Concrete problems hit Hinkley Point tunnels

Grant Prior 1 month ago
Share

Contractors at Hinkley Point will have to replace 150 cubic metres of concrete poured on the site as part of work to form tunnels to contain pipes and cables.

Aerial view of the north office and galleries under construction

Problems have been identified in sections of the concrete base slabs constructed above the galleries sections of tunnels which will contain site infrastructure.

The Enquirer understands that the problem concrete is local to a small stretch of the 8km network of galleries tunneling.

Only 150 cubic metres of material are affected from the first 60,000 cubic metres poured on the site so far.

Nothing has been built on the slab and it does not form part of the foundations for the main nuclear power plant building where work is not due to get underway for 18 months.

A joint venture of Kier and Bam Nuttall is main contractor on the site earthworks package.

GetImage-1

Work underway last month in the galleries

Hinkley delivery director Nigel Cann said: “We have decided to replace a small area of concrete poured as part of the work to create tunnels for the pipes and cables.

“This is in line with the uncompromising attitude to quality taken at the Hinkley Point C Project.

“It is a very small proportion of the concrete poured on site so far and has no impact on the project schedule.”

Site Progress so far:

2,000 workers are on site every day, 65,000 meals every month needed to feed the growing workforce.

1,500 bed “Campus” accommodation for workers under construction with 500 beds on the site and 1,000 in Bridgwater – supplied by Newark-based Caledonian Modular .

76 apprentices are already working on the project, which will create up to 1,000 apprenticeships during the build.

4 million cubic metres of earth have been excavated – that’s enough to fill Wembley Stadium.

Two concrete batching plants are now complete. Up to 2,000 tonnes of concrete a day can be produced on site. At least 3 million tonnes of concrete will be used – 75 times more concrete than was used to build the Millennium Stadium in Cardiff.

10,000 tonnes of rock has already been delivered by ship from Pembroke, for the site’s new 13.5 metres high seawall.

29km of ground nails have been installed – enough to loop the perimeter of Hyde Park six times. The steel rods, each measuring up to 12 metres long, are used to stabilise the ground. A total of 110km will be used during construction.

Project remains on track to meet the 64% UK supply contribution with nearly £9bn of contracts signed since final approval. The latest contract with ABB Group was signed last month for the main power transmission systems for both reactors.

49 piles have been installed for the 500m temporary jetty in the Bristol Channel. Each pile – the foundation legs for the jetty – is 36 metres long, 3.6 metres in diameter and weighs in at 140 tonnes. The jetty will allow 80% of the aggregate to be brought in by sea rather than by road and is due to be completed next year. Devon engineering firm Blackhill worked on its largest-ever project involving 550 tonnes of steel for the jetty.

Dozens of cranes of all sizes are already on site alongside 200 pieces of large-scale construction equipment, ranging from excavators capable of moving 30 tonnes of earth in a single scoop to giant dumper trucks. The tallest ‘tower’ crane is 40 metres tall and can lift 16 tonnes. At peak construction there will be 50 ‘tower’ cranes at site.

£15 million is being invested into education, employment and skills to help inspire the next generation and provide people with the necessary training and support to help them into long term careers. Multi-million pound investments into a Construction Skills Centre and an Energy Skills Centre are not only ensuring that local people are equipped with the skills they need for the future, but helping to fill a national skills gap.

Latest news

McMullen Facades follows Lakesmere into administration

Firms circle to buy profitable cladding arm from administrators
9 hours ago

Clugston set to start £1.2bn Lincolnshire Lakes project

Excavation and engineering works set to begin early next year
7 hours ago

Sisk tipped for £88m Gatwick Airport hangar

Firm closes in on huge Boeing GoldCare hangar
12 hours ago

Willmott Dixon to build first Passivhaus secondary school

Builder to start work on £36m Harris Academy Sutton in the New Year
12 hours ago

Renew profit slides after £6.4m gas mains exit hit

Flowing AMP6 water work boosts engineering services revenue
7 hours ago

18 jobs at risk as London roofing specialist fails

Essex-based Superior Roofing & Building Services placed in administration
12 hours ago

Accounting watchdog launches probe into Mitie’s books

Investigation into preparation and approval of contractor’s 2016 financial statements
1 day ago

Severfield to supply small steelwork fabricators

Half-year profits soar as Severfield unveils plan to supply steel to small project
12 hours ago

£200m funding green light for Midland Metro extension

Theresa May launches £1.7bn city transport funding pot
1 day ago

Lendlease confirms £440m order for two London jobs

Order book swells with major Euston office revamp and 43-storey Pan Pacific hotel and flats
1 day ago

Chancellor vows to build 300,000 homes a year

Treasury reported to have found £5bn boost for housing schemes
1 day ago

Union demands urgent talks over threat to Carillion jobs

Union Unite seeks meeting after profit warning and latest debt figures
1 day ago

Over 80 jobs lost as historic builder goes under

Around 80 job losses as Knowles & Son (Oxford) falls into administration
1 day ago

Clancy Docwra breaks even as profits slide

Civils firm caught in two significant contractual disputes
2 days ago

Wates bags one of Birmingham’s tallest resi buildings

Developer Regal signs £32m deal for second tower at Broad Street
2 days ago

Green light for Salford resi block trio

Developer Select Property will pick a contractor for Embankment West by the Spring
2 days ago

GF Tomlinson wins £16m Nottingham Uni biosciences job

Work is due to start on new laboratories and lecturer theatre in early 2018
2 days ago

Carillion warns on profits again as it breaches banking covenants

Contractor asks for more time from lenders as debts set to soar up to £925m
5 days ago

T Clarke powers ahead on London major project wins

M&E specialist boasts strong orders for next two years despite Brexit fears
5 days ago

Kier wins £35m Clydebank hospital project

Kier to start work early next year on first of two treatment centres for Golden Jubilee hospital
4 days ago

M&E specialists suffering from blight of retentions

Nearly a third of firms have up to 10% of their turnover locked-up in retentions
5 days ago

15 councils face action over local housing plans

Government set to intervene to force through local housebuilding plans
5 days ago

Betting Spy: Winning start for the Moyes boys?

West Ham are worth a go at 5/2 to turn up for their new boss
5 days ago

North to get own transport spending powers

Plan to give Transport for the North statutory powers from April a game-changer
5 days ago

White collar skills crisis strangling construction

Nearly two thirds of companies can't find Quantity Surveyors
5 days ago

Winvic bags £40m Nottingham build to rent scheme

Construction to start this month on 350-home scheme
5 days ago

Government rethink over £130m Balfour lorry park

Current plans dropped as Highways England goes back to the drawing board
6 days ago

Green light for £270m Swindon leisure complex

Work to start next year on North Star ski centre, hotel and cinema complex
6 days ago

£60m+ offsite secondary school bundle out to bid

ESFA plans trio of £20m-plus secondary schools projects using modular construction
5 days ago

British Land to start £200m London office revamp

Regent's Place office to be enlarged in major revamp near Euston
6 days ago

Contractor services