Concrete problems hit Hinkley Point tunnels

Grant Prior 4 months ago
Share

Contractors at Hinkley Point will have to replace 150 cubic metres of concrete poured on the site as part of work to form tunnels to contain pipes and cables.

Aerial view of the north office and galleries under construction

Problems have been identified in sections of the concrete base slabs constructed above the galleries sections of tunnels which will contain site infrastructure.

The Enquirer understands that the problem concrete is local to a small stretch of the 8km network of galleries tunneling.

Only 150 cubic metres of material are affected from the first 60,000 cubic metres poured on the site so far.

Nothing has been built on the slab and it does not form part of the foundations for the main nuclear power plant building where work is not due to get underway for 18 months.

A joint venture of Kier and Bam Nuttall is main contractor on the site earthworks package.

GetImage-1

Work underway last month in the galleries

Hinkley delivery director Nigel Cann said: “We have decided to replace a small area of concrete poured as part of the work to create tunnels for the pipes and cables.

“This is in line with the uncompromising attitude to quality taken at the Hinkley Point C Project.

“It is a very small proportion of the concrete poured on site so far and has no impact on the project schedule.”

Site Progress so far:

2,000 workers are on site every day, 65,000 meals every month needed to feed the growing workforce.

1,500 bed “Campus” accommodation for workers under construction with 500 beds on the site and 1,000 in Bridgwater – supplied by Newark-based Caledonian Modular .

76 apprentices are already working on the project, which will create up to 1,000 apprenticeships during the build.

4 million cubic metres of earth have been excavated – that’s enough to fill Wembley Stadium.

Two concrete batching plants are now complete. Up to 2,000 tonnes of concrete a day can be produced on site. At least 3 million tonnes of concrete will be used – 75 times more concrete than was used to build the Millennium Stadium in Cardiff.

10,000 tonnes of rock has already been delivered by ship from Pembroke, for the site’s new 13.5 metres high seawall.

29km of ground nails have been installed – enough to loop the perimeter of Hyde Park six times. The steel rods, each measuring up to 12 metres long, are used to stabilise the ground. A total of 110km will be used during construction.

Project remains on track to meet the 64% UK supply contribution with nearly £9bn of contracts signed since final approval. The latest contract with ABB Group was signed last month for the main power transmission systems for both reactors.

49 piles have been installed for the 500m temporary jetty in the Bristol Channel. Each pile – the foundation legs for the jetty – is 36 metres long, 3.6 metres in diameter and weighs in at 140 tonnes. The jetty will allow 80% of the aggregate to be brought in by sea rather than by road and is due to be completed next year. Devon engineering firm Blackhill worked on its largest-ever project involving 550 tonnes of steel for the jetty.

Dozens of cranes of all sizes are already on site alongside 200 pieces of large-scale construction equipment, ranging from excavators capable of moving 30 tonnes of earth in a single scoop to giant dumper trucks. The tallest ‘tower’ crane is 40 metres tall and can lift 16 tonnes. At peak construction there will be 50 ‘tower’ cranes at site.

£15 million is being invested into education, employment and skills to help inspire the next generation and provide people with the necessary training and support to help them into long term careers. Multi-million pound investments into a Construction Skills Centre and an Energy Skills Centre are not only ensuring that local people are equipped with the skills they need for the future, but helping to fill a national skills gap.

Latest news

Almacantar chief in Twitter tirade against McAlpine

Mike Hussey says he would not trust contractor to 'deliver a pizza'
3 days ago

Persimmon chiefs hand back £50m after bonuses outcry

Persimmon bosses waive second instalment of bonuses
3 days ago

Colas and Volker to exit huge London highways contract

CVU joint venture and TfL agree to part company early on eight-year framework
3 days ago

Boost your online presence with the new Enquirer Directory

New site for suppliers and buyers will showcase their products, services and latest stories
4 months ago

Lendlease on board for £4bn London Euston district

Arup and Grimshaw will now work on Euston plans
3 days ago

Carillion cracked hospital beams remedial work unfinished

Auditors and pension regulator heavily criticised by MPs
3 days ago

Amey Rail snaps up Carillion rail projects saving 700 jobs

Projects in the East Midlands, London and North West England back on track
4 days ago

Willmott Dixon gets start date for £49m Colston Hall revamp

Work to start in June on major regeneration for Bristol landmark
3 days ago

Carillion bosses dodge pension black hole

Accounts show one pension scheme was in surplus while the rest had an £800m deficit
4 days ago

Morgan Sindall profits soar as margins restored

Fit-out and construction deliver strong profit growth as 2018 set to be bumper year
4 days ago

Centre Point Tower developer claws back £1m from McAlpine

McAlpine counts cost of row over design and build or construction management route for London tower
4 days ago

Betting Spy: England to win the Calcutta Cup

England can cover the handicap in the Six Nations while West Ham have it all to do as usual at Anfield
3 days ago

Sisk vows to complete joint venture jobs after Lagan collapse

Contractor will complete Highways England schemes on its own
5 days ago

Suspended sentence for scaffolder spotted without harness

Court hears how experienced worker chose to ignore safety rules
4 days ago

Construction slave labour ring smashed in East London

Fifty Eastern European workers saved after exploitation on sites
4 days ago

GRAHAM wins £86m Liverpool build to rent tower

Demolition work to start on waterfront site this month
5 days ago

Interserve to close power lines operation axing over 70 jobs

Power transmission firm to be wound down over next few months
5 days ago

Lagan puts construction arms into administration

Up to 200 jobs at risk as construction and building divisions hit by delays and disputes
6 days ago

Barratt looks to new building methods to boost volumes

Completions creep up by 2% as UK's largest house builder looks to use more offsite construction
5 days ago

BAM counts cost of weaker pound

UK business pre-tax profit slip of 7% to £35m due to exchange rate change
5 days ago

Galliford Try clinches £55m Leamington Spa housing project

Partnerships arm will build 375 homes for Waterloo Housing Group
5 days ago

Green light for London Deutsche Bank HQ

Developer Landsec says construction to continue once substructure is complete next March
5 days ago

Highways England calls bids for £326m Area 10

Hunt starts for maintenance and response contractor in north west
6 days ago

Carillion directors ‘contemptuous’ of pension funding

Carillion trustees alerted watchdog twice over pensions shortfall to no avail
6 days ago

Civils to start on £160m Yorkshire shopping centre

Advanced highways and infrastructure work to start this summer
6 days ago

Liverpool advances £700m Festival Park redevelopment

Willmott Dixon to carry out enabling works around Festival Garden dome base
6 days ago

Consultant Dar to build new Holborn HQ

Hunt on for contractor as Currie & Brown owner plans UK expansion
6 days ago

Another 152 Carillion staff axed taking job toll to 1,141

Staff told to pack up as fresh wave of job cuts unveiled today
6 days ago

Mace lands £350m Stevenage town centre revamp

Council picks winning developer for major town centre regeneration
6 days ago

Construction cartel whistleblowers offered £100k for tip-offs

Competition and Markets Authority targets construction in latest crackdown
7 days ago

Contractor services