Brickwork contractors facing mortar rationing

Aaron Morby 4 years ago
Share

Brickwork contractors are warning projects could grind to a halt because of rationing of bulk mortar supplies in the face of deepening cement shortages.

Brickwork contractors sound the alarm over mortar shortages
Brickwork contractors sound the alarm over mortar shortages

Bulk mortar suppliers have been put on allocation by major cement suppliers limiting their ability to manufacture and supply.

One dry mortar supplier Remix temporarily stopped taking orders this week although it hopes to get back on track next week.

Another big industry supplier Euromix has written to customers warning of disruption to supplies.

Kevin Flahive,  director of Watford firm Flahive Brickwork, said: “We started to see mortar silo refill lead times go from 4 days to 2 weeks.

“Now we’re are being told there is an issue with cement supplies and we could only be getting 60% of what we want.”

He added: “We’ve come very close to running out and another brickwork firm I know had to stop work last week.”

Eve Livett, Chief Executive Officer of the Association of Brickwork Contractors, said: “The majority of our 30 member contractors are experiencing problems with supply.

“If this continues it is going to scupper progress of works.

“It is vital that the wider industry be made aware of this so that a collaborative approach can be made with main contractors and their brickwork subcontractors.”

Supplier CPI Euromix’s managing director, Larry Dale said: “With immediate effect, our principle cement supplier has placed CPI and other customers on allocation, this will limit our ability to manufacture and supply mortar in certain locations.

“We will endeavour to provide the best service that we can, however these new production constraints will inevitably cause disruption in our ability to supply.

“We will provide the best information we can at the time of ordering in terms of indicative order call off times, we very much hope that this is a short term issue but in any event is out of our control at this time.”

Mineral Products Association chief executive Nigel Jackson, speaking on behalf of cement suppliers, said that a mix of high demand, kiln shutdowns for maintenance and trouble finding hauliers was causing localised delays.

“Where demand exceeds supply capacity longer lead times may be expected.

“As production catches up it shouldn’t be long before supplies are back to normal depending on how long this surge in pent-up demand actually lasts and subject to transport availability.”

Latest news

Oxford United win green light for £150m all-electric stadium

Planners back 16,000-seat Kidlington ground with hotel, plaza and community hub
1 day ago

Demolition record as eight cooling towers come down

Watch Brown & Mason set record at Cottam Power Station
2 days ago

Hitachi Energy named for EGL3 converter station deal

Firm to build major HVDC converter stations in Aberdeenshire and West Norfolk
1 day ago

PAS NW secures landmark £20m civils deal in Lancashire

Groundworks firm wins infrastructure for 429-home Wain Homes scheme
1 day ago

Subcontractors wanted for jobs across the South West

Register now for latest Constructionline event in Bristol
1 day ago

Profits double at Octavius as road and rail work grows

Recent acquisitions add to turnover growth at infrastructure specialist
2 days ago

Quarterly construction output growth masks orders slide

New orders down by over 8% driven by fall in infrastructure and offices
2 days ago

Vinci UK swings back into profit after group restructure

£166m cash injected to strengthen building and facilities operations balance sheets
3 days ago

Staged procurement to make comeback as pricing risk bites

Developers turn to staged deals to control costs on big-ticket commercial jobs
2 days ago

McGee profit halves as project start delays hit

Revenue up 24% but profits fall on higher carry costs
2 days ago

Vistry to deliver 2,300 homes at Rugeley power station site

139-acre brownfield site has already been extensively remediated
2 days ago

Andrew Scott wins role on Swansea’s next big office build

Contractor appointed for detailed design of 800-desk city centre hub.
2 days ago

Knights Brown to start £29m Poole flood wall job

1.5km barrier to protect homes and unlock regeneration plans
2 days ago

Kier lands £16m first ECI job with Southern Water

Design deal covers nitrogen cut and UV upgrade at Hampshire wastewater sites
3 days ago

Watkin Jones seals deal on 200-bed student scheme

Bristol project will involve four brick buildings rising to seven storeys
3 days ago

Severfield brings in new CEO from Laing O’Rourke ranks

Everton Stadium job chief Paul McNerney to take the helm in the autumn
3 days ago

Balfour hits 3% construction margin target

Profit target finally reached after eight years
3 days ago

Network Rail launches £240m OLE steelworks framework race

Deal to supply overhead line equipment for electrification schemes
3 days ago

Briefing starts for £8bn highways maintenance shake-up

National Highways launches early talks on next-generation regional roads upkeep
3 days ago

Plant hirer Lynch launches labour supply division

Workers now available to Tier 1 and Tier 2 infrastructure contractors
3 days ago

Kori lands latest £17m care home contract

Work to start on site in south west London next month
4 days ago

£70m Bristol student job finally gets Gateway 2 approval

Student developer Unite to progress two big schemes
4 days ago

Government unveils 10 new construction technical colleges

£100m plan to train 40,000 skilled trades by 2029 gets off the ground
4 days ago

McLaren lands London School of Economics £100m revamp

Central London job will be largest Passivhaus retrofit building in the UK
4 days ago

Industry standards body parts company with chairman

Considerate Constructors Scheme executive chairman also leaves role at Lighthouse Charity
4 days ago

Clegg wins car park to flats conversion contract

Work to start this autumn on transforming multi-storey car park into flats
5 days ago

Go-ahead for major retrofit of former London De Beers office

Mace advised on pre-planning construction plan for Hatton Garden gateway scheme
4 days ago

Danny Sullivan HS2 workers hit-out over agency moves

Site workers unhappy about how TUPE transfers are being handled
5 days ago

Overbury set for major law firm fit-out win

Contractor tipped for 2 Aldermanbury Square win
1 week ago

M&E contractor Cannock goes under

Supply chain takes hit as Staffordshire specialist goes down owing £4m
5 days ago