Worker crushed during energy plant construction

Grant Prior 3 years ago

Three construction companies have been fined after a worker was crushed by a falling section of conveyor at a plant in Sleaford.

The incident happened during construction of the Sleaford Renewable Energy plant on 14 February 2013 when the 4.5 tonne conveyor section overturned during installation.

It trapped Michael Doyle, a 49-year-old employee of Derby-based Shaw Group UK Ltd, who suffered multiple injuries including four cracked vertebrae, broken ribs, a punctured lung and broken ankle.

He has not returned to work since.

Lincoln Magistrates’ Court heard that Shaw Group UK Ltd had been subcontracted to install a boiler and associated equipment , including a conveyor system to carry large straw bales, by Burmeister and Wain Energy (BWE).

BWE was one of two Danish companies, the other being Burmeister and Wain Scandinavian Contractor (BWSC), that had formed a consortium to design and build the centre, which burns straw and wood to create electricity.

Shaw Group UK Ltd had already lifted three conveyor sections on to a slope leading up to the boiler by craning them on to a platform at the bottom of the slope.

Skates were bolted to the front and rear legs which helped keep the section of conveyor on rails as it was dragged up the slope by manual winches set up at the top.

In order to fix the sections of conveyor in place workers needed to remove the skates and used jacks to raise the legs enough to take the skates off and then lower the legs down onto the rail.

This was carried out successfully on the first three sections but as the jacks were released, on the lower legs of the fourth and final section, one side lowered faster than the other and the conveyor swung towards two workers before violently swinging the other way and turning on its side, trapping Doyle underneath.

An HSE investigation identified safety failings by all three companies.

Shaw Group UK Ltd had produced a risk assessment and a plan for the installation but it did not consider removal of the skates from the legs of the conveyor sections or the manual winching of the load up the slope.

The document had been sent to BWE for checking but the company did not pick up on the omission.

The lifting operation using jacks was not carried out safely and none of the three defendants was managing or monitoring the work in a way that would ensure its safety.

The investigation also found that BWSC failed in its responsibility as principal contractor to ensure work was properly assessed and co-ordinated between the many contractors on site.

Shaw Group UK Ltd, of Derby, was fined a total of £17,350 and ordered to pay costs of £1,710 after pleading guilty to safety regulations.

Burmeister and Wain Scandinavian Contractor, of Allerød, Denmark, was fined £4,670 and ordered to pay costs of £1,710 while Burmeister and Wain Energy, of Kgs Lyngby, Denmark, was fined £5,350 and ordered to pay costs of £1,710.

Speaking after the hearing, HSE inspector Martin Giles said: “This was a large site with multiple contractors and up to 300 people working at any one time.

“Although there was a series of site rules set out in a construction phase plan, BWSC’s management of the site was poor as each of the main contractors ran their own areas of the site as they desired and were able to set additional rules.

“This led to different procedures being followed and a lack of control over temporary works.

“The failure to ensure work was carried out safely on the slope was symptomatic of more general failures which were the responsibility of  principal contractor BWSC in setting the rules, procedures and checks needed to manage a large site. These failures put all the workers on site at risk.

“BWE specified the use of skates for installing the conveyor system but removing them required adequate risk assessment.

“Although the company had read the assessment and method statement produced by Shaw Group it made no comment on it and did not approve it before it was implemented. BWE should have picked up on that document’s failures and asked Shaw Group to re-evaluate before work was allowed to begin.

“Shaw Group UK Ltd’s risk assessment was flawed, and its management and monitoring of the task was not sufficient to identify potential problems and stop the work in the four days before Mr Doyle was hurt.

“The actual method of work followed by its employees was unsafe and led to Mr Doyle’s injuries when the load overturned.”

Latest news

Vinci UK profits soar despite £18m civils loss

Profit boost from land disposal offsets further losses at Taylor Woodrow
9 hours ago

£36m Cardiff student block set for planning OK

Crosslane gets go-ahead for 384-bed scheme
3 hours ago

Stalled Angelgate site put up for sale

Land earmarked for blighted Manchester resi scheme to go under auctioneer's hammer
4 hours ago

FRC launches probe into Carillion finance directors

Investigation into Richard Adam and Zafar Khan over preparation of financial accounts back to 2014
10 hours ago

Kier set for £48m Pirbright animal virus research lab

Work due to start before end of 2018 on the high containment large animal facility
9 hours ago

Wates sees order book swell to record £5.1bn

Contractor confident about future prospects as it offers new roles to former Carillion staff
10 hours ago

Engie to start stripping cladding on East London tower blocks

Canning Town and Plaistow Tower housing blocks get reclad go-ahead
9 hours ago

Passer-by raises safety alarm over solar panel contractor

Director and contractor fined after ignoring safety warnings
9 hours ago

RSK buys ground investigation specialist

Central Alliance is latest deal in acquisition spree by consultant
3 days ago

Plans in for Cheesegrater’s big brother in London

Tapering skyscraper at 100 Leadenhall will tower over the Cheesegrater
3 days ago

Vast £1.6bn South London estate rebuild approved

Clapham Park to be built out with 2,500 homes in mid-rise blocks
4 days ago

BESA appoints David Frise as new chief executive

Former submariner takes the helm at the Building Engineering Services Association
3 days ago

ISG clinches £17.5m Bradford leisure centre

Sedbergh sports and leisure facility will contain a 25m pool, gym
3 days ago

Boost your online presence with the new Enquirer Directory

New site for suppliers and buyers will showcase their products, services and latest stories
3 weeks ago

Berkeley unable to boost construction of new homes

Housing giant blames market conditions as it predicts £3.3bn profit in five years to 2021
3 days ago

Balfour Beatty tipped for £200m London student/office scheme

Landmark Vine Street project could become Balfour's second major contract with Urbanest
3 days ago

VolkerWessels UK margins edge up to 3.2%

Profits and order book grow by 7% on back of rising infrastructure spend
3 days ago

Weston Homes submits 1.2m sq ft Norwich scheme

Anglia Square scheme will provide over 1,000 homes, 40 shops and a 200-bed hotel
3 days ago

Network Rail seeks two geotechnical firms for £190m north deal

Scottish and North East earthworks delivery places up for grabs
3 days ago

Search to start for £400m Southend regen partner

Council searching for development partner to build 1,300 homes
4 days ago

Kier lifted by McNicholas deal in first half

Kier says claims and final account still to be settled on challenging Mersey Gateway project
4 days ago

Betting Spy: Man City can win Champions League

City look a good bet at 3/1 to go all the way
4 days ago

Buckingham to build giant fridge at Dover port

Contractor wins race for £15m Refrigerated Cargo Terminal
4 days ago

Hydrock places remediation arm into administration

Up to 95 jobs at risk as Bristol-based QDS Contracting collapses
5 days ago

Balfour supplier hit by Hinkley contract delays

Engineering specialist Redhall hampered by delays to nuclear deal
4 days ago

£120m Glasgow police HQ to flats scheme approved

Moda Living is planning over 400 private rented flats
5 days ago

Worker loses finger at builders merchant

Welsh firm fined after glove gets caught in table saw
4 days ago

Hill secures £200m finance to deliver 5-year plan

House builder on recruitment drive as it plans to raise revenue to £1bn by 2023
5 days ago

Alumasc sounds profit warning over project delays

Shares slump 20% as commercial new build demand dips
5 days ago

Balfour Beatty UK construction arm returns to profit

Contractor continues turnaround despite Aberdeen bypass problems
5 days ago

Contractor services