Carillion defends 120 day payment terms

Grant Prior 11 years ago
Share

Carillion has published a defence of its controversial move to extend payment terms for subcontractors to 120 days.

The move has sparked a barrage of complaints online as outraged trade contractors have taken to Twitter to voice their opposition to the plan.

The new policy also includes an “Early Payment Facility” which allows suppliers to be paid ahead of schedule if they pay a fee to Carillion’s bankers.

Carillion has now posted an online statement clarifying the position and confirming that its standard payment terms where extended to 120 days late last year.

The firm said:  “There has been some negative coverage recently about our payment terms. We would like to take this opportunity to set the record straight and provide further information about our payment terms and Early Payment Facility (EPF).

We have a very wide range of payment terms which are negotiated with all of our suppliers on an individual basis.

“These range from our standard terms, which we extended last year to 120 days, to payments in advance for some of our smaller suppliers.

“We are also working on a range of initiatives that will help to improve access to credit and cash flow management for our supply chain.

“One of these initiatives is our Early Payment Facility (EPF) which we relaunched last year in support of the Government’s Supply Chain Initiative which aims to improve cash flow in the supply chain.

“A large number of key suppliers have already signed up to the scheme and the feedback has been very positive. Many more suppliers are in the process of joining as they recognise the benefits.”

Carillion also published a guide to the new Early Payment Facility:


How does the Early Payment Facility work?

1. The EPF programme enables many suppliers to receive payments against approved invoices in advance of their current contractual terms and this facility is being rolled out progressively to our suppliers. Please refer to this leaflet for further details about the EPF.

2.  Carillion is not charging for this facility and payments will continue to be made to suppliers in line with existing terms at no cost. The only fees associated with this facility are those incurred when the supplier chooses to access funds earlier than the existing payment terms.

3.  Independently of this, Carillion is increasing standard payment terms to 120 days with a Supplier Incentive Scheme in place to ensure the supplier’s financial position is not detrimentally affected by the change in terms versus current position. But, as already explained, payments will continue to made against existing terms at no cost, including those subject to Public Sector Fair Payment Charters.

4.  Irrespective of current payment terms, all preferred suppliers will have the opportunity to access payment early through the EPF at very competitive bank rates; far lower than most small and medium sized businesses (SME’s) would be able to access via traditional routes.

5.  Suppliers who work on contracts subject to Public Sector Fair Payment Charters will be able to receive payment in line with those terms at no cost to themselves.

6.  In essence, our EPF gives our suppliers access to working capital by enabling them to borrow against Carillion’s balance sheet, either at no cost to themselves, or at fees that are more competitive in comparison with typical bank borrowing.

This initiative is designed to help businesses, particularly small and medium sized enterprises (SME’s) to improve their cash flow and reduce their borrowing requirements at a time when many SMEs are unable to borrow from banks.


Frequently Asked Questions

Q. Is it expected that all Carillion suppliers extend their terms?

A. Carillion has a very wide range of payment terms ranging from payments in advance up to our standard terms. We negotiate payment terms with all our suppliers on an individual basis and we are working on a range of initiatives, such as the EPF, which will help to improve access to credit and cash flow management for our supply chain.

Q. Why is Carillion requesting that suppliers extend payment terms whilst also providing the EPF which enables them to get paid ‘early’? Why not just stick to original terms and pay in line with these?

A. The extension of our standard payment terms provides Carillion with greater payment flexibility. But, as already explained, all of our suppliers have the opportunity to use our EPF, regardless of the terms that they are on, to receive payments either earlier than they do now, or no later, at no cost to themselves.

Latest news

Carpenter killed by falling timber frame panels

Court fines specialist contractor £8,000 after site tragedy
3 hours ago

Road sweeper specialist files administration notice

Go Plant lodges court notice
9 hours ago

Anglian Homes rides in to finish crashed Everest contracts

Rival doubled glazed window specialist commits to complete orders
8 hours ago

Final work starts to connect super sewer to London system

End in sight with 1.5m thick concrete wall to be demolished to link-up to Lee Tunnel sewer system
9 hours ago

Legal challenge launched against £1.5bn A66 dualling

Balfour Beatty, Kier and Keltbray must now await outcome of court challenge
9 hours ago

John F Hunt wins 24-storey Battersea tower

Specialist to carry-out demolition, enabling works and RC frame construction
1 day ago

William Hare wins steelwork on £500m Broadgate towers

Specialist to work on 2 Finsbury Avenue with McAlpine
1 day ago

McAlpine appoints MD to grow ventures business

Owain Thomas will build on private rental and healthcare development successes
1 day ago

BAM Co-op Live Arena opening delayed yet again

Another gig cancelled last night amid last minute safety concerns
1 day ago

National Grid unveils winners for £9bn network upgrade

New 'enterprise model' to deliver infrastructure schemes quicker and cheaper
2 days ago

Turkish insulation panel maker to build £45m UK factory

Assan Panel to open first UK plant at Freeport East
1 day ago

Expanding consultant Stantec swoops for Hydrock

Stantec UK business expands by a third as 950 staff join from Bristol-based engineer
2 days ago

Contractors wanted for £800m highways deal

Bids invited for Eastern Highways Alliance Framework 4
1 day ago

Galliford Try names group head of infrastructure

David Lowery promoted to Divisional Managing Director – Infrastructure.
1 day ago

Chigwell Group looks at stock market listing

Essex contractor registers as Public Limited Company
2 days ago

A57 Mottram Bypass clears final legal challenge

Balfour Beatty to get go-ahead to start shortly
2 days ago

100 jobs axed as Geoffrey Osborne confirms administration

Chairman Andrew Osborne calls it a 'sad day' as board loses fight for survival
3 days ago

Midgard set for Notting Hill office tower overhaul

Landmark project edges towards final approval after 10-year planning saga
2 days ago

Cumbrian civils firm clinches £40m Sellafield contract

Civils specialist Stobbarts will support McAlpine on groundworks and concrete
2 days ago

Designers named for London 2000-bed student rooms job

Bouygues will build £400m London School of Economics student scheme next to Tate Modern
2 days ago

£117m-turnover contractor files administration notice

ARJ Construction lodges court notice
3 days ago

£1bn London Blackfriars tower blocks approved

Trio of buildings rising to 45, 40 and 22 storeys approved by Southwark Council
3 days ago

Council decides to end Balfour deal after 13 years

Contractor has been maintaining roads across Herefordshire since 2013
3 days ago

Six civils clients to switch to low carbon concrete and steel

National Highways, Northumbrian Water and Sellafield sign fresh decarbonising pledge
4 days ago

Fortem extends homes repair deal across Birmingham

Willmott Dixon owned firm adds another two years to deal worth £170m
3 days ago

Kier wins £118m civil service Darlington hub

Work is expected to start towards the end of this year
4 days ago

Green light for 34-storey Digbeth apartments tower

480 flats will be delivered for Clarion housing association
3 days ago

LHC starts race for major retrofit and decarb framework

Hunt starts for firms to help with 6.1m social homes upgrade target
4 days ago

Windows giant Everest crashes into administration

Around 350 jobs at risk while hunt starts for a buyer to salvage business
4 days ago

Green light for £500m Newcastle health complex

Mixed use scheme will promote healthy living across all stages of life
4 days ago

Contractor services