Amec appeal refused over £94m costs on submarine job

Aaron Morby 7 years ago
Share

Amec’s legal battle to reduce the amount it must pay of a £93.6m cost overrun on a nuclear submarine jetty contract at Faslane has failed.

Now Amec and partners Morgan Sindall face a huge bill as they hammer out with the Ministry of Defence what proportion of cost overruns were properly incurred on the troubled project.

A costly legal battle has been running as both firms struggle to finish the Faslane SSN Berthing Project, first revealed in the Enquirer, more than four years late and at an expected final cost of £235.7m.

When the project was first awarded Amec was sole contractor for the jetty. But after Morgan Sindall acquired Amec’s construction arm for £26m back in 2007, the job became a 50:50 joint venture between the two firms.

Under the terms of the contract, the contractors are liable to pay the first £50m of overruns on the agreed maximum target price for the job, which has itself already risen from £89m to £142m.

This element was not challenged in the latest legal contest, but Amec held that the remaining £43.6m cost overrun should be split between client and contractor, with Amec due any costs howsoever incurred.

An arbitration panel rejected this saying the only costs payable were the actual costs reasonably and properly incurred within the contract.

A High Court judge has now refused Amec’s attempt to appeal this decision in a written ruling this week upholding the arbitration decision.

Latest news

M&E specialist “vanishes” from Willmott Dixon hotel job

Holmes Metrotech leaves subcontractors with unpaid bills
11 hours ago

Seddon suffers £3.4m construction loss

North West builder latest to be hit by challenging market
11 hours ago

Liverpool FC raises ambition for new Anfield stand

Plan ditched for 4,000-seat added capacity Anfield Road stand in favour of more ambitious scheme
10 hours ago

Worker killed on £40m shopping centre site

Tragedy at Glasgow McAlpine site
10 hours ago

Portsmouth sounds out industry for £1.3bn scheme

44ha Tipner Peninsula scheme will create a 4,000-home waterfront community
11 hours ago

Architects stop hiring as market jitters bite

RIBA research highlights "quiet and challenging" market
10 hours ago

Altrad scaffolders set to strike at Drax power station

Workers vote for stoppages over pay and conditions dispute
11 hours ago

BAM UK profits slide in first half of 2019

Margin squeezed to 1.8% from 2.8% a year ago
1 day ago

Boost your online presence – join the Enquirer Directory

Site for suppliers and buyers showcases products, services and latest stories
1 year ago

Birmingham seeks highways firm to step in for Amey

Temporary stand-in highways contractor to deliver £85m work programme to July 2021
1 day ago

HS2 review to decide if construction should continue

Decision on future of project due this autumn
2 days ago

Structure Tone lands £60m office revamp for ad giant WPP

Extensive upgrade of Southwark office includes recladding and extensions
1 day ago

Barrett Steel buys Parker site from administrators

Shoreham deal saves 50 jobs and expands Barrett's network to 50 locations
1 day ago

First modular council homes in Cardiff approved

Wates Living to deliver homes as part of a 600 council homes partnership
2 days ago

Miller on course for 4,000 homes by 2021

House builder to open Teesside office, 18 months after setting up in the West Midlands
2 days ago

Willmott Dixon wins £14m Brighton Met college job

New college for digital and creative industries to be built at Pelham Street site
2 days ago

Costain margin up to 4% despite fall in profits

Pre-tax profit more than halved after £10m roof repair bill for Diamond Synchrotron
2 days ago

Carey Group CEO steps down

Denis Deacy's role to be taken on by Tommy Carey and Jason Carey
2 days ago

Private equity firm buys cladding specialist

EAG plans to expand its pre-construction team to bid for more work
2 days ago

£700m funding bid for 16 northern road projects

Transport for North calls on Chancellor to back ready-to-go schemes
3 days ago

First JCB electric mini diggers start arriving on site

Willow Hire and Lynch take first zero emission excavators
3 days ago

Graham to start Liverpool flyovers demolition next month

Complex dismantling of Churchill Way flyovers to cost nearly £7m
3 days ago

Private equity firm snaps up roofing supplier Marley

Belgian materials giant Etex sells Staffordshire-based roofing specialist employing 600 staff
3 days ago

Jacobs to buy John Wood nuclear arm for £250m

More than 2,000 staff to transfer to Jacobs in major UK nuclear take-over
3 days ago

Creditors blast Britain’s oldest building company

Firms owed cash demand answers after Durtnell strikes debt repayment deal with some suppliers
3 days ago

Persimmon calls in independent site quality enforcers

New construction quality checkers will vet trade contractor delivery independent from site management teams
3 days ago

Crossrail enters its “most challenging phase”

Contractor productivity a "main area of programme risk and uncertainty."
3 days ago

Shaylor collapse hits trade contractors for £19m

Directors Stephen and Ritchie Shaylor listed among major creditors
4 days ago

City planners tighten rules to avoid tower downdraughts

Skyscrapers will now be designed with pedestrian and cyclist safety in mind
3 days ago

Failed piling firm Aspin auctions off plant fleet

More than 600 pieces of kit expected to raise over £2m
3 days ago

Contractor services