First new roof panel installed at Olympic Stadium

Grant Prior 9 years ago
Share

The first piece of roof panelling has been lifted into place at the Olympic Stadium.

The 1 x 4.4 metre roof panel is the first of almost 10,000 panels to be fitted to the Stadium.

The roof will be split into two sections, a solid rear section and a translucent forward section. There will be 6,300 rear panels and 3,600 transparent polycarbonate panels at the front.

The initial lift comes after several weeks of preparation works.

Eight kilometres of cable net weighing 930 tonnes was lifted and connected over a four week period before 112 steel roof rafters, the longest of which is 38 metres, were lifted and secured into place.

Main contractor Balfour Beatty struck a deal last month with the London Legacy Development Corporation for an extra £36m for the conversion contract.

This has driven the original project cost up by nearly a quarter to close to £190m to convert the stadium into a new home for West Ham United.

Balfour was awarded the contract in January and is running against a fixed deadline to complete the first phase of the conversion to host games for the 2015 Rugby World Cup.

After the tournament Balfour will return to finish the conversion and create a permanent home for West Ham from 2016.

When complete the new roof will be twice the size of the original at around 45,000 square metres.

At 84 metres at its deepest point it will be the longest cantilevered roof of its type in the world and will cover every seat in the Stadium.

David Goldstone, Chief Executive of the London Legacy Development Corporation said: “Installing the first roof panel represents another significant milestone in the transformation of the Stadium into a world class multi-use venue.

“The overall spectator experience, whether that’s at a football match, concert or other sporting event, will improve significantly and the Stadium will become a great addition to Queen Elizabeth Olympic Park which is already proving to be a top destination for world-class events of all kinds.”

Karren Brady West Ham United Vice-Chairman said:  “The roof is just one of the superb features that will make our new home one of the greatest stadiums in world football and a fitting legacy for the venue that did Britain so proud in 2012.”

To see latest pictures from the stadium site click here

Facts about the Stadium roof

  • At 45,000sq metres, the new roof will be twice the size of the original.
  • At 84 metres at its deepest point it will be the longest cantilevered roof of its type in the world.
  • The new roof will cover every seat in the Stadium.
  • The design is intended to improve the acoustics and spectator experience for football matches, other sporting events and concerts.
  • New floodlights will be installed that will reuse the light bulbs from the original Stadium lights.
  • Work will be completed ahead of Rugby World Cup 2015.
  • Eight kilometres of cable net ranging in width from 60 to 105 millimetres was lifted and connected over a four week period.
  • The cable net weighs around 930 tonnes.
  • There are 5,423 pieces of steel in the roof, weighing 3,900 tonnes.
  • The longest roof rafters are 38 metres long and it will take 27 weeks to install all the steel.
  • The roof panelling to the rear of the roof is an insulated system using a profiled lower deck with an insulation layer and covering for weather protection.
  • The roof panelling to the front of the roof is formed of transparent polycarbonate corrugated sheeting.
  • It will take 26 weeks to install the roof panelling.

 

Latest news

Carpenter killed by falling timber frame panels

Court fines specialist contractor £8,000 after site tragedy
1 day ago

Road sweeper specialist files administration notice

Go Plant lodges court notice
1 day ago

Anglian Homes rides in to finish crashed Everest contracts

Rival doubled glazed window specialist commits to complete orders
1 day ago

Final work starts to connect super sewer to London system

End in sight with 1.5m thick concrete wall to be demolished to link-up to Lee Tunnel sewer system
1 day ago

Legal challenge launched against £1.5bn A66 dualling

Balfour Beatty, Kier and Keltbray must now await outcome of court challenge
1 day ago

John F Hunt wins 24-storey Battersea tower

Specialist to carry-out demolition, enabling works and RC frame construction
2 days ago

William Hare wins steelwork on £500m Broadgate towers

Specialist to work on 2 Finsbury Avenue with McAlpine
2 days ago

McAlpine appoints MD to grow ventures business

Owain Thomas will build on private rental and healthcare development successes
2 days ago

BAM Co-op Live Arena opening delayed yet again

Another gig cancelled last night amid last minute safety concerns
2 days ago

National Grid unveils winners for £9bn network upgrade

New 'enterprise model' to deliver infrastructure schemes quicker and cheaper
3 days ago

Turkish insulation panel maker to build £45m UK factory

Assan Panel to open first UK plant at Freeport East
2 days ago

Expanding consultant Stantec swoops for Hydrock

Stantec UK business expands by a third as 950 staff join from Bristol-based engineer
3 days ago

Contractors wanted for £800m highways deal

Bids invited for Eastern Highways Alliance Framework 4
2 days ago

Galliford Try names group head of infrastructure

David Lowery promoted to Divisional Managing Director – Infrastructure.
2 days ago

Chigwell Group looks at stock market listing

Essex contractor registers as Public Limited Company
3 days ago

A57 Mottram Bypass clears final legal challenge

Balfour Beatty to get go-ahead to start shortly
3 days ago

100 jobs axed as Geoffrey Osborne confirms administration

Chairman Andrew Osborne calls it a 'sad day' as board loses fight for survival
4 days ago

Midgard set for Notting Hill office tower overhaul

Landmark project edges towards final approval after 10-year planning saga
3 days ago

Cumbrian civils firm clinches £40m Sellafield contract

Civils specialist Stobbarts will support McAlpine on groundworks and concrete
3 days ago

Designers named for London 2000-bed student rooms job

Bouygues will build £400m London School of Economics student scheme next to Tate Modern
3 days ago

£117m-turnover contractor files administration notice

ARJ Construction lodges court notice
4 days ago

£1bn London Blackfriars tower blocks approved

Trio of buildings rising to 45, 40 and 22 storeys approved by Southwark Council
4 days ago

Council decides to end Balfour deal after 13 years

Contractor has been maintaining roads across Herefordshire since 2013
4 days ago

Six civils clients to switch to low carbon concrete and steel

National Highways, Northumbrian Water and Sellafield sign fresh decarbonising pledge
5 days ago

Fortem extends homes repair deal across Birmingham

Willmott Dixon owned firm adds another two years to deal worth £170m
4 days ago

Kier wins £118m civil service Darlington hub

Work is expected to start towards the end of this year
5 days ago

Green light for 34-storey Digbeth apartments tower

480 flats will be delivered for Clarion housing association
4 days ago

LHC starts race for major retrofit and decarb framework

Hunt starts for firms to help with 6.1m social homes upgrade target
5 days ago

Windows giant Everest crashes into administration

Around 350 jobs at risk while hunt starts for a buyer to salvage business
5 days ago

Green light for £500m Newcastle health complex

Mixed use scheme will promote healthy living across all stages of life
5 days ago

Contractor services