Mark Wild radical reset plan to rescue HS2

Aaron Morby 11 hours ago
Share

The Government has revealed HS2 chief executive Mark Wild’s reset plan to rescue the troubled rail megaproject.

Renegotiating main works civils contracts will form a key part of Mark Wild's turn around plan
Renegotiating main works civils contracts will form a key part of Mark Wild's turn around plan

In a blunt letter to transport secretary Heidi Alexander, Wild said a “comprehensive reset” was now essential to deliver the railway on a credible timescale and within a realistic budget.

The letter sent at the end of March but published for the first time yesterday, reveals that just one-third of the civils work is complete, compared with the 75% planned by now.

Wild’s big reset hinges on simplifying the railway opening plan. He also pledged to overhaul HS2 Ltd’s structure, and renegotiate supply chain contracts. Going forward, Wild said there would be much closer alignment with Government on scope and funding.

Rather than halting construction for the reset, Wild confirmed HS2 Ltd would press on with productivity drives in 2025/26, focusing only on work essential to the reset.

HS2 has already reduced the number of non-permanent labour contractors. Performance-related pay rises for senior managers and excutive bonuses relating to last year have been scrapped.

Wild’s four-point HS2 reset strategy


  1. Simplify the opening phase – by trimming features like automatic train operation and opening at lower speeds to reduce risk and allow earlier services.

  2. Reset the supply chain – with new commercial terms to incentivise cost control. Wild warned that regaining control of the Main Works Civils Contracts will require tough negotiations and possibly robust government backing.

  3. Restructure HS2 Ltd – by cutting corporate excess, filling delivery gaps, and creating a leaner, expert team focused on outcomes.

  4. Rebuild alignment with Government – on scope, costs and timelines to ensure decisions are made quickly and progress stays on track.

Wild said the new baseline cost and schedule would be finalised by April 2026, with initial technical advice on sequencing due this summer.

His letter gave a damning early assessment of HS2’s progress, which he described as “systemic failure”.

“There is a lack of accountability, with individuals feeling disempowered to make decisions or drive change,” Wild warned. “HS2 Ltd does not operate like an expert builder of a railway.”

He revealed that costs have ballooned to £61.8bn (excluding Euston) – up from the original £44.6bn – and that the current 2029–2033 target to open between Old Oak Common and Birmingham is no longer achievable.

Testing schedules have also been badly underestimated, with just 14 months allocated rather than 36 months that he said would likely be needed.

Three core failings were identified:

  • Construction began too early with unstable designs and unrealistic timelines, leading to inefficiencies and major delays.

  • Flawed contracting model handed too much risk to HS2 Ltd while failing to incentivise cost control among contractors.

  • An unbalanced and bloated organisation, with delivery teams understaffed and the corporate centre overgrown.

Wild warned that cultural and capability issues ran deep but stressed that a committed, skilled workforce and the backing of Government could still turn the project around.

Latest news

10-Year Infrastructure Strategy published

Full details as Government pledges £725bn of funding over the next decade
4 hours ago

Competition watchdog turns attention to civil engineering

Competition and Markets Authority launches study into road and rail delivery
5 hours ago

Korean firm buys part built Hackney job from failed Elements Europe

Work can now restart on 21-storey hotel and office development
7 hours ago

Mark Wild radical reset plan to rescue HS2

Senior manager bonuses scrapped and non-permanent labour cutback
11 hours ago

HS2 supply chain fraud claims spark ministerial probe

Transport secretary pledges one-year reset for HS2 to end 'litany of failures'
1 day ago

Lords launch inquiry into Building Safety Regulator delays

Industry asked for evidence of how system is failing: Have your say
18 hours ago

Willmott Dixon director becomes co-owner of local contractor BSN

Nick Gibb targets £100m turnover at Dudley based national contractor
1 day ago

Dry lining boss sentenced after mystery account moves

Court hears of £500,000 in unexplained transfers before contractor went under
11 hours ago

Barhale bags £16m shaft tank for Severn Trent Water

"Final piece in the puzzle" of Etruria Vale upgrade
9 hours ago

Keltbray strikes £30m funding deal for growth

Three-year funding deal to support push into higher-margin work
1 day ago

Take That brother buys steelwork giant William Hare

Entrepreneur Simon Orange seals deal for £350m turnover contractor
2 days ago

Civils contractor LF Solutions files administration notice

£20m-turnover specialist has labour supply arm and own plant fleet
1 day ago

Joseph Gallagher lands £50m green energy deal

Major trenchless construction contract for HyNet North West project
1 day ago

New boss drives NG Bailey to record revenue

Fresh strategy lifts M&E group's order book to £1.6bn
2 days ago

Costain wins vast underground hydrogen storage design job

Firms lands FEED contract for Cheshire salt caverns conversion
1 day ago

Graham gets green light for £70m Glasgow student tower

Construction due to start this year on 25-storey Anderston scheme
1 day ago

New £16bn National Housing Bank to drive 500k new builds

Homes England given new powers to finance stalled and complex schemes
2 days ago

Morgan Sindall upgrades profits forecast for this year

Overbury fitout and construction operations exceed trading expectations
2 days ago

Major project bidders to face ‘British jobs’ test

Contractors to face tougher jobs pledge scrutiny under new procurement shake-up
3 days ago

Green light for £32m Wythenshawe Culture Hub

Construction to start this year on first phase of £500m town centre revamp
2 days ago

Hercules delivers record first half as HS2 fuels growth

Labour supply specialist says HS2 demand climbing with 630 workers now deployed
2 days ago

Private equity firm acquires Hepworth Clay pipes business

Historic UK drainage manufacturer sold by Wavin
2 days ago

Balfour Beatty names new Scottish MD

Nick Rowan to take reins as Hector MacAulay to retire after 40 years
3 days ago

£500m rail deal locks in future for Scunthorpe steelworks

Government-backed deal with Network Rail safeguards UK production
2 days ago

Morrison rides in for £19m mountain bike R&D hub

Flagship Borders cycling R&D hub set for Caerlee Mill site
3 days ago

Revised plan submitted for Manchester landmark towers

400 more flats added to Albert Bridge House scheme
3 days ago

Job losses loom at consultant GHD

Redundancy consultation underway with jobs at risk
3 days ago

Knight Harwood lifts margin to 4.9% as profit hits £6.5m

London specialist sees strong office and luxury resi pipeline
3 days ago

Hampshire launches £150m minor works reboot

General builders, M&E and roofing firms invited to apply
3 days ago

Winners named for £2.6bn NHS SBS Modular 3 framework

Twenty-seven secure spots on health, education and resi framework
6 days ago

Contractor services