launches

Scaffolding Training Alliance formed amid disquiet caused by planned training changes
2 days ago

£1.8bn framework planned for green retrofit drive

Procure Plus to invite bids later this month
2 days ago

Breakthrough for HS2 as first Birmingham tunnel section dug

Balfour Beatty VINCI completes 3.5-mile TBM drive in 652 days
5 days ago

HS2 Curzon Street station redesign approved as timber roof axed

Change to meet stricter fire safety rules and cut maintenance costs
5 days ago

Care home fire trial collapses

Prosecution withdrawn against four firms including Morgan Sindall Property Services
6 days ago

Leicester rebids £22m station revamp after failed tender race

Council opts for ECI route after receiving one bid for project
5 days ago

Kier wins £58m East Coast College rebuild job in Great Yarmouth

Work to start this summer for 1,300-student college
5 days ago

R G Carter wins £28m hospital car park job in King’s Lynn

MSCP paves way for £1.5bn Queen Elizabeth Hospital rebuild in 2027
5 days ago

London to relax green belt building rules

Sadiq Khan shifts position on planning
5 days ago

Willmott Dixon wins Great Yarmouth waterfront deal

North Quay 10.5 acres mixed-use scheme to advance
6 days ago

SIG chief quits to join Travis Perkins

Gavin Slark to leave by the end of this year
5 days ago

Eight take key spots on £250m Prosper framework

Housing and public building upkeep deal for North East awarded
6 days ago

Contractor services