Amec appeal refused over £94m costs on submarine job

Aaron Morby 12 years ago
Share

Amec’s legal battle to reduce the amount it must pay of a £93.6m cost overrun on a nuclear submarine jetty contract at Faslane has failed.

Now Amec and partners Morgan Sindall face a huge bill as they hammer out with the Ministry of Defence what proportion of cost overruns were properly incurred on the troubled project.

A costly legal battle has been running as both firms struggle to finish the Faslane SSN Berthing Project, first revealed in the Enquirer, more than four years late and at an expected final cost of £235.7m.

When the project was first awarded Amec was sole contractor for the jetty. But after Morgan Sindall acquired Amec’s construction arm for £26m back in 2007, the job became a 50:50 joint venture between the two firms.

Under the terms of the contract, the contractors are liable to pay the first £50m of overruns on the agreed maximum target price for the job, which has itself already risen from £89m to £142m.

This element was not challenged in the latest legal contest, but Amec held that the remaining £43.6m cost overrun should be split between client and contractor, with Amec due any costs howsoever incurred.

An arbitration panel rejected this saying the only costs payable were the actual costs reasonably and properly incurred within the contract.

A High Court judge has now refused Amec’s attempt to appeal this decision in a written ruling this week upholding the arbitration decision.

Latest news

Government wields procurement stick on late payment

New rules would block slow payers from bidding on big public jobs
3 days ago

Hercules buys power line labour firm for £15.7m

Labour supply specialist snaps up Advantage NRG to tap booming electricity upgrade market
3 days ago

Universal bid to fast-track planning for theme park

Entertainment giant eyes 2026 start at Bedford site
3 days ago

Developer Breck to transform former Ibstock brick factory

Ravenhead works to become 300-home development
3 days ago

SP Energy Networks awards contracts worth £1.4bn

First round of awards under £5.4bn national electricity grid upgrade programme
4 days ago

Travelodge to convert Liverpool Street office building

Office-to-hotel conversion in City of London
3 days ago

Plans lodged for 1m sq ft City of London office

Barbican landmark building will reuse 40% of existing structure
3 days ago

PTSG acquires roofing specialist HD Sharman Group

Premier Technical Services Group expands building maintenance division
3 days ago

Balfour Beatty lands £833m carbon capture power plant job

Work to start later this year on Teesside carbon capture gas-fired power station
4 days ago

Svella agrees deal to save Cubby Construction

Solvent purchase set to save 214 jobs and protect supply chain
4 days ago

J Coffey holds line on margins despite £52m revenue slide

Pre-tax profit down 14% but firm eyes strong pipeline to bounce back
4 days ago

Consultants called up for £2.3bn NHS SBS panel reboot

Market asked for views ahead of next-gen procurement rollout
4 days ago

Hochtief launches new UK data centre division

German business model to be introduced for UK construction
5 days ago

Construction skills body launches with 100,000 worker target

Industry to work closer with Jobcentres to find new talent
4 days ago

Kier lands £42m Midlothian school and community hub

Contractor strengthens presence in Scotland with big education job
4 days ago

BESA audit blitz sees 14 specialist contractors suspended

Building engineering services trade body cracks down on standards
5 days ago

Engineers pull-off 220m HS2 viaduct slide in 3 days

Five-structure Northants sequence ends with 1,300t deck slide - video
5 days ago

Managing Director moves to advisory role at Shufflebottom

Alex Shufflebottom steps-down after acquisition by Embrace
5 days ago

JV North unveils winners of £500m housing blitz

Consortium gears up to deliver 3,000 new homes across North West
5 days ago

Partnerships builder Keepmoat names new chief executive

Ian Hoad to take reins as Tim Beale steps down after eight years
5 days ago

Ballymore to transform former Crossrail construction site

Limmo Peninsula will be new neighbourhood in East London
5 days ago

Building Safety Regulator chief to step down

Search on to find replacement for Philip White
6 days ago

Amazon unveils £40bn investment plan for UK sites

Four new fulfillment centres confirmed as part of huge spending package
6 days ago

Glass bridge picked for Queen Elizabeth II memorial

New bridge and gardens will honour late Queen in the heart of London
6 days ago

Mears set to beat profit forecasts after strong first half

Maintenance growth and 100% contract retention drive bullish outlook for 2025
6 days ago

Bouygues lands London 150 key worker homes job

Affordable flats planned near London Bridge in landmark council scheme
6 days ago

Hebden Bridge £68m flood defence job heads to market

Market engagement opens on four-year Environment Agency scheme
6 days ago

Housing plans go in for abandoned theme park

Story Homes to transform former Camelot Theme Park in Lancashire
6 days ago

Morris & Spottiswood sees turnover and profits surge

Growth at M&E division helps power record numbers
6 days ago

Redundancies loom at M&E giant Dalkia

Consultation starts at Southern region
7 days ago