The cost of repainting and repairing Newport Bridge has risen from £1.6m to £4.1m.

Works by main contractor Pyeroy will also take much longer than the original timescale after significant areas of corrosion were discovered on the Grade II structure.

Pyeroy started repairs on the 80-year-old bridge in July with work scheduled to be completed by next month.

The completion date has now been put back to next Spring.

But motorists should be able to use the A1032 which runs across the bridge by the end of this month after Stockton Council changed the way works are carried-out.

The amended project will see a large tunnel style scaffold constructed which will allow the A1032 to fully re-open so motorists can use the road while the remaining repairs and painting take place.

Stockton Council’s Cabinet Member for Regeneration and Transport, Councillor Mike Smith, said: “We know how well used the A1032 is and appreciate the frustration its closure has caused so we are working hard to construct the scaffold tunnel as soon as possible.

“Once it is complete, motorists will be able to use the road as usual.

“The damage that has been found is a lot worse than we anticipated so we have reacted decisively to change the repair and painting programme.

“It would be counter-productive to carry out a quick ‘patching-up’ exercise as this would result in us having to re-close the bridge to carry out more extensive works in a couple of years.

“We have a duty to maintain this iconic structure and it is important that we repair it properly now to prevent even more disruption in future.

“We carefully plan our finances so we have sufficient contingency reserves to cope with circumstances like this.

“Consequently, we have committed £4.1 million to pay for the revised programme so that motorists can use the road while the works take place.”

Latest news

Osborne staff start looking for new jobs

"Open to Work" flags appear on LinkedIn profiles
3 days ago

Plan rejected for 42-storey tower above historic building

Councillor describes as ludicrous plan to build 300 flats above Georgian mansion
3 days ago

Ventilation deal could hike product prices for contractors

Watchdogs at CMA launch probe after duct firm acquires rival
3 days ago

Tide gets go-ahead for London 412 student flats scheme

Volumetric developer secures planning for West Ealing project
3 days ago

Green light for £75m Friar Gate Goods Yard in Derby

Construction set to start this summer on revamp of historic buildings
3 days ago

Robertson to deliver £45m Newcastle NHS Trust works

Capital works will be focused on Freeman Hospital and the Royal Victoria Infirmary sites
3 days ago

Winners named for £2bn Healthy Homes framework

CHIC reveals line-up of over 40 firms for net zero and building safety works
3 days ago

Plan lodged for tallest skyscraper outside London

Developer Salboy submits plan for 76-storey Manchester resi tower
4 days ago

Curo starts £170m race for new homes framework

Bath housing association plans to build up to 300 homes a year
4 days ago

Gove approves major Cambridge North mixed-use scheme

Government backs controversial scheme of 424 flats and 600,000 sq ft of tech and lab space
4 days ago

Pontins holiday park to house Sizewell C builders

Suffolk holiday park to house 500 nuclear construction workers
4 days ago

Adrian Bloor targets 1,000 homes-a-year

Expansion plans after major investment into challenger house building business HarperCrewe
4 days ago

Housing firm fined £528,000 after cable strike

Maintenance workers given no information on underground services
4 days ago

Berkeley subbies face six weeks without payments

Introduction of new finance software means payment hiatus for suppliers
5 days ago

Pagabo reveals 56 winners of latest £1.6bn retrofit deal

Decarbonisation Solutions Framework launched: Full list of winners
5 days ago

Go-ahead for £100m Liverpool Love Lane flats

500-flat scheme will be built across four blocks in Vauxhall area of city
5 days ago

Unions win HS2 site access battle at Old Oak Common job

Skanska, Costain, Strabag JV now the last denying unions access to HS2 sites
5 days ago

Contractors jack 1,100t viaduct into place in 13-hour operation

158m-long composite deck structure jacked into place 10-hours ahead of schedule
5 days ago

Wates wins former Daily Mail printworks transformation

British Land advances major cultural venue at London’s Canada Water
6 days ago

Mace poaches Ramboll chief to be Head of Engineering

Martin Feakes will develop civil and structural engineering offer at Mace
5 days ago

Subcontractors form alliance for major civils jobs

Trio of specialists join forces to collaborate and offer Tier 1 contractors a turnkey solution
6 days ago

Fear of supply chain failures boosting collaboration

Procurement survey also reveals project bank account use is rising
6 days ago

Wates sets up business to target 160,000 mouldy social homes

Healthy Homes service will be offered to social landlords across England
6 days ago

Higgins wins £75m Peabody Passive House job

Latest phase of Deptford Landings to start construction
6 days ago

Contractors and unions agree Sizewell C working deal

New deal offers improved sick pay and parental leave over Hinkley Point deal
6 days ago

Competition chiefs win legal fight for more construction raids

High Court rules CMA officials can raid a domestic property as part of investigation
6 days ago

More Osborne companies file administration notices

Three more divisions lodge notices with court
7 days ago

McLaren wins multi-storey urban logistics contract

South London win with British Land is pioneering urban logistics hub
7 days ago

Big social housing schemes at risk over funding uncertainty

Housing associations warn uncertainty over public funding beyond 2026 is curbing new schemes
7 days ago

Kier wins Worcestershire town centre renewal

Firm secures Bromsgrove commercial and cultural hub project
7 days ago

Contractor services