Worker crushed during energy plant construction

Grant Prior 4 years ago
Share

Three construction companies have been fined after a worker was crushed by a falling section of conveyor at a plant in Sleaford.

The incident happened during construction of the Sleaford Renewable Energy plant on 14 February 2013 when the 4.5 tonne conveyor section overturned during installation.

It trapped Michael Doyle, a 49-year-old employee of Derby-based Shaw Group UK Ltd, who suffered multiple injuries including four cracked vertebrae, broken ribs, a punctured lung and broken ankle.

He has not returned to work since.

Lincoln Magistrates’ Court heard that Shaw Group UK Ltd had been subcontracted to install a boiler and associated equipment , including a conveyor system to carry large straw bales, by Burmeister and Wain Energy (BWE).

BWE was one of two Danish companies, the other being Burmeister and Wain Scandinavian Contractor (BWSC), that had formed a consortium to design and build the centre, which burns straw and wood to create electricity.

Shaw Group UK Ltd had already lifted three conveyor sections on to a slope leading up to the boiler by craning them on to a platform at the bottom of the slope.

Skates were bolted to the front and rear legs which helped keep the section of conveyor on rails as it was dragged up the slope by manual winches set up at the top.

In order to fix the sections of conveyor in place workers needed to remove the skates and used jacks to raise the legs enough to take the skates off and then lower the legs down onto the rail.

This was carried out successfully on the first three sections but as the jacks were released, on the lower legs of the fourth and final section, one side lowered faster than the other and the conveyor swung towards two workers before violently swinging the other way and turning on its side, trapping Doyle underneath.

An HSE investigation identified safety failings by all three companies.

Shaw Group UK Ltd had produced a risk assessment and a plan for the installation but it did not consider removal of the skates from the legs of the conveyor sections or the manual winching of the load up the slope.

The document had been sent to BWE for checking but the company did not pick up on the omission.

The lifting operation using jacks was not carried out safely and none of the three defendants was managing or monitoring the work in a way that would ensure its safety.

The investigation also found that BWSC failed in its responsibility as principal contractor to ensure work was properly assessed and co-ordinated between the many contractors on site.

Shaw Group UK Ltd, of Derby, was fined a total of £17,350 and ordered to pay costs of £1,710 after pleading guilty to safety regulations.

Burmeister and Wain Scandinavian Contractor, of Allerød, Denmark, was fined £4,670 and ordered to pay costs of £1,710 while Burmeister and Wain Energy, of Kgs Lyngby, Denmark, was fined £5,350 and ordered to pay costs of £1,710.

Speaking after the hearing, HSE inspector Martin Giles said: “This was a large site with multiple contractors and up to 300 people working at any one time.

“Although there was a series of site rules set out in a construction phase plan, BWSC’s management of the site was poor as each of the main contractors ran their own areas of the site as they desired and were able to set additional rules.

“This led to different procedures being followed and a lack of control over temporary works.

“The failure to ensure work was carried out safely on the slope was symptomatic of more general failures which were the responsibility of  principal contractor BWSC in setting the rules, procedures and checks needed to manage a large site. These failures put all the workers on site at risk.

“BWE specified the use of skates for installing the conveyor system but removing them required adequate risk assessment.

“Although the company had read the assessment and method statement produced by Shaw Group it made no comment on it and did not approve it before it was implemented. BWE should have picked up on that document’s failures and asked Shaw Group to re-evaluate before work was allowed to begin.

“Shaw Group UK Ltd’s risk assessment was flawed, and its management and monitoring of the task was not sufficient to identify potential problems and stop the work in the four days before Mr Doyle was hurt.

“The actual method of work followed by its employees was unsafe and led to Mr Doyle’s injuries when the load overturned.”

Latest news

Lakehouse subbies plan showdown with Sureserve bosses

Suppliers owed millions to demand answers at company AGM
10 hours ago

Interserve subcontractors told it’s business as usual

Outsourcers circle Interserve support services division
16 hours ago

Morgan Sindall wins 20-year Sellafield civils deal

Four teams named for Sellafield decommissioning project partnership
17 hours ago

Hunt for quartet to deliver £700m Birmingham Uni pipeline

University is preparing to deliver phase two of its estate masterplan
18 hours ago

Stepnell wins £14m Northampton Vulcan works redevelopment

Historic factory to be refurbished for business start-ups
17 hours ago

Hunt starts for developer on £200m South Shields scheme

South Tyneside Council looking for housing partner and remediation specialist
17 hours ago

Revamp plans for Birmingham Moor Street station unveiled

Transfer deck across the top of station will connect to all platforms
17 hours ago

Boost your online presence – join the Enquirer Directory

New site for suppliers and buyers showcases products, services and latest stories
11 months ago

Interserve workers told to report for work as usual

Interserve subsidiaries to trade solvently as PLC business pre-packed
3 days ago

Interserve to file for administration as rescue rejected

Shareholders vote down rescue plan
3 days ago

Dawnus Group goes into administration

Grant Thornton now in charge of contractor which employed 700 staff
3 days ago

Bricklayer killed by collapsing wall

Court hands out £900,000 fine but contractor went into administration six months after tragedy
3 days ago

Dawnus collapse a “Welsh Carillion”

Subcontractors braced for huge losses as administrators poised to take control
4 days ago

Taylor Woodrow losses halve Vinci UK profits

Building operations trade profitably but Taylor Woodrow suffers fifth year in the red
4 days ago

Plans in for £70m Edinburgh botanic garden revamp

New glasshouse features in major overhaul plan
4 days ago

Mace to steer £350m Stevenage town centre revamp

Work set to begin on site next year
4 days ago

Plan for £250m new Tees Crossing

Tees Valley Combined Authority hopes work could start by 2023
5 days ago

Rail safety warning over runaway machine on tracks

Accident investigators highlight problems with safety management systems
4 days ago

Subbies braced for worst if Interserve loses crunch vote

Interserve to fall into administration if shareholders reject rescue plan
4 days ago

Dawnus heading for administration

Dawnus Construction Holdings on brink of collapse
6 days ago

11 firms win £5.2bn Southern Construction Framework

McLaren and McAlpine join new line up as Bouygues and Balfour drop out
5 days ago

Lakehouse Contracts ceases trading

£71m turnover business goes bust seven months after being sold by Sureserve
5 days ago

Torsion to build £65m twin towers in Leeds

Court Collaboration and Torsion Developments put in plans for build to rent scheme
5 days ago

Balfour Beatty bags £1.5bn central railway alliance

Network Rail names winner of last of three new track alliance deals
5 days ago

Brunel Uni starts race for £40m teaching block

Seven-storey facility will replace the 1968 John Crank building at Uxbridge campus
5 days ago

27 years in jail for “industrial scale” skills card forgers

Police smash forgery gang who were flooding the market with fake CSCS cards
5 days ago

£250m mixed-use scheme unveiled for Wolverhampton

Work planned to start next year creating 1,000 construction jobs
5 days ago

Holly Price becomes new head of the NFDC

Keltbray director becomes new leader of the demolition industry
6 days ago

Housing boosted in Spring Statement

£717m released for 37,000 homes at Old Oak Common in London, the Oxford-Cambridge Arc and Cheshire.
5 days ago

Balfour Beatty hits 2.4% construction margin

Leo Quinn puts group on strong footing after four-year turnaround
6 days ago

Contractor services