London super sewer turned on after eight years of construction

Grant Prior 7 months ago
Share

London’s £4.5bn super sewer has now been turned on after eight years of construction work.

The first four of 21 sites have been switched on with the new tunnel starting to protect the River Thames from sewage pollution for the first time.

Valves, which operate like giant gates, are now open at four sites with the rest due to come online in the coming months when the sewer will reach full operating capacity next year.

In May the new 25km super sewer was connected to the 6.9km Lee Tunnel – completing the full ‘London Tideway Tunnel’ network which has a combined capacity of 1.6m m3.

Tideway CEO Andy Mitchell said: “This is an important moment for the Thames. The super sewer has been switched on and is starting to protect the river from sewage pollution.

“After eight years of construction, in which almost 25,000 people have contributed more than 40 million working hours, this system is operating for the first time.

“These are early days, with more connections to make and further testing to come, but the super sewer’s positive influence on the health of the Thames will increase over the coming months – and London will soon be home to the cleaner, healthier river it deserves.”

Teams are now working to bring the system into full operation. This involves connecting the remaining discharge points to the new super sewer and testing the entire system during different weather conditions, including heavy storms.

While the testing phase is now underway, work continues above ground to finish the new riverside public spaces being created as part of the project.

The Tideway project is being delivered by an alliance of contractors. The west region is being delivered by a joint venture of BAM Nuttall, Morgan Sindall Infrastructure and Balfour Beatty. The central region is being delivered by a joint venture of Ferrovial Agroman UK and Laing O’Rourke. The east region is being delivered by a joint venture of Costain, Vinci Construction Grands Projets and Bachy Soletanche.

System integration is being delivered by Amey, which is responsible for providing process control, communication equipment and software systems for operation, maintenance and reporting across the Thames Tideway Tunnel system.

 

 

Latest news

Six guilty of £2m bribery over Devon housing site deals

Corrupt building bosses and E.ON project chief and QS sentenced
1 day ago

1,650 former ISG staff launch legal claims

Redundancy Payment Service facing payout of more than £9m
2 days ago

Plans lodged for £1bn cancer research centre in Sutton

London Cancer Hub will deliver around 1m sq ft of lab and research space
20 hours ago

London Met Uni seeks firm for £284m estate revamp

Contractor wanted to deliver capital works and FM
21 hours ago

Delayed £2bn estate rebuild back on as Berkeley signs deal

Birmingham council development agreement paves way for 2028 Ladywood start
2 days ago

Tilbury Douglas boosts margin to 2.1% as profits double

Firm targets 3.5% margin by 2029 under new business plan
2 days ago

Subbies battle for fastest bricklayer title

Winchmore management team go back on the tools
2 days ago

Green light for revised McLaren Reading revamp

Mixed-use plans to transform Broad Street Mall site
21 hours ago

Three arrested in Blu-3 and Mace bribery probe

Serious fraud office swoops over alleged £3m bribes to former Mace associates
2 days ago

Scotland’s most complex A9 dualling job heads to market

Market testing starts for £205m Pitlochry to Killiecrankie 6.4km upgrade
2 days ago

Unite signs £390m student beds JV with Manchester Met

Construction at Cambridge Halls site to start next year
2 days ago

Turkish contractor Limak to build new Luton Town stadium

Construction to start this summer on 25,000-seater venue
3 days ago

Kitchen fitter crushed to death by concrete blocks

House builder goes into liquidation before court case
2 days ago

Mears clinches £230m renewal for key Milton Keynes housing deal

Housing upkeep contractor achieves 100% renewal rate in bust rebid period
2 days ago

Murphy on board at new £32m rail station

Construction to start next year at Golborne station
3 days ago

HS2 engineers finish UK’s heaviest bridge slide early

A46 Kenilworth Bypass reopens 30 hours earlier than planned
3 days ago

Bowmer + Kirkland to build £190m Oxford science scheme

Work to start at end of next month on 180,000 sq ft Fabrica scheme
3 days ago

New BAM leisure centre pool springs a leak

Contractor investigating "technical issues" delaying new £36m green leisure centre
4 days ago

United Living lands £250m HyNet pipeline deal

Firm wins deal to design and build over 34km of pipework to collect CO2
3 days ago

Hydrogen diggers get green light to use roads

JCB hails historic decision for advance of hydrogen-fuelled plant on sites
3 days ago

Go-ahead for McAleer & Rushe Glasgow student job

£100m funding deal paves way for 591-bed student tower
3 days ago

Fly-tippers to get their vehicles crushed

Drones will be used to identify cowboy construction waste operators
3 days ago

Green light for £150m West End office revamp

Shaftesbury Avenue office retrofit retains 75% of original building
4 days ago

Morgan Sindall lands £30m Brunswick Wharf scheme in Bideford

North Devon waterside project will provide 100 flats
3 days ago

Former Keltbray managers jailed after corruption trial

Jail sentences following bribery probe on jobs including Battersea Power Station
4 days ago

Lidl pumps £500m into store and logistics expansion

Discounter plans 40 new stores this year as expansion ramps up
4 days ago

JJ Rhatigan UK profit jumps as turnover tops £150m

Irish contractor's expansion in England gathers pace
4 days ago

Driverless digger to be used on Taylor Woodrow site

Autonomous excavator to work at Manchester Airport after successful trial
4 days ago

MCS Build lands Basingstoke warehouse scheme

Construction starts this month after £26m funding deal
4 days ago

Leeds United unveil stadium revamp design

Club has still to set a timeframe for staged Elland Road upgrade
4 days ago

Contractor services