Skills and material crisis hitting London housing delivery

Aaron Morby 3 years ago
Share

The Mayor of London has called on the Government to create a Coronavirus Recovery Visa to help combat worsening shortages of construction workers which have started to impact on house building delivery in the capital.

Mayor Sadiq Khan wants to see a new visa and greater funding from central Government as shortages and cost rises start to derail planned affordable housing programmes.

He highlighted growing concern after a planned development in south east London saw tender returns come in 45% above estimates.

He said a south London borough reported cost inflation spiking up to 17%, while a north east London borough reported average cost increases across the board at over 10%.

Khan said the visa should offer at least 12 months to work in the UK.

He said: “From City Hall, we have worked tirelessly to get London building again, but the twin effects of the pandemic and Brexit has hit both housebuilders and consumers hard.

“Put simply, materials and labour are needed to build homes. I call on the Government to create a temporary visa scheme for construction workers, which would go some way towards alleviating the debilitating double impact of Brexit and the pandemic on the building industry.

“I am also calling on ministers to provide the increased funding for genuinely affordable housing in London that I have long called for and which is needed now more than ever. Without bricks and mortar, and enough skilled workers, the excellent progress we have made in delivering the good quality and genuinely affordable homes that Londoners need is at risk of stalling.”

Brian Berry, chief executive of the Federation of Master Builders, said: “For over a year, small builders who deliver new housing and improve existing homes either through extensions or by retrofitting, have been struggling with the twin challenges of rising prices for essential materials and severe labour shortages.

“Today’s State of Trade Survey data from the FMB shows these pressures aren’t going away, and there are now added fears about the impact of rising inflation.”

G15 social housing body chair, Geeta Nanda, said: “The rising costs of materials we are seeing across our affordable house building projects is a real challenge. We’re working hard with the Mayor and local authorities to build the homes Londoners need, but we need to address both the shortage of skilled workers and the impact of inflation on our projects.”

 

Latest news

Data centres and airport expansion to spur growth

Government hails £25bn data centre and £1.1bn Stansted Airport expansion plan
34 mins ago

BAM reassures supply chain after winding-up petition

Firm's credit rating temporarily affected after dispute with supplier
7 hours ago

Winvic secures Leeds build to rent scheme

Phase one of £500m Sweet Street South Bank regeneration starts
7 hours ago

£60m turnover construction group sold to staff

Meldrum Construction Services Group becomes Employee Owned Trust
8 hours ago

Starmer vows to “rip out” obstacles to investment

Prime Minister to make pledge at inaugural International Investment Summit
7 hours ago

VolkerFitzpatrick starts prep-work for £210m M3 junction upgrade

Main works to begin in early 2025 on Winchester junction job
8 hours ago

London super sewer turned on after eight years of construction

£4.5bn project starts protecting River Thames from pollution
8 hours ago

Housing and office new work jump fuels output recovery

August new construction work rebounds 1.6% after early summer fall
3 days ago

£300m London City fringe office tower approved

Rocket's 27-storey One Fairchild Street job set for take-off
4 days ago

Consultants named for London Tube Bakerloo Line extension

Aecom and architect WW+P to work up designs for four new stations
3 days ago

15 giant bridge beams lifted into place at HS2 station

Balfour Beatty VINCI carries-out civils work for Solihull station: Video
4 days ago

Ballymore JV picked for £500m King’s Cross scheme

Camley Street scheme to consist of 350 homes and offices
4 days ago

Digger stolen from Dorset site recovered in Poland

Machine found after four month police hunt
3 days ago

Construction firms face claw back of R&D tax credits

HMRC estimates only 38% of construction claims are "wholly compliant"
4 days ago

Willmott Dixon bounces back into profit in first half

CEO predicts ISG demise will shift client mindsets from lowest bid to best quality
4 days ago

M&E specialist Integral UK suffers fifth year of losses

Building services and FM specialist plunges to £32m loss
4 days ago

Glenbrook plans 44-storey Manchester resi tower

Scheme next to Deansgate station will contain 360 flats
4 days ago

Downing submits 430-bed London student scheme

Two-10 storey towers planned at Wandsworth Gasholder Site
4 days ago

Mace construction head steps down

Andrew Jackson leaves top role after three months
5 days ago

Pre-pack saves 60 jobs at fit-out firm WFC Contractors

Aviation fit-out group swoops on up-market hospitality fit-out specialist
5 days ago

Multiplex in talks for ISG’s £70m London offices to labs job

Plan to restart Regent Quarter life science campus with ISG project team
5 days ago

M&E firm goes under after more than 70 years in business

HBS Group Southern employed 75 staff
6 days ago

Trio of big names win £600m biscuit factory revamp

Developer Greystar confirms deals for McLaren, McAleer & Rushe and Sisk
6 days ago

HS2 London tunnels chief joins Transpennine Route Upgrade

James Richardson will take up MD role at TRU in New Year
5 days ago

Transport minister signals HS2 will run to Euston

Decision expected in spending review and budget later this month
6 days ago

£9bn Lower Thames Crossing decision delayed 7 months

Fears grow mega project could be axed in upcoming Budget
6 days ago

Vistry issues profit warning over build out costs at southern division

Probe launched after £115m hit on 9 schemes where build costs under estimated by 10%
6 days ago

ISG administrator tells subbies no funds to pay debts

EY warns trade creditors they are unlikely to see any of the cash they are owed
6 days ago

Giga factory powers McAlpine to top of contracts league

Work winning for the top 50 firms rebounded in September after August lull
6 days ago

Merit to build £30m modular NHS medicines centre

Specialist starts work on offsite components
6 days ago

Contractor services