Murphy loses legal battle over delayed Beckton power plant

Aaron Morby 8 years ago
Share

J Murphy & Sons has lost its fight in the High Court to stop the client of its East London power plant project calling an on-demand bond in respect of a claim for liquidated damages of £8.27m.

Client and contractor are at loggerheads about cost overuns
Client and contractor are at loggerheads about cost overuns

The ruling ahead of attempts to settle claims is the latest blow for the contractor on its fat-fired combined heat and power project in Beckton.

The project, which is now in protracted commissioning and testing, is running nearly 15 months late,  with a handover date still to be agreed by Murphy and client Beckton Energy.

Murphy first revealed the cost of problems on the power plant scheme five months ago when it blamed much of an £16m operating loss in 2014 on the extra cost of building the combined heat and power plant.

The contractor said difficulties with design, cost escalation, supply chain and engine related technical breakdowns all had major impacts on the project.

At the time Murphy said it was reviewing its entitlement for recovery of sums, but had stuck to its policy of booking losses as they emerged.

The £70m engineer, procure and construct contract was awarded following a competitive tender three years ago and was due to be handed over in January 2015.

In the High Court, Murphy had asked the judge to rule whether client Beckton Energy could make a demand on the bond in respect of its claim for liquidated damages before the project engineer had made a determination on the amount of LDs due.

During the case its emerged that Murphy disputes Beckton’s entitlement to any liquidated damages, and claims to have suffered significant delays on the project and requested extensions of time, in particular in August 2014, February 2015, September 2015, November 2015 and December 2015.

Beckton Energy claims that extensions were not granted by the engineer because Murphy had not demonstrated that any event or circumstances gave rise to a claim for extension of time or payment.

The judge ruled the details of the main dispute were not pertinent to contract terms at issue and in a set-back for Murphy ruled that Beckton Energy was entitled to call  the on demand bond under the contract.

Latest news

Bouygues/Murphy JV confirmed for £2.3bn Thames tunnel job

BMJV clinches 4.2km Lower Thames Crossing road tunnel job
2 days ago

Berkeley keeping close eye on subbies as market softens

Supply chain insolvency now bigger threat than build cost rises
1 day ago

Roofing firm fined £881,000 after double fall

Court hears of two falls on sites involving same contractor
2 days ago

Plans in for £450m Coventry city centre regeneration

Work is expected to start next summer on City Centre South scheme
1 day ago

Galliford Try to upgrade Red Arrows base

Contractor seals quartet of RAF base upgrades
1 day ago

Strabag tunnel drive in Yorkshire sets new world record

Woodsmith potash mine tunnelling project to be included in Guinness World Records
2 days ago

McLaren and Arlington to develop York Central site

Developer deal signed for one of the UK’s largest city centre regeneration schemes
2 days ago

Watkin Jones plans 36-storey Glasgow tower

The Ard student rooms scheme will be Glasgow's second tallest building
2 days ago

Balfour Beatty on track for solid set of results

Country's largest contractor on course to meet financial targets
2 days ago

Brymor Group Southern heads for CVA

Hampshire builder applies for Company Voluntary Arrangement with its creditors.
2 days ago

Former Costain transport chief joins Aecom

Sue Kershaw takes up US-based vice president job with consultant
3 days ago

Industry’s best construction managers revealed

More than 80 now in the running for delayed awards: Full list
3 days ago

Materials prices plummet as housing demand slumps

Buyers report biggest fall in purchasing costs for 14 years
3 days ago

Welsh contractor Andrew Scott targets £90m turnover

Profit and revenue up at Port Talbot-based civils and building firm
3 days ago

M-AR buyer starts round of redundancies

30 jobs at risk after modular firm bought out of administration
3 days ago

First HS2 viaduct completes deck beam installation

EKFB completes beams for first of project's 50 major viaducts
3 days ago

Fatal accident at Laing O’Rourke Oxford site

Work suspended on site after tragedy
4 days ago

Homes lead the way as Bancon Group boosts turnover

Homes and contracting group looking to further growth in 2024
3 days ago

L&G Modular Homes scheme replaced by traditional build

Wolverhampton council chooses new partner and build method for £150m project
3 days ago

£33m Plymouth city centre homes scheme approved

Spring start for Bath Street scheme in Millbay regeneration area
3 days ago

Balfour renews £330m Lincolnshire highways deal

Firm will use its new operational control hub to promptly address network issues
4 days ago

Three Caledonian Modular-built schools to be demolished

DfE confirms Essex, Somerset and Northampton schools will be bulldozed and rebuilt
4 days ago

Gilbert-Ash takes £30m Tate Liverpool revamp

Work to start in the New Year on remodelling of iconic 1846 warehouse
4 days ago

HS2 Solihull mass transit enabling works out to bid

Bidding for £60m main works to start early next year
4 days ago

Modular health specialist Vanguard rescues M-AR

Deal with administrators sees Vanguard add production capacity with 100,00 sq ft offsite factory
4 days ago

Torsion forms JV to build £90m Leeds resi tower

Construction to start in January on one of Leeds' tallest towers
4 days ago

Approved change to concrete ‘recipe’ to slash carbon emissions

New approved concrete mixes will be able to blend finely ground limestone and fly ash
5 days ago

Network Rail unveils Cardiff South Central masterplan

Plans being drawn up for major housing-led mixed-use scheme
5 days ago

McLaren Living to revamp Watford police station site

Developer to submit plans for a major mixed-use development
5 days ago

National Grid £12.8bn HV civils framework hits market

Firms needed for major power line links and high voltage direct current converter stations
5 days ago

Contractor services