Inquiry warns hospital build programme in disarray

Aaron Morby 1 year ago
Share

The Public Accounts Committee has no confidence that Government will deliver the new hospitals it promised.

In a highly critical report published today, the PAC voices extreme concern at the New Hospital Programme’s lack of progress.

It warns the recently revised target to construct 32 new hospitals by 2030 rather than 40 as first planned is unlikely to be met.

The Committee says that delays to Hospital 2.0 have eaten into the time available to pilot new standardised designs in real-life scenarios running the risk of baking-in and replicating design and construction problems across England.

The PAC report highlights that most worryingly of all, the latest version of Hospital 2.0 is based on assumptions that appear very likely to produce hospitals that are too small.

Delays to signing off standardised design principles has also hindered meaningful engagement with the construction industry on the details of the design and the commercial pipeline of work.

Dame Meg Hillier MPm chair of the PAC, said that big questions remain to be answered about the industry’s capacity and appetite to build the required number of hospitals in the new way and to a very tight timetable.

It also challenges the plan to bolt the rebuilding of seven RAAC impacted hospitals on to the back of the revised programme risks some hospitals having to close before replacements are ready.

“The physical edifice that is the NHS is quite literally crumbling before our eyes. There was nothing inevitable about this heartbreaking crisis.

“It can be laid squarely at the door of the decision to raid budgets reserved for maintenance and investment in favour of day-to-day spending.

“The sharp distinction between capital and revenue budgets exists for a reason. We are now seeing the consequences of this short-termism visited on patients and services.”

She added: “Quite aside from the fact that the planned new hospitals risk being too small for future purposes, funding does not even appear to be in place to construct them in time, all underpinned by failures of basic record-keeping and fresh and urgent concerns over RAAC.

“Though we have no confidence that the NHP will deliver on its current promises, we hope that the recommendations in our report help to get it back on track – for the sake of all citizens who desperately need the NHS to get well soon.”

Recommendations:


The Department for Health is being urged to consider:

Whether more new hospitals should commence construction sooner using pre-existing approaches to design and contracting.

Start construction before the end of 2025 on replacements for the seven entirely RAAC hospitals.

Aim to be ready to start construction during 2024 of at least one early scheme that uses its standardised hospital design, with a particular focus on trialling new clinical infrastructure such as standardised operating theatres.

Amend its Minimum Viable Product version of Hospital 2.0 so it does not result in future hospitals that are too small, and should set out clearly how these future hospitals fit into its assessment of total required hospital capacity nationally and by region.

Avoid reducing planned capital investment to meet day-to-day spending needs in future

Latest news

Six guilty of £2m bribery over Devon housing site deals

Corrupt building bosses and E.ON project chief and QS sentenced
4 days ago

1,650 former ISG staff launch legal claims

Redundancy Payment Service facing payout of more than £9m
4 days ago

Plans lodged for £1bn cancer research centre in Sutton

London Cancer Hub will deliver around 1m sq ft of lab and research space
3 days ago

London Met Uni seeks firm for £284m estate revamp

Contractor wanted to deliver capital works and FM
3 days ago

Delayed £2bn estate rebuild back on as Berkeley signs deal

Birmingham council development agreement paves way for 2028 Ladywood start
4 days ago

Tilbury Douglas boosts margin to 2.1% as profits double

Firm targets 3.5% margin by 2029 under new business plan
4 days ago

Subbies battle for fastest bricklayer title

Winchmore management team go back on the tools
4 days ago

Green light for revised McLaren Reading revamp

Mixed-use plans to transform Broad Street Mall site
3 days ago

Three arrested in Blu-3 and Mace bribery probe

Serious fraud office swoops over alleged £3m bribes to former Mace associates
4 days ago

Scotland’s most complex A9 dualling job heads to market

Market testing starts for £205m Pitlochry to Killiecrankie 6.4km upgrade
4 days ago

Unite signs £390m student beds JV with Manchester Met

Construction at Cambridge Halls site to start next year
4 days ago

Turkish contractor Limak to build new Luton Town stadium

Construction to start this summer on 25,000-seater venue
5 days ago

Kitchen fitter crushed to death by concrete blocks

House builder goes into liquidation before court case
4 days ago

Mears clinches £230m renewal for key Milton Keynes housing deal

Housing upkeep contractor achieves 100% renewal rate in bust rebid period
4 days ago

Murphy on board at new £32m rail station

Construction to start next year at Golborne station
5 days ago

HS2 engineers finish UK’s heaviest bridge slide early

A46 Kenilworth Bypass reopens 30 hours earlier than planned
5 days ago

Bowmer + Kirkland to build £190m Oxford science scheme

Work to start at end of next month on 180,000 sq ft Fabrica scheme
5 days ago

New BAM leisure centre pool springs a leak

Contractor investigating "technical issues" delaying new £36m green leisure centre
6 days ago

United Living lands £250m HyNet pipeline deal

Firm wins deal to design and build over 34km of pipework to collect CO2
5 days ago

Hydrogen diggers get green light to use roads

JCB hails historic decision for advance of hydrogen-fuelled plant on sites
5 days ago

Go-ahead for McAleer & Rushe Glasgow student job

£100m funding deal paves way for 591-bed student tower
5 days ago

Fly-tippers to get their vehicles crushed

Drones will be used to identify cowboy construction waste operators
5 days ago

Green light for £150m West End office revamp

Shaftesbury Avenue office retrofit retains 75% of original building
6 days ago

Morgan Sindall lands £30m Brunswick Wharf scheme in Bideford

North Devon waterside project will provide 100 flats
6 days ago

Former Keltbray managers jailed after corruption trial

Jail sentences following bribery probe on jobs including Battersea Power Station
6 days ago

Lidl pumps £500m into store and logistics expansion

Discounter plans 40 new stores this year as expansion ramps up
6 days ago

JJ Rhatigan UK profit jumps as turnover tops £150m

Irish contractor's expansion in England gathers pace
6 days ago

Driverless digger to be used on Taylor Woodrow site

Autonomous excavator to work at Manchester Airport after successful trial
6 days ago

MCS Build lands Basingstoke warehouse scheme

Construction starts this month after £26m funding deal
6 days ago

Leeds United unveil stadium revamp design

Club has still to set a timeframe for staged Elland Road upgrade
6 days ago

Contractor services