Three-year HS2 station box excavation completed

Grant Prior 10 months ago
Share

Workers on HS2’s new super-hub station at Old Oak Common in west London have completed the excavation of the huge underground box structure where high speed trains will stop.

The excavation has taken three years after permanent construction to form the walls of the box began in June 2021.

The vast underground box has a 1.12 mile fibre-reinforced concrete diaphragm wall around it, and 1.3million tonnes of London Clay has been removed from inside – enough to fill over 300 Olympic sized swimming pools.

HS2’s Station Construction Partner, Balfour Beatty VINCI SYSTRA joint venture (BBVS JV), working with their specialist structures contractor Expanded, completed the excavation with apprentice Miguel Jardim removing the last of the London clay from the box.

Jardim, 19, a civil engineering apprentice from Surrey Quays, south east London, joined in the landmark excavation at Old Oak Common as the 1,500th apprentice to start a role helping to build HS2.

He said: “It is quite an honour to be part of celebrating such a massive excavation milestone – the opportunity came along very unexpectedly!

The excavation was completed section by section within the box starting from the west and the east of the structure and meeting in the middle.

The box is 20m in depth and a reinforced concrete base slab up to 2m in depth is being poured throughout and 32,000 tonnes of steel rebar, assembled by hand on site, has been used in the box alongside 160 reinforced concrete columns which have been installed inside the outer wall to help support the structure.

Now the box has been fully excavated the team will be working to pour the final sections of base slab to complete it.

Six 450m platforms will be constructed in the underground box for HS2 services. Above ground, eight further platforms are being built, and will be served by the Elizabeth Line, Great Western Mainline services and the Heathrow Express. Old Oak Common station will become one of the country’s most vital transport hubs which will be directly connected on the UK’s railway network to more than 170 destinations.

Sam Clark, Head of Delivery for HS2 Ltd, said: “The tremendous progress made by our construction team to complete the excavation of the box is an exciting milestone for the project as it signals the next phase of construction where high speed platforms will be built, as well as the station building itself.

“HS2’s Old Oak Common station will be transformational for local and regional connectivity and attract huge investment, development and regeneration to the surrounding area.”

The huge amount of London Clay removed in the excavation has been taken away from site by conveyor, reducing lorry movements on local roads.

The conveyor, run by the Subcontractor Fairport, took the spoil to the nearby London Logistics Hub, managed by Skanska Costain STRABAG (SCS JV), from where it has been transported by rail to beneficial reuse sites in Kent, Warwickshire and Cambridgeshire.

Coinciding with the excavation of the box, HS2 has decommissioned the Old Oak Common station conveyor which has removed over 75,000 lorries from the road since it’s operation in November 2022. Further spurs of the conveyor being used for HS2’s tunnelling operation in the area remain in use.

Steve O’Sullivan, Project Director, Balfour Beatty VINCI SYTRA joint venture, said: “This achievement is a testament to the dedication and hard work of our team, and in particular the valuable contributions of our apprentices like Miguel.

“The progress here at Old Oak Common moves us one step closer to completing this key transport hub, which will enhance connectivity and drive regeneration in the area. We are excited to move forward to the next phase of construction and continue delivering this transformative project.”

The east end of the underground box has been handed over to HS2’s London Tunnels contractor, SCS JV, who are preparing to construct HS2’s running tunnel to Euston.

Two giant tunnel boring machines will be lowered into the underground box later this year, before the station team commencing building the roof structure of the super-hub station. Timings and funding for the construction of the Euston Tunnel are being confirmed with government.

Latest news

Breakthrough for HS2 as first Birmingham tunnel section dug

Balfour Beatty VINCI completes 3.5km TBM drive in 652 days drive
2 days ago

HS2 Curzon Street station redesign approved as timber roof axed

Change to meet stricter fire safety rules and cut maintenance costs
2 days ago

Care home fire trial collapses

Prosecution withdrawn against four firms including Morgan Sindall Property Services
3 days ago

Leicester rebids £22m station revamp after failed tender race

Council opts for ECI route after receiving one bid for project
2 days ago

Kier wins East Coast College rebuild job in Great Yarmouth

Work to start this summer for 1,300-student college
2 days ago

R G Carter wins £28m hospital car park job in King’s Lynn

MSCP paves way for £1.5bn Queen Elizabeth Hospital rebuild in 2027
2 days ago

London to relax green belt building rules

Sadiq Khan shifts position on planning
2 days ago

Willmott Dixon wins Great Yarmouth waterfront deal

North Quay 10.5 acres mixed-use scheme to advance
3 days ago

SIG chief quits to join Travis Perkins

Gavin Slark to leave by the end of this year
2 days ago

Eight take key spots on £250m Prosper framework

Housing and public building upkeep deal for North East awarded
3 days ago

Early call-out for £150m Ebbsfleet Garden City infrastructure

Bidders day to set out plan for Ebbsfleet Central commercial scheme
4 days ago

McLaren storms April contracts league with flurry of wins

Cardiff Bay Arena job headlines a series of big contract wins
3 days ago

Balfour Beatty lifts cash forecast after strong first quarter

Contractor set to hit £1bn average monthly net cash in 2025
3 days ago

Goldman Sachs-owned Adler & Allan buys 180-strong civils outfit

West Country's Glanville Environmental gets new owner
3 days ago

Caddick lands first contract for £200m Skelmersdale revamp

Developer gets green light for masterplan
3 days ago

Van Elle sells HGV fleet to haulage firm

WS Specialist Logistics pays £2.9m to take on fleet and drivers
3 days ago

Buyers more bullish about prospects for year ahead

Residential "resilient" but commercial work a weak spot
4 days ago

Council backs first Brutalist car park-to-flats scheme

Newcastle-under-Lyme multi-storey car park to be reborn as pioneering homes scheme
4 days ago

Hinkley Point C hits peak build with 26,000 jobs

3,000 more workers to join as fit-out work ramps up
4 days ago

Over 40 firms win Wessex Water M&E minor works deal

Broad sweep of specialists picked for AMP8 programme
4 days ago

Spencer lands Scottish bridge hat-trick

Steelwork, gantries and bearing upgrades on Kessock, Forth and Tay crossings
5 days ago

Winners revealed for £1.5bn decarbonisation deal

Fusion21 confirms places for 40 firms: Full list
4 days ago

Cladding firm fined £225,000 after fatal fall

Court hears how cherry picker didn't reach all parts of repair job
4 days ago

Completed buildings caught-up in Gateway 2 chaos

Developer distraught after dealing with Building Safety Regulator
5 days ago

Aviva submits plans for 34-storey City office tower

Subject to planning work to start in autumn 2027
5 days ago

Murphy takes 40% stake in Aussie civils contractor

Firm enters Australasian market with stake in Sydney-based contractor Abergeldie
6 days ago

Moat seeks firm for £420m repairs and maintenance deal

15-year deal to upkeep 20,000 south east homes
5 days ago

Lynch takes over hotel for Sizewell plant operators

Hire giant now in the hotel business to guarantee accommodation for workers
5 days ago

Subcontractors wanted across Scotland

Latest Constructionline event in Glasgow: Register now
5 days ago

Six guilty of £2m bribery over Devon housing site deals

Corrupt building bosses and E.ON project chief and QS sentenced
1 week ago

Contractor services