See how the Tube was built 150 years ago

Grant Prior 12 years ago
Share

Pictures of construction work on the London Underground have been released to celebrate the Tube’s 150-year anniversary.

The images form part of a major new exhibition at the Museum of London detailing how work first began under London’s streets in the 1860s.

Early labour-intensive “cut and cover” techniques soon gave way to a technique named “the shield”, as engineers looked to build tunnels deep beneath Victorian London.

Transport for London’s design and heritage manager, Mike Ashworth, told the BBC: “The cut and cover method was to dig a trench, build back the side and roof it over.”

It was a simplistic approach to tunnel building, with work happening just below the surface, Mr Ashworth said.

“There was so much disruption caused by demolition through a very crowded city.

“Most roads were already full of gas mains and other utilities and there would have been enormous upheaval as they had to shut roads.”

When Tube engineers adopted the more successful shield method it heralded the transformation of London’s transport network which now serves 270 stations on a service spanning 250 miles.

Ashworth said: “It is highly unlikely that our system would have developed to such an extent if it hadn’t left cut and cover.”

The shield, which was the technique used as the Underground expanded, was first successfully used in 1825 to excavate what is now the Wapping – Rotherhithe tunnel, which was one of the first underwater tunnels in the world.

Modifications by James Greathead and mechanised forms of the shield helped form the basis of Crossrail’s tunnel boring machines (TBM).

At the front of the original design there was an iron frame and within each pocket was a man with a spade.

Once each section was dug out, timbers were put up to support the earth before hydraulic jacks pushed the frame forward and a row of bricks was built inside the tunnel they had created.

Workers dug by hand in the pockets of the shield

But Tim Shields, curator at London Transport Museum, said: “The shield offered the workers some protection but it would have been claustrophobic and very hot.

“They would often have been bare-chested but some pictures show them working in a jacket and shirt which is quite surprising.”

Andy Alder, project manager at Crossrail for the western tunnels, explained: “It was called the shield because it shields the men from the ground.

“The story goes that it is based on observing how worms bore through wood and this was pretty much the foundation for the main tunnelling work we are doing.

“All we’ve done is put a steel rotating cutter head with a motor at the front.

“There’s still then men digging, the jacks are still the same, then building the precast concrete sections behind and we have a railway that takes the ground out.”

Alder said the men digging the Tube could make the same progress in a year that the team behind Crossrail make in a week.

Latest news

Careys directors sacked after £4m job-loss showdown

Pair win unfair dismissal case after being accused of "tickling each other’s bollocks"
15 hours ago

Danny Sullivan Group hits back over HS2 allegations

Labour supply giant confident it is "fully compliant with all tax obligations"
19 hours ago

Bid race takes off for £500m MAG airport small works deal

Nine-lot framework to cover civils, building and M&E jobs up to £5m
1 day ago

Mace director joins Wates as Chief Commercial Officer

Pat Fitzgerald to lead commercial strategy at Wates
1 day ago

Rob Perrins steps up as executive chair in Berkeley shake-up

Long-serving chief steps up to lead housebuilder’s next growth phase
21 hours ago

Competition watchdog turns attention to civil engineering

Competition and Markets Authority launches study into road and rail delivery
2 days ago

Timber imports rise for first time in four years

Softwood volumes and prices lead rebound as housing outlook improves
21 hours ago

10-Year Infrastructure Strategy published

Full details as Government pledges £725bn of funding over the next decade
2 days ago

Korean firm buys part built Hackney job from failed Elements Europe

Work can now restart on 21-storey hotel and office development
2 days ago

Mark Wild radical reset plan to rescue HS2

Senior manager bonuses scrapped and non-permanent labour cutback
2 days ago

HS2 supply chain fraud claims spark ministerial probe

Transport secretary pledges one-year reset for HS2 to end 'litany of failures'
3 days ago

Lords launch inquiry into Building Safety Regulator delays

Industry asked for evidence of how system is failing: Have your say
2 days ago

Willmott Dixon director becomes co-owner of local contractor BSN

Nick Gibb targets £100m turnover at Dudley based national contractor
3 days ago

Dry lining boss sentenced after mystery account moves

Court hears of £500,000 in unexplained transfers before contractor went under
2 days ago

Barhale bags £16m shaft tank for Severn Trent Water

"Final piece in the puzzle" of Etruria Vale upgrade
2 days ago

Keltbray strikes £30m funding deal for growth

Three-year funding deal to support push into higher-margin work
3 days ago

Take That brother buys steelwork giant William Hare

Entrepreneur Simon Orange seals deal for £350m turnover contractor
4 days ago

Civils contractor LF Solutions files administration notice

£20m-turnover specialist has labour supply arm and own plant fleet
3 days ago

Joseph Gallagher lands £50m green energy deal

Major trenchless construction contract for HyNet North West project
3 days ago

New boss drives NG Bailey to record revenue

Fresh strategy lifts M&E group's order book to £1.6bn
3 days ago

Costain wins vast underground hydrogen storage design job

Firms lands FEED contract for Cheshire salt caverns conversion
3 days ago

Graham gets green light for £70m Glasgow student tower

Construction due to start this year on 25-storey Anderston scheme
3 days ago

New £16bn National Housing Bank to drive 500k new builds

Homes England given new powers to finance stalled and complex schemes
3 days ago

Morgan Sindall upgrades profits forecast for this year

Overbury fitout and construction operations exceed trading expectations
4 days ago

Major project bidders to face ‘British jobs’ test

Contractors to face tougher jobs pledge scrutiny under new procurement shake-up
5 days ago

Green light for £32m Wythenshawe Culture Hub

Construction to start this year on first phase of £500m town centre revamp
4 days ago

Hercules delivers record first half as HS2 fuels growth

Labour supply specialist says HS2 demand climbing with 630 workers now deployed
4 days ago

Private equity firm acquires Hepworth Clay pipes business

Historic UK drainage manufacturer sold by Wavin
4 days ago

Balfour Beatty names new Scottish MD

Nick Rowan to take reins as Hector MacAulay to retire after 40 years
5 days ago

£500m rail deal locks in future for Scunthorpe steelworks

Government-backed deal with Network Rail safeguards UK production
4 days ago

Contractor services