‘Affordable’ HS2 Crewe to Euston plan submitted to Treasury

Aaron Morby 2 months ago
Share

The industry’s High Speed Rail Group has submitted outline plans to the Treasury to rescope the HS2 project to unlock maximum economic benefit within a constrained budget.

HS2 at a crossroads as industry warns Government risks failing to capture full economic benefits with existing plan
HS2 at a crossroads as industry warns Government risks failing to capture full economic benefits with existing plan

The plan to rescope HS2 to a “Euston-Crewe core” would accelerate delivery, and ensure a substantial financial return to the Treasury, while recognising current fiscal constraints.

Rescoped proposals have been submitted to the Treasury ahead of the spending review with a warning the project is at a crossroads that could determine its failure or success.

Industry backers argue the extension to Crewe would add urgently needed national transport capacity between London, the West Midlands and the North West.

The HSRG is calling on the Government to ‘un-freeze’ the planned connection from the West Midlands to Crewe.

Without this, the group warns HS2 would fail to relieve pressure on the West Coast Main Line at its biggest pinch-point.

It also proposes that the Government fund and delivers a scaled-back, cost-effective Euston Station with a simple functional design that could be delivered ahead of the wider regeneration ambition for the area.

HSRG is advocating for a six platform design, with the option for future expansion retained.

Under present plans, Euston looks set to be delivered many years after the opening of HS2, with trains terminating at Old Oak Common station in North London.

The group estimates that the cost of delivering at both ends of the line could be reduced by 35%, unlocking potential savings of £3bn – £4bn compared to previous estimates.

HSRG estimates that a concession let for a London–Birmingham & Crewe railway line would generate between £7.5bn – £10bn, a significant return for taxpayers.

But it warns that without Euston station and the connection from the West Midlands to Crewe, the value of a HS2 concession to HM Treasury would likely be halved.

Dyan Perry, chair of HSRG, said: “HS2 is at a crossroads. If delivered correctly, it will unlock national transport capacity, generate a multi-billion pound return to the Treasury, drive economic growth across the UK and enhance regional connectivity.

“However, if cut short, the Government risks wasting substantial investments to date, short-changing the national account and squandering HS2’s far reaching socio-economic benefits.

“HS2 has already stimulated significant investment in the UK’s supply chain, workforce skills, and infrastructure expertise to name just a few benefits.

“To secure the long-term advantages of a modern, high speed rail network, we strongly urge the Government to adopt our recommendations and take decisive action to restore financial control and accelerate delivery. By investing in our infrastructure now, we set the UK up for long term growth and economic success.”

 

Latest news

Three arrested in Blu-3 and Mace bribery probe

Serious fraud office swoops over alleged £3m bribes to former Mace associates
6 hours ago

Scotland’s most complex A9 dualling job heads to market

Market testing starts for £205m Pitlochry to Killiecrankie 6.4km upgrade
5 hours ago

Turkish contractor Limak to build new Luton Town stadium

Construction to start this summer on 25,000-seater venue
14 hours ago

Murphy on board at new £32m rail station

Construction to start next year at Golborne station
13 hours ago

HS2 engineers finish UK’s heaviest bridge slide early

A46 Kenilworth Bypass reopens 30 hours earlier than planned
12 hours ago

Bowmer + Kirkland to build £190m Oxford science scheme

Work to start at end of next month on 180,000 sq ft Fabrica scheme
20 hours ago

New BAM leisure centre pool springs a leak

Contractor investigating "technical issues" delaying new £36m green leisure centre
2 days ago

United Living lands £250m HyNet pipeline deal

Firm wins deal to design and build over 34km of pipework to collect CO2
20 hours ago

Hydrogen diggers get green light to use roads

JCB hails historic decision for advance of hydrogen-fuelled plant on sites
21 hours ago

Go-ahead for McAleer & Rushe Glasgow student job

£100m funding deal paves way for 591-bed student tower
21 hours ago

Fly-tippers to get their vehicles crushed

Drones will be used to identify cowboy construction waste operators
21 hours ago

Green light for £150m West End office revamp

Shaftesbury Avenue office retrofit retains 75% of original building
2 days ago

Morgan Sindall lands £20m Brunswick Wharf scheme in Bideford

North Devon waterside project will provide 100 flats
1 day ago

Former Keltbray managers jailed after corruption trial

Jail sentences following bribery probe on jobs including Battersea Power Station
2 days ago

Lidl pumps £500m into store and logistics expansion

Discounter plans 40 new stores this year as expansion ramps up
2 days ago

JJ Rhatigan UK profit jumps as turnover tops £150m

Irish contractor's expansion in England gathers pace
2 days ago

Driverless digger to be used on Taylor Woodrow site

Autonomous excavator to work at Manchester Airport after successful trial
2 days ago

MCS Build lands Basingstoke warehouse scheme

Construction starts this month after £26m funding deal
2 days ago

Leeds United unveil stadium revamp design

Club has still to set a timeframe for staged Elland Road upgrade
2 days ago

Bowmer & Kirkland boosts margins as profits surge to £69m

Revenue nudges up towards £1.3bn in year of expansion
3 days ago

Offshore construction starts on £4bn windfarm

Foundations for first of 95 turbines installed: Watch video
3 days ago

AECOM buys civils consultant Allen Gordon

Global giant acquires Scottish water and energy specialist
3 days ago

Plans in for £1bn Northern Gateway site in Manchester

Plan for 500-acre manufacturing and logistic park advance
3 days ago

RED wins £31m London Shoreditch student digs job

Two extra floors will be added to Willen House scheme
3 days ago

Deconstruct handed £12m Grenfell demolition

Firm maintaining building awarded job without bid race to speed process
3 days ago

Sizewell site workers get made to measure PPE

Bespoke fitting service on offer at new Bryson branch
3 days ago

Comment: Gateway is acting like a barricade

Contractors left banging their heads on an (unbuilt) brick wall
6 days ago

Final phase of £1.5bn Elephant and Castle revamp hits planning

Get Living submits revised plan for 500 homes and 450-bed student block
7 days ago

Ealing backs final phase of £1.3bn estate rebuild

Friary Park estate rebuild in Acton reaches end stage
6 days ago

Green light for scaled-down Nottingham student tower

Glasshouse Street scheme will deliver 247 student rooms
6 days ago

Contractor services