Just 10% of £10bn Levelling Up funding spent by councils

Aaron Morby 1 year ago
Share

Just over 10% of the Government’s promised Levelling Up funds have actually been spent and are making a difference on the ground.

Watchdog MPs on the Public Accounts Committee also found the Government was unable to provide any compelling examples of what Levelling Up funding has delivered so far.

In a report published today, the committee MPs warn that councils have been able to spend just a fraction of the Government’s promised funding.

The public accounts committee said barely any of the first funding tranche of 71 “shovel-ready” projects due to be completed this month were on track. Most had reprofiled their spend into 2024-25.

The report says that, of £10.47bn in total funding from central government, which must be spent between 2020-21 and 2025-26, so far only £3.7bn has been dished out to local authorities.

And of that sum local authorities have only managed to spend £1.24bn as of September 2023.

Dame Meg Hillier MP, Chair of the Committee, said: “The levels of delay that our report finds in one of Government’s flagship policy platforms is absolutely astonishing.

“The vast majority of Levelling Up projects that were successful in early rounds of funding are now being delivered late, with further delays likely baked in.

“DLUHC appears to have been blinded by optimism in funding projects that were clearly anything but ‘shovel-ready’, at the expense of projects that could have made a real difference.

“We are further concerned, and surprised given the generational ambition of this agenda, that there appears to be no plan to evaluate success in the long-term.

“Our Committee is here to scrutinise value for money in the delivery of Government policy. But in the case of Levelling Up, our report finds that the Government is struggling to even get the money out of the door to begin with.

“Government has not helped the situation by changing the rules for funding mid-process, wasting time and money and hindering transparency.

“We will now be seeking to keep a close eye on DLUHC’s progress in unclogging the funding system. Citizens deserve to begin to see the results of delivery on the ground.”

 

 

Latest news

Tide gets go-ahead for over 1,000-home London scheme

Volumetric expert gains planning for co-living homes scheme in Southwark
13 hours ago

Construction output flickers into life in March

First quarter activity flatlines after slow start to year
16 hours ago

Skanska lifts margin to 4.3% as profit hits £78m

Infrastructure and FM drive near-tripling of profits
1 day ago

Mayor backs 46-storey student tower at Canary Wharf

City Hall overturns Tower Hamlets council rejection of 912-bed scheme
24 hours ago

Plans go in for 100 acre Port of Tilbury expansion

Construction could start next year on site the size of 70 football pitches
15 hours ago

Inland Homes creditors face £38m hit

Administrator confirms no cash for supply chain
1 day ago

Durkan dogged by legacy jobs despite return to trading profit

Durkan scales down new homes contracting to focus on retrofit work
1 day ago

Munnelly founder hands over CEO role to son

Paul David Munnelly steps up to CEO as father becomes chairman
16 hours ago

Barking build to rent towers face rebuild

Major remedial work needed on resi scheme built by Shapoorji Pallonji UK Ltd
2 days ago

London new home starts plunge 38% as Building Safety Act bites

Capital only region to see Q1 fall in NHBC new home registrations
2 days ago

Sureserve swoops for rival compliance outfit Kinovo in £56m deal

Recommended cash offer will take AIM listed contractor private
2 days ago

Crown Golf tees up £1bn plan to build 3,000 homes on course land

Major housing plan for spare land on eight UK courses
2 days ago

Green light for Peterborough Station Quarter £48m revamp

First phase to start before the end of the year
2 days ago

Morgan Sindall starts £38m Caerphilly leisure hub

New swimming pool and health suite forms part of town regeneration plan
2 days ago

145 firms win places on £800m building safety framework

Fusion21 confirms latest winners: Full list
2 days ago

Higgins Homes and site workers face manslaughter charges

Contractor and four site staff charged after woman killed by falling pallet of bricks
3 days ago

Operator spots cracked mast on Hinkley tower crane

Hinkley Point C contractor hit with safety notice over failed mast pin and cracks
3 days ago

Countdown starts for £1bn Birmingham highways bid race

Council will break-up mega framework into five lots
3 days ago

Acciona wins £400m Thames waterworks upgrade

Lea Valley Coppermills water treatment works to get full overhaul
3 days ago

Pension giants pledge £25bn for infrastructure push

Seventeen pension providers pledge to invest in projects
3 days ago

Safety row over London tower ducking fire regs by 30cm

Fire union calls on Mayor to block Bromley flats plan over single staircase
3 days ago

Midgard lands £145m deal to build Edition Birmingham

Construction to start shortly on twin residential towers
3 days ago

McAleer & Rushe set to break £500m turnover barrier

Pre-tax profit jumped 16% to £46m last year
4 days ago

Top design team picked for £2.5bn York Central scheme

Massive city centre regen scheme moves to detailed design
4 days ago

MoD to bid £100m command HQ enabling works

Hertfordshire joint forces command centre expansion advances
4 days ago

Failed shed specialist Marbank owed suppliers £10m

Contractor was facing a string of adjudication claims
4 days ago

New scaffolding training trade body launches

Scaffolding Training Alliance formed amid disquiet caused by planned training changes
3 days ago

£1.8bn framework planned for green retrofit drive

Procure Plus to invite bids later this month
4 days ago

Breakthrough for HS2 as first Birmingham tunnel section dug

Balfour Beatty VINCI completes 3.5-mile TBM drive in 652 days
6 days ago

HS2 Curzon Street station redesign approved as timber roof axed

Change to meet stricter fire safety rules and cut maintenance costs
7 days ago

Contractor services